View/Open - Repository Home

UNIVERSITY OF NAIROBI
USE OF GIS TO DEPICT POWER INTERRUPTIONS
CASE STUDY: NAIROBI COUNTY
AKOTH RUZUNA
F19/3911/2009
A project report submitted to the Department of Geospatial and Space Technology in
partial fulfillment of the requirements for the award of the degree of:
Bachelor of Science in Geospatial Engineering
APRIL 2014
0
Abstract
This project tries to improve and add to the communication problem between the Kenya
Power and Lighting Company and its consumers by providing an alternative method of
relaying power disruption information. This is an alternative method to the traditional
newspaper notices which do not clearly make consumers understand why only some
parts of the same locality fail to have power.
The project result is a web mapping application which displays the areas experiencing
power outages at a particular time. The system can be installed by the Kenya Power
and Lighting Company for easy updating of the power coverage and for checking the
efficiency of the power network in the area of study. The web mapping application can
be managed by personnel, equipped with the identity of the network that log on to it and
update as required. It also allows the persons viewing the page to share it with others in
other social networks. The system also allows for digital archiving previous power
disruptions from which areas frequently affected can be determined.
The web application is developed using Java script and Extensible Markup Language
(XML), the server based program is written in HTML and the databases are My
Structured Query Language (MySQL). The computer application is developed using
Java and also contains a MySQL database. The Web page is designed using HTML
and is connected to Google Maps using Google Maps Application Programming
Interface (API).
1
Acknowledgements
I would like to acknowledge and thank my supervisor Mr. D.N. Siriba for his support and
guidance throughout the duration of the project study.
I would also like to thank the Chief Manager of Operations and Management
department at the Kenya Power and Lighting Company for his hospitality, generosity
and readiness to assist whenever needed. My special thanks to Mr. M. Omondi of the
same department who not only availed the data but also helped translate it.
I would like to thank my family, my siblings Edgar and Eader, and most importantly my
mother, Ms. Amina Baraka for the sacrifices she has made to educate me.
I would like to thank my friend and classmate Justus Muhando for helping me design
the web page.
Finally I would like to thank my friends and classmates Justus Muhando and Rose
Njambi for their moral support and help as I did my project.
2
DEDICATION
I dedicate this report to my mother, Ms. Amina Baraka, Brother, Edgar and sister,
Eader.
3
TABLE OF CONTENTS
ABSTRACT………………………………………………………………………..……..i
ACKNOWLEDGEMENTS……………………………………………………………...ii
DEDICATION……………………………………………………………………………iii
TABLE OF CONTENTS..........................................................................................iv
LIST OF ABBREVIATIONS AND SYNONYMS……………………………………...v
CHAPTER 1: INTRODUCTION………………………………………………………..1
1.1
1.2
1.3
1.4
Background…………………………………………………………….……3
Problem statement…………………………………………………………..4
Objectives………………………………………………………………….....5
Organization of the report……………………………………………….…..5
CHAPTER 2: LITERATURE REVIEW………………………………………….……..6
2.1 Causes of power interruptions…………………………………………….….6
2.2 Definitions………………………………………………………………….…...6
2.2.1 Electricity generation ………………………………………….……...6
2.2.2 Electricity distribution network ……………………………….………6
2.2.3 Electricity power transmission ……………………………….………7
2.2.4 Electricity distribution……………………………………………….…7
2.3 Historical development in transmission and distribution of electricity….....8
2.4 Electricity generation and transmission……………………………….….….8
2.4.1 Electric power grid……………………………………………….…….9
2.4.2 Substations……………………………………………………….……9
2.4.3 Power Grid in Nairobi…………………………………………………9
2.5 Power Interruptions…………………………………………………………...12
CHAPTER 3: METHODOLOGY……………………………………………………...14
3.1 The study area……………………………………………………………….…14
4
3.2 Data sources and tools ……………………………………………………..14
3.2.1 Data sources…………………………………………………………14
3.2.2 Tools…………………………………………………………………..14
3.3 Overview of methodology…………………………………………………..15
3.4 User needs assessment……………………………………………………15
3.5 Data preparation…………………………………………………………….16
3.5.1 Description of the data……………………………………………...17
3.5.2 Manipulation of the data……………………………………………18
3.6 Data capture and editing…………………………………………………...19
3.6.1 Editing………………………………………………………………..19
3.6.2 Creation of Geodatabase…………………………………………...21
3.6.3 Creation of the web page…………………………………………..25
CHAPTER 4: RESULTS AND ANALYSIS……………………………………….27
4.1 Results………………………………………………………………………27
4.2 Analysis of results………………………………………………………….30
CHAPTER 5: CONCLUSIONS AND RECOMMENDATIONS………………….35
5.1 Conclusions …………………………………………………………………35
5.2 Recommendations………………………………………………………….35
REFERENCES……………………………………………………………………….37
5
LIST FIGURES
