SWM POND DESIGN CALCULATIONS
DRAWDOWN TIME
Project Name: Milton Meadow and 1321387 Ontario INC.
Prepared by: R.K.
Municipality: City of Milton
Checked by: A.F.
Project No.: 10-334
Last Revised: 1-May-14
Date: 1-May-14
Pond S44
Detention Time Calculations
t = (0.66C2h1.5+2C3h0.5)/2.75Ao
(MOE Eq'n 4.11)
t= 345258
t= 95.9
drawdown time in seconds
drawdown time in hours
d= 0.11
A0= 0.0095
h= 0.945
diameter of the orifice (m)
cross-sectional area of the orifice (m2 )
maximum water elevation above orifice (m)
Drainage Area= 21.60
Qext det= 0.0246
ha (includes pond block area)
proposed extended detention release rate (m3/s)
Qtarget= 0.0238
based on target release rate (0.0011m3/s/ha) and 21.6ha drainage area
C2= 1927
slope coefficient from the area-depth linear regression
C3= 4040
intercept from the area-depth linear regression
Pond area-depth relationship:
Elevation
208.40
209.40
N.W.L.
Ext. Detention
Area
4040
5967
Depth
0.00
1.00
The drawdown time for Pond S44 is 95.9 hours (4 days)
Hickenbottom (Perforated Riser Pipe) Calculation
Pipe Diameter
Hole Diameter
Number of Holes
300
75
20
(mm)
(mm)
Hole Spacing
50
(mm)
Max. # of holes per row
# of rows required
Min. Perf. Pipe Length
7
3
0.43
(m)
Area Check:
Area of holes
Equivalent Diameter
88357
335
(mm2)
(mm)
Therefore, the perforated riser pipe does not control the extended detention release rate.
Provided Perf. Pipe Length
1
(m)
P:\Projects\10-334\Reports\FSR - Century Grove\1st Submission CG\Design\SWM\[Drawdown time calculation S44.xlsx]Pond S44
Urbantech Consulting, A Division of Leighton-Zec Ltd.
25 Royal Crest Court, Suite 201 Markham, Ontario L3R 9X4
TEL: 905.946.9461 FAX: 905.946.9595
www.urbantech.com