Figure 1: Diagram showing flow of power from the main station…………………….7
Figure 2: Diagram of transmission network…………………………………………….11
Figure 3: Map of Distribution network…………………………………………………..12
Figure 4: flow chart showing organization of project…………………………………..15
Figure 5: Map of the Grid Network………………………………………………………16
Figure 6: Flow chart showing voltage step down…………………………………………17
Figure 7: Reduced network………………………………………………………………18
Figure 8: A screen shot of geodatabase formation……………………………………22
Figure 9: Relationship creation………………………………………………………….23
Figure 10: Relationships created………………………………………………………..23
Figure 11: Query statements……………………………………………………………..24
Figure 12: Homepage…………………………………………………………………….25
Figure 13: HTML code…………………………………………………………………….25
Figure 14: JavaScript……………………………………………………………………..26
Figure 15: Icons……………………………………………………………………………27
Figure 16: Screen shot of station selection…………………………………………….28
Figure 17: Check box……………………………………………………………………..29
Figure 18: Querying……………………………………………………………………….29
Figure 19: map of power interruptions………………………………………………….32
Figure 20: Screenshot of power disruptions map……………………………………..33
Figure 21: Page sharing………………………………………………………………….34
6
LIST OF TABLES
Table 1: Attribute table for the feeders………………………………………………….20
Table 2: Attribute table for the primary substations……………………………………20
Table 3: A section of the attribute table for distribution lines…………………………21
Table 4: Field (state)………………………………………………………………………24
Table5: Access table status of power off……………………………………………….30
Table 6: ArcGIS status of power off……………………………………………………..31
7
LIST OF ABBREVIATIONS AND ACRONYMS
GIS- Geography Information Systems
HTML- Hyper text Markup Language
KPLC- Kenya Power and Lighting Company
KV- Kilo Volts
LV- Low Voltage
MySQL- My Structured Query Language
SQL- Structured Query Language
8
CHAPTER 1: INTRODUCTION
BACKGROUND
Every year the Kenya Power and Lighting Company invests a lot of time, money and
other resources maintaining and improving electricity network and its customer service
modalities. It is not possible, however to have a completely efficient network, thus power
outages are bound to happen. Given the harsh reality that there can be no way around
power interruptions, we are faced with the challenge of developing mechanisms that
can aid in smooth operations of our daily activities even when experiencing these
outages. We live in an information society where people tend to embrace the best
means possible of obtaining information that they need in their daily living with ease.
People want to accomplish tasks from the comfort of their couches. Business people
can communicate much easily by coming up with systems that reach their consumers
wherever they are. In Kenya today, a lot of projects are under way in a bid to achieve
the vision 2030. It is essential therefore that communication about any situation that can
stall any project be communicated earlier enough such as information on planned power
interruptions. This enables efficient planning in all areas of development. It is relevant to
devise a means of getting such information to the people as it comes up. Power
interruptions are spatial in nature since they occur in specified geographical locations at
a particular time. It is thus possible to integrate tools of GIS and the knowledge from the
discipline to depict information on power disruptions for use by the relevant stake
holders.
Electricity supply in Kenya has solely been the responsibility of the Kenya Power and
Lighting Company. The company organizes and carries out matters affecting power
supply on its own terms. There are instances where power interruption notices are given
out with an allowance of only one day. Some consumers may not be comfortable with
this idea but are not left with much choice. This not only makes it difficult for the
consumers but also affects the company itself in terms of efficiency. Power provision
can be explored using GIS to ease interaction between supplier (KPLC) and
consumers. KPLC is allowed by the laws of Kenya under rule 27 of the electric
rules(Constitution of Kenya Cap 314) to disrupt power supply to various regions of the
9
country from time to time to enable them carry out certain important duties which could
be as simple as maintenance. Given that KPLC serves the whole country, it is tasked
with the responsibility of ensuring that it can service every region as effectively and
efficiently as possible irrespective of geographical or any other challenges that it
encounters. Currently, the only means of communication to the consumers about power
interruptions is through the print media. This is done by putting out public notices on
newspapers with the obvious assumption that everyone eventually gets to be able to not
only access the information but also do so in good time. GIS can be used to show areas
that are scheduled to experience power outage. This will enable a lot of consumers to
access the information as soon as it is made available. Web GIS can be applied to
achieve this.
Electricity supply covers the whole country through a distribution network. There are
major stations with the highest voltages located at different points in the country. From
these there are subsequent step down stations that eventually service households. The
power lines to all areas form the distribution network and each power line is formally
referred to as a feeder. Feeders are of different voltages depending on how large the
region is that it serves. Most feeders are 66kv. These feeders are named or rather
coded to provide the linkage between them and the areas they cover. Up until know the
KPLC has been able to use GIS to digitize the network
GIS can be used to relate the power network to all areas that receive electric power
supply from KPLC. The relationship between the various power lines and power stations
can be shown as illustrated in Figure 1 above. Power is generated in small voltages but
is stepped up at the main station to very high voltages. These voltages are
subsequently carried by power lines t smaller substations. Other power lines pick up
transmission to much smaller stations until they get to the consumers. Figure 1 shows
this flow of power. In this case, Nairobi region is used as a case study. GIS is used to
analyze the power grid in the area and to establish how to link the various parts of the
network to the areas that they supply power to. This can go a long way in enhancing
maintenance protocols and customer services at the company as well as keeping
consumers informed.
10
STATEMENT OF THE PROBLEM
In Kenya, news about scheduled power interruptions is communicated to the consumers
in advance through notices in the newspapers. KPLC uploads these notices on to their
website so that people can access them. The obvious assumption is that everyone
eventually accesses the information in time. However, it is arguable that not every
consumer buys newspapers daily and therefore will definitely get the information.
Moreover, even for those who do, the information may not be timely. Some areas tend
to bear the brunt of these power outages more than others. The Kenya Power and
Lighting Company aims at efficient and timely communication with consumers on their
activities especially when it comes to power interruptions. Most consumers are often
caught off their guard when power is disabled in their areas because they did not
access the notices or by the time the notices came out they had already made plans
that are then bound to be affected. It is also possible that most consumers don’t check
for these notices even when they do have access to these notices. On the other hand, it
is indeed a fact that power interruptions cannot be avoided. It’s like the weather, we
cannot control it but we want to be ready anyway. The question therefore is whether
enough has been done to overcome the challenges brought about by the frequent
power interruptions and if whatever we have is adequate in dealing with the challenges.
Newspaper notices have worked over the years and still are but we can device other
modes of relaying this information to compliment them and ease communication
between supplier and consumers. This project seeks to use GIS to show the
relationship between the power grid network and the regions they supply power to while
at the same time indicating power outages in an area in advance.
Given the society today is in the information age most people obtain information they
need mostly from the Internet. Today, it is possible to locate one position online at any
point in time from the maps available. Social networks such as Facebook, Twitter, and
My space among others ensure that there is always a large magnitude of audience in
the Internet. This audience cuts across any divide. Using its website, Facebook and
Twitter accounts and other accounts in its domain, KPLC can share the web page on
power interruptions with its consumers in the shortest time possible and reach a much
larger number of people at the same time. In Kenya it is estimated that at least 93% of
11
the population are mobile phone subscribers (e-library 2012). Between the years 2011
and 2012 alone there was a 95% increase in Internet users in the country and the
number has increased drastically according to the Communications Commission of
Kenya. Kenya also has a 36.6% Internet penetration (Humanipo) which is higher than
the world’s average of 26.6%. This implies that use of Internet to communicate
information on power outages is bound to be more effective especially in Kenya. In one
twitter account alone, KPLC has close to 10000 followers and even more Facebook
friends. This would enable them to share information on power disruptions as soon as
they make the changes with more consumers in the shortest time possible. Against this
backdrop it is possible to come up with a web based page that depicts scheduled power
interruptions at any point in time using GIS.
When the print media avails the notices on power interruptions, it merely gives the
names of the places affected. This is done by listing. This does not give an idea of the
extent of the outage on a particular day. If this could however be depicted on a map
then it would be much easier to see the extent of the areas affected by power outages
and possibly raise questions why a very large area is without electricity in one day.
There is also the fact that the electricity network organization is arguably complicated in
its structuring. Electricity network in an area is called its power grid. The power grid of a
region consists of the transmission and distribution networks. Inside KPLC as a
company, the departments responsible for distribution and transmission are separate.
The distribution and transmission networks are not linked. The department that gives
out the names of areas that are scheduled to experience power interruptions is also
separate. Using GIS to create a linkage between these networks overlay it accurately
on the map of Nairobi and develop a web page for the same will enable the personnel in
charge to be able to tell just from the display on their screens whether the disruptions
are on the transmission end or the distribution end. This will also enable to check the
efficient flow of the electricity network and help device alternative routes for power lines.
In mapping all areas that are beneficiaries of the Kenya power and lighting company,
deducing geographically areas covered by the same power lines and incorporating the
time aspect, it is possible to have these scheduled power interruptions known to the
12
consumers early enough. This way, things like planning for events can be done
appropriately.
OBJECTIVES
Main Objective
1. To come up with a web based map of Nairobi that shows areas experiencing
power interruptions at a particular time.
Other objectives
1. Link between the transmission and distribution networks
2. To provide an alternative means of informing people about scheduled power
disruptions.
ORGANIZATION OF THE REPORT
This project is organized in five chapters. Chapter 1 contains the background
information related to power interruptions and electricity distribution, the problem
statement, the objectives of the study, and the organization of the report. Chapter two
contains the literature review which outlines the definitions, history, scope and
relevance of the study. It gives the advancements in electricity so far. In the third
chapter there is the methodology which gives a step by step account of tasks
undertaken to achieve the results. This entails data collection, creation of the database,
creation of relationships, showing on a map, model building and finally linking online.
Chapter four presents the results and the analysis of the results and chapter five gives
conclusions and recommendations in view of the obtained results.
CHAPTER 2: LITERATURE REVIEW
13
2.1 Causes of Power interruptions
There are various reasons why power interruptions may occur. These could be planned
or unplanned. In the case of planned power interruptions, they are usually necessary to
allow for important maintenance tasks to be undertaken on the network. Unplanned
power interruptions occur for diverse reasons, most of which are inevitable situations for
example, high winds, storms and lightning strikes, debris or vegetation hitting power
lines, animal life such as birds or possums, vandalism, pole top fires, overloads,
equipment failure, wiring or appliance faults on property, a fire or an accident(vehicle or
machinery) among others. This project focuses on planned power interruptions. Power
may be interrupted so as to undertake any of the following:
i.
Undertake upgrades or planned maintenance to the electricity network
ii.
Upgrade supply to existing or connect new customers
iii.
Replace one’s metering equipment or service line.
iv.
Safely complete vegetation maintenance.
2.2 Definition
Electricity generation is the process of generating electric power from other sources of
primary energy. The basic method of electricity generation is by the movement of a loop
of wire between magnetic poles (Michael Faraday, 1820s to 1830s). This is the first
process of electricity delivery to consumers. The electric power industry is responsible
for electricity transmission, distribution, storage and recovery of power. Electricity is
often generated at a power station by electromechanical generators driven by heat
engines. Power transformers are used to transmit electricity from the Central power
stations at high voltages with low loss.
Electricity distribution network is a regional grid that branches from a national grid to
deliver power to industrial commercial and domestic users. Electricity generation is
often done with electronic generators but can also be supplied by chemical sources
such as batteries or by other means from a wide variety of energy sources. Electric
power is generally supplied to businesses and homes by the electric power industry.
Electricity is usually sold by the Kilowatt hour which is the product of power in kilowatts
14
multiplied by the running time in hours. Electric utilities measure power using electricity
meters which keep a running total of the electric energy delivered to a customer.
Electricity power transmission is the bulk transfer of electrical energy from generating
power plants to electrical power substations located near demand centers. The
interconnection between transmission lines forms what is referred to as the
transmission network.
Electricity distribution on the other hand is the local wiring between the high voltage
substations and the customers. It is the final stage of delivery of electricity to the end
users. The distribution network system carries electricity from the transmission system
and delivers it to the consumers. The combination of the electricity transmission and
distribution networks is called the power grid (National grid). Electricity distribution
network often include medium voltage power lines, substations and pole mounted
transformers.
power station
transmiss
ion substation
transmiss
ion substation
primary
substation
secondar
y substation
CUSTOM
ER
CUSTOM
ER
primary
substation
secondar
y substation
CUSTOM
ER
CUSTOM
ER
secondar
y substation
CUSTOM
ER
CUSTOM
ER
primary
substation
secondar
y substation
CUSTOM
ER
CUSTOM
ER
secondar
y substation
CUSTOM
ER
CUSTOM
ER
primary
substation
secondar
y substation
CUSTOM
ER
CUSTOM
ER
secondar
y substation
CUSTOM
ER
CUSTOM
ER
secondar
y substation
CUSTOM
ER
CUSTOM
ER
Figure 1: Flow of power
15
2.3 HISTORICAL DEVELOPMENT IN TRANSMISSION AND DISTRIBUTION OF
ELECTRICITY
Initially, direct current (DC), were largely employed in the distribution process. At this
point in time, there was no way of changing DC voltages thus the loads, generation and
transmission was mostly done at the same voltages. This meant that low voltages were
used and this in turn required less insulation for safe distribution especially within
buildings. However, this resulted to great losses along the cables and to minimize these
losses thick cables and local generators were used. The generating plants had to be at
least within 2.4 km of the furthest customer to avoid expensive conductors.
Eventually, alternating current (AC) was introduced and it soon became the major mode
of transmission of power. In this scenario, power transformers that were installed at
power stations were used to raise the voltage from the generators, and the transformers
at local substations could be used to reduce voltage to supply loads. Increasing the
voltage, reduced the current in the transmission and distribution lines and hence the
size of the conductors and distribution losses (Hughes et al, 1993). Consequently, it
became economical to distribute power over long distances.
2.4 ELECTRICITY GENERATION AND TRANSMISSION
Electric power is normally generated at 11-25kv at a power station. It is the stepped up
to 400kv, 220kv or 132kv for transmission over long distances. This transmission
network is the connected to load centers (cities) through a sub transmission network of
lines at voltages of 33kv to 230kv. The lines end at substations where they are
subsequently stepped down to 25kv or less for distribution to customers.
Most transmission lines use high voltage to reduce power loss over long distances.
Power is either transmitted through overhead power lines or by underground
transmission. The latter has high costs and more operational limitations but is
sometimes preferred in urban and other sensitive areas. Overhead transmission voltage
levels are considered to be 110kv and above. Lower voltages of 66kv or 33kv are often
used at sub transmission levels. Voltages less than 33kv are used in distribution
16
(Oestergaard et al, 2001). Underground cables take up lesser right of way compared to
overhead power lines and have less visibility and are rarely affected by bad weather.
2.4.1 Electric power grid
A transmission grid is a network of power stations, transmission lines and substations. A
power station is an industrial facility responsible for the generation of electric power.
Substations are parts of an electrical grid that transform voltage from high to low or vice
versa among other electrical functions. Several substations may exist between the
consumers and the generating station. A substation may be owned and operated by an
electrical utility or by a large industrial or commercial customer. A substation can include
a transformer to change voltage levels between high transmission voltages and lower
distribution voltages.
2.4.2 Substations
These generally have protection, control, switching equipments and transformers. They
may be on the surface, in fenced enclosures, underground or located in special purpose
buildings. Substations may be described by their voltage class, applications within the
power system, method used to insulate the connections or by the style or materials of
the structures used. A transmission substation may have important distribution
functions.
A transmission substation connects two or more transmission lines. The most basic
scenario is where all transmission lines have the same voltage in which case the
substation consists of high voltage switches that allow lines to be connected or isolated
for fault clearance and/or maintenance. Transmission substations can cover large areas
of several acreages with multiple voltage levels. Examples of substations within Nairobi
include, Juja, Ruaraka, Dandora and Embakasi substations.
A distribution substation transfers power from the transmission system to the distribution
system of an area. It decreases voltage to a level that is appropriate for local
distribution. The input for a distribution substation is most likely to be two transmission
lines or sub transmission lines. Input voltage is usually 220kv or 132kv as is the
situation in Nairobi. The output is a number of feeders which are of 66kv in Nairobi
17
region. The feeders run along the streets mostly overhead (or sometimes underground
especially within the central business district). They also power the distribution
transformers near the customer premises. Distribution substations also isolate faults in
either transmission or distribution systems.
2.4.3 Power Grid in Nairobi
The national grid in Kenya is generally operated as an integral network linked by a
220kv and 132kv transmission network and there exists limited lengths of 66kv
transmission lines in use which are mostly referred to as the feeders. Nairobi region as
indicated in Figure 2 is covered by at least 16(set to rise) major transmission lines that
originate from various power stations located within and outside Nairobi i.e Kamburu,
Kiambere,
Juja,
Dandora,
Kindaruma and Nairobi North substations.
These
transmission lines run at a voltage of either 220kv or 132kv and supply to the four major
transmission substations: Juja, Dandora, Embakasi and Ruaraka. Sub transmission
lines running at a voltage of 66kv each pick up transmission from the substations to
primary substations which are relatively closer to the consumer locations and are more
in number compared to the transmission substations. There are at least 35 primary
substations spread all over the region and examples include Parklands, Ridgeways,
Kitsuru, Karen, Westlands etc. Primary substations step down the voltages to
distribution voltage (11kv). Distribution lines originate from these stations and supply
power to various secondary transmission substations from which switches and service
lines distribute to individual customers.
18
Figure 2: Diagram of Transmission network.
19
Figure 3 Map of distribution network
2.5 Power Interruptions
Power interruption is a short term or long term loss of power supply to an area. It occurs
for various reasons. These reasons can be planned or unplanned. Whichever the case,
restoration of power should be swift and fast. Planned power interruptions are
necessary to allow for essential maintenance to be done and sometimes to upgrade the
network. Often, customers are informed in advance by way of newspapers, radio or text
alerts. Unplanned power interruptions occur due to situations that are difficult to contain,
for example, adverse weather conditions like storms, fires or car accidents.
Accidental power failures usually occur because certain features of the network have
been tampered with by the bad weather or accidents. These include faults at power
stations, damage to electric transmission lines, substations, parts of the distribution
system, a short circuit or overloading of the electric mains. Power outage can be said to
be either brownout, transient or a blackout. A brownout is also referred to as sag. It is
20
the temporary drop in the voltage in an electrical supply. It causes lights to dim and
results to poor equipment performance. A blackout is the total loss of power supply to
an area and is severe. A transient is loss of power for just a few seconds or minutes
due to a temporary fault on a power line.
Under certain conditions, a network component may shut down and cause current
fluctuations in neighboring segments of the network resulting to cascading power failure
of a large section of the network and this could be a whole building or sometimes an
entire city or even the whole electrical grid. This in most cases is unavoidable (Dobson
et al, 2009). This project aims at showing how this does happen.
There is also what is referred to as rolling blackout (planned power interruptions). It is
intentionally engineered power shut down where delivery of electricity is stopped for
non-overlapping periods of time over different parts of the distribution region. They are,
in most instances safety precaution measures taken by the electrical company to avoid
total power blackout in the system. Rolling blackouts can be restricted to just a small
locality but can also cover an entire region. They are necessitated by insufficient
generation capacity or inadequate transmission infrastructure to deliver power.
21
CHAPTER 3: METHODOLOGY
3.1 The Study Area
The study area of this project is the Nairobi area which t lies within latitudes 1°10' S and
1°25' S and longitudes 36°40′E and 37°10E and occupies 696 square kilometers and is
both the political and administrative headquarters of Kenya. It is entirely urban and
bordered by Kiambu to the North, Thika to the West, Kajiado to the West and Machakos
to the South. The study area is extended past the Nairobi County but within the
proposed Nairobi Metropolitan area of Northern Kajiado.
3.2 Data sources and tools
3.2.1 Data sources
The Grid
A digitized network of the power grid in the study area was obtained from the Kenya
Power and Lighting Company. Shapefiles containing information on transmission and
distribution properties of the network were also obtained and these provided the basis
for the creation of the database.
3.2.2 Tools
a) .Hardware:

A computer with 500GB memory, 2GB of RAM, 2.13GHz speed.

A flash disk of capacity 2GB

A printer.
b).Software:

ArcGIS 10.1

Microsoft Office Access 2007
22
The softwares above were chosen for their various capabilities. ArcGIS for its wide
variety of mapping functions including its online connection and Microsoft office
access because of provision to create tabular relationships and query statements.
3.3 Overview of Methodology
This project was carried out in three phases. These are data collection, processing and
presentation of the results. Data was obtained from the department of operations and
management at the Kenya Power and Lighting Company. The data obtained was
processed using GIS software and Microsoft office applications. The current chapter
details the steps taken to achieve the objectives. This entails data identification,
manipulation and capturing.
Data collection
Data processing
Data preparation
Creation of table relationships
Web design
Results
Figure 4: Organization of project
3.4 User needs Assessment
Every company strives towards efficiency in the delivery of its services. The KPLC is
one such company. Currently, notices about scheduled power interruptions are relayed
through newspapers. The departments that deal with Information on scheduled power
interruptions and power distribution and transmission Network, work separately. A
webpage showing areas experiencing power interruptions will not only ease the
23
diffusion of this information but will also enable the creation of a single database for
both departments. The users will benefit from the system in that the grid is linked to the
region that is served by the company, therefore, the personnel in charge just logs onto
the system and disable power at a station, a line or a transformer and all the areas
attached to the same will be affected accordingly. For the consumers, it will be possible
for them to view this change as soon as it is made.
3.5 Data preparation
The data that was obtained for this project were shapefiles that contained information
on the various parts of the electric grid in the region. These shape files were saved in a
folder and loaded onto ArcGIS 10.1. The Figure 5 below shows the form of the data as it
was.
Figure 5: A map of the grid network
24
3.5.1 Description of the data
There are four major transmission stations. These are Juja, Ruaraka, Embakasi and
Dandora. These stations are supplied by transmission lines that carry 220kv of
electricity from the generating power stations. From the transmission substations, sub
transmission lines called feeders take up transmission at stepped down voltages of
66kv and supplies this to primary substations distributed throughout the area.
Distribution begins at these primary substations where power is further stepped down to
11kv and carried by distribution lines to secondary transmission stations commonly
referred to as transformers. From the transformers power is distributed to consumers by
service lines at much smaller voltages. The flow chart (Figure 6) below summarizes the
transmission and distribution network.
Transmission lines
Transmission substation
Feeders
66Kv
Primary substation
66Kv
66Kv
11Kv
Distribution lines
Secondary transmission stations
Service lines
Figure 6: Flow chart showing voltage step down.
25
3.5.2 Manipulation of the data
The network was reduced to a workable size for the project. This was done by following
one line from the main source up to the distribution end. Consequently, a small part of
the network was extracted and used for analysis as shown in Figure 7.
Figure 7: Reduced network
26
3.6 Data capture and editing
3.6.1 Editing
Attributes of the layers were edited so as to link the distribution network to the
transmission network (The network was such that the shapefiles of the transmission and
distribution were independent of each other). This was done considering the origin and
destination of the transmission lines, feeders and distribution lines. Attention was also
given to the unique identifiers of the stations and every line in the extracted network. It
was also of essence to note all the lines that supply power to given station and how
many that stem from that very station.
This was done for all the stations in the network. Ideally transmission lines (220Kv)
supply power to the transmission substations, but there are instances in the network
that they supply from other transmission substations to others. This also applied to
some feeders (66Kv) where instead of some of them taking up power from transmission
substations they instead originated from primary substations and supplied power to
other primary substations. In such instances the some records were transferred to one
attribute table to another to conform to the intended flow.
Transmission substations and primary substations had names which were unique to
them. In the case of transmission lines fields added to provide them with unique
identities.
All feeders(66Kv) supplying power to one station say, Steel Billets (see Table 1, 2 and
3) which is a primary substation, were given the same identifier in relation to Steel
Billets. A field was included in the attribute table for primary substations called, Name
10 in which the unique identifiers for all feeders (66Kv), supplying to Steel Billets was
recorded. In the attribute table for feeders (66Kv) the field that was used to identify all
those taking power to Steel Billets for instance was named Feeder 05. This identification
was done for all stations. The edited shapefiles were then saved as a project on their
own.
27
Table 1: Attribute table for the feeders.
The field named Feeder o5 shows that the feeders were given a common name if they
supply power to one station. Feeder 6, 7 and 8 are therefore all steel billets 66Kv
meaning they take power to Steel Billets primary substation.
Table 2: Attribute table for the primary substations.
The field named `Name 10’ was used to connect the station Steel Billets with the
feeders 6, 7 and 8 as they contained similar records.
28
Table 3: Attribute table for distribution lines (section).
The highlighted field was used to connect the distribution lines from Steel Billets with the
station Steel Billets.
3.6.2 Creation of Geodatabase
A folder was created for the geodatabase named power. A personal geodatabase was
then created in ArcGIS and all the shape files exported to it (see figure 8)
29
Figure 8: A screen shot of geodatabase formation.
Microsoft office access was then used to create database relationships between the
attribute tables of the shapefiles. This was done by establishing unique identifiers for
each line and station and connecting them by origin and destinations. These unique
identifiers are the primary keys which are used as foreign keys in the rest of the tables
(see Figure 9 and 10).
30
Figure 9: Relationship creation.
Primary Key
Foreign Key
Figure 10: Relationships created.
A field called state was added to each table that would be used to determine and show
that areas affected by that particular line or station was either on or off. The records in
the field give the two possibilities which are either on or off. In ArcGIS a series of ones
and zeroes were used. Ones to show that power is on and zero to show that power is
off as illustrated in Table 4.
31
Table 4: Field(state).
State
The ticks in the boxes imply that those feeders are switched on.
The next step was to write query statements for every table. An example is given in
Figure 11.
Figure 11: Query statements.
A graphic user interface for directly accessing the database and changing the state was
then created (see Figure 12)
32
Figure 12: Homepage.
3.6.3 Creation of the web page.
A code was written in HTML and another in Javascript. The database created was then
linked to it. The Web page’s domain name was made www.simoa.me.ke/power.html
Figure 13: HTML code
33
Figure 14: Java Script
34
CHAPTER 4: RESULTS AND ANALYSIS
4.1 Results
a). Performance of the Application
This system is designed with a homepage. The homepage is equipped with icons for
the various parts of the transmission and distribution network. These include, in
descending order, the transmission lines, the transmission substations, the feeders,
primary substations and the distribution lines. Each of these has its own icon (see
Figure 15).
Figure 15: Icons
Icons
When the user launches the application, the screen with the list of buttons described
above appears. The user can access any of them by simply clicking on it. If a certain
primary substation is supposed to be switched on for example, then the user will click
on the primary substations button.
When the user clicks on this button, another window appears on the screen (Figure 16).
This window consists of three other buttons, a drop box and a state box. The user will
use the drop box to scroll to the station of interest.
35
Figure 16: selecting a station.
A user will click on it and the status box will immediately indicate whether that station is
on or off at the time. In this case it is assumed that it was off so then the user activates
the state by clicking the state button and a tick appears to show that it is now on (Figure
17). When this happens, the user ought to click the save record button to save the
change made and then proceed to click the run query button which ultimately effects the
changes throughout the system. This implies that every other power line or station that
has its origin emanating from this one station is automatically switched on.
36
Figure 17: Check box
Before the query is effected , a small window appears that checks if one is sure to
proceed and if so then click yes and the process is complete (see Figure 18).
Figure 18: Querying
Run Query button
37
b). Analysis
The queries basically change zeroes to ones and vice versa. When a station is off then
the field called state contains zeroes only and the converse is true. In ArcGIS therefore,
when power is off the field, state is queried to show only those areas with zeroes only
and vice versa. In the figure below which is a table from access shows that all the
primary stations are switched off since all the boxes in the status field are unchecked.
Table 5: Power off
The table above corresponds to the attribute table in Table 6 whose status field
indicates zeroes for power being off.
38
Table 6: Power off in ArcGIS
Figure 19, below shows how the map appears when the one primary station, say, Steel
Billets, is the only station that is switched off. All secondary stations whose power origin
is Steel Billets are affected and thus disappear from the map face. In the same manner,
if a transmission station was to be switched off, the all primary stations, distribution lines
and secondary stations that originate from it will disappear from the map face. In the
web page however, the code was written such that those areas experiencing power
outage are the ones that appear on the map face.
39
Figure 19: Map of power interruption
Consequently this relationship was joined to the online database and thus these
changes could be made online using html and Javascript. Figure 20 is a screen shot of
the resultant web page. It indicates the layers for the various days affected and the map
of Nairobi as the base layer as opposed to the current situation where the information is
uploaded in form of pdf. Figure 21 a sharing button for Facebook has been included so
that the administrator of this page can share it with all Facebook friends.
40
Figure 20: Power interruptions map
41
Figure 21: Map with a share button
share button
42
CHAPTER 5: CONCLUSIONS AND RECOMMENDATIONS
5.1 Conclusions.
The aim of this project was to come up with a system that enables KPLC notify
consumers on scheduled power interruptions using GIS. The result would be a map
face showing areas experiencing power interruptions. This was done by establishing
connectors between different parts of the network in such a manner that these parts
would be interdependent. The interdependency enabled the writing of query statements
that would determine what appears on the map face-areas experiencing power outage.
The transmission and distribution network are independent of each other. The aim of
this project was to link the two networks to provide smooth and efficient flow of power in
any part of the network. This was done by creating a geodatabase that links all the
attributes of both networks I organized manner. This makes it easy to tell whether a
problem is being experienced on the transmission end or the distribution end. Also, the
geodatabase makes it easy to in co-operate other aspects of power distribution and
transmission in one database.
This project also aimed at giving the consumers and the KPLC a visual outlook of the
extent of power disruptions on a particular day instead of the usual place names alone.
With this given as a web page, sharing of this information is much easier and less
costly. Depicting of power interruptions on a map was also possible. With the
achievement of the objectives, it can be concluded that it is possible to communicate
information on scheduled power interruptions to consumers more graphically by using
mapping tools (GIS). In order to achieve this, the network must be clearly organized
hence the development of the geodatabase. The designed web page will also enables
storage of past power outage incidences and planned future outages.
5.2 Recommendations
The following recommendations arise from the study:

The system should be adopted to supplement the current notices in the
newspapers so that even without access to newspapers one can still check
online for information on scheduled power disruptions in the area of interest.
43

To reach out to as many consumers as possible KPLC can share the page
through as many social networks as possible.

From this project a real time application showing power availability in an area at a
particular time can be developed.

Using such database as created in this project, other aspects of power
transmission and distribution other than power interruptions can be included such
as public safety in relation to power, organize priority services etc.
44
REFERENCES
Power
Generation
and
Transmission,
EnerNoc
(2013-2014)
at
http://www.enernoc.com/our-resources
Burke, J., Power Distribution Engineering, Marcel Dekker In., 1994.
Kenya
Power(2014),
Power
Interruptions(2014)
at
http://www.kplc.co.ke/index.php?id=44
Electric
power
transmission
facts,
pg
4,
at
http://www.aep.com/about
transmission/docs/transmission facts.pdf
National council on Electricity policy, Electricity Transmission: a primer.pdf
Hughes Thomas P., Networks of power Electrification in Western Society 1880-1930,
the John Hopkins University Press, Baltimore.
HumanIPO (2011/2012) Kenya Records 95.63% Increase in Internet Use, (2011/2012)
at http://www.humanipo.com/news
Gabriel Demombynes, Aaron Thegeya, (2012) e-library, Kenya’s Mobile Revolution and
the
Promise
of
Mobile
savings:
Policy
Research
Working
Papers,
at
interruptions
(2014)
at
http://elibrary.worldbank.org/doi/book/101596/1813-9450-5988
Western
Power,
Common
Causes
of
Power
http://www.westernpower.com.au/customerservice/restoration
Dobson et al (2007). Complex Systems analysis of Series of Blackouts: Cascading
failure, Critical Points, and Self-organization. Chaos 17 2007.
Wikipedia, Power outage at http://en.m.wikipedia.org/wiki/power_outage
Kenya Law (2007), Energy Act Cap 314 Part 3-Electrical Energy (2007) at
http://www.kenyalaw.org:8181/kenyaex/actview.xql?actud=CAP30314/part_|||
Jacob Oestergaad et al, 2001 Energy Losses of Super Conducting Power Transmission Cables
in the Grid
45
Margaret Wahito (July 2012) 3
in 4
Kenyans
have a
Mobile
Phone at
www.capitalfm.co.ke/business
46