M.Tomisawa - Japan Hadron Facility (JHF) Accelerator Home Page

ATAC2004, March 5
KEK Masahito Tomizawa
1. MR scheme for 181MeV Linac
2. Tunnel and Buildings
3. Beam Transport from RCS to MR
4. Main Magnet and Power Supply
5. RF
6. Vacuum
7. Injection and 3GeV Dump
8. Slow Extraction
9. Fast Extraction and 50GeV Abort
10. Neutrino Facility
11. MR Schedule
181MeV linac
400MeV linac
Injection time
540ms à 120ms
RF frequency
3.34-3.44 à 1.67-1.72 MHz
Pulse bending magnet flat top
600ms à 120ms :pattern change
Injection kicker rise time
170ns à <300ns :no change
Injection kicker flat top
130ns à 900ns :longer PFN cable
Acceleration Pattern and Beam Intensity
180MeV Linac case
15batches/15bunches
slow extraction 30GeV
fast extraction 40GeV
0.7s
0.61s
1.9s
1.9s
0.87s
0.87s
0.61s
total 4.08s
beam current: f × 24µA
beam power: f × 0.73MW
total 3.38s
beam current: f × 29µA
beam power: f × 1.17MW
f: RCS beam intensity ratio between 181MeV/400MeV
beam loss caused by long injection time?
Beam Transport from RCS to MR
Pulse Bending Magnet
and power supply --> ready
rise/flat: 30ms/600ms,
rep. rate: 3.6s
L=1.5m, B=1.21T
DC magnets and power supply
-->ready
3 horizontal bend, 2 vertical bend
38 quadrupole
14 steering
pulse bending magnet
Collimator section
4.3m Down slope
Vacuum chambers -->ready
titanium
500W Collimators
6 horizontal, 6 vertical
L=1m, every 60o
MR injection point
Magnets
Bending Magnets (BM)
Quadrupole Magnets (QM)
Sextupole Magnets (SX)
Steering Magnets (ST)
60/97
60/216
24/72
124/186
•Flip-Flop coil for BM and data taking system
Harmonic coil for short QM and data taking system
have been made and tested by measuring BM and QM fields
•Mass measurements for BM and QM will soon start
Power Supply
Bending
Quadrupole
Sextupole
Steering
6/6
0/11
(completed next year)
3/3
186/186
Test of BM power supply (1-unit) by load of an R&D magnet
•Ripples (spec. ? 1×10-6 p-p)
DC 201A (flat bottom)
DC 2186A (40GeV flat top)
? 1×10-6@all components (50Hz -higher)
2.5×10-6@1200Hz
? 1×10-6@other components (50Hz-higher)
•Tracking error (spec. ?1×10-4)
40GeV pattern operation
? 0.9×10-4
--> More tuning will be performed for real condition
22kV/2kV transformer
RF
number of unit 6
Cavity
frequency double OK
cooling: direct water (gap 10mm)
core coating:
epoxy resin
#1 ready
#2 constructing (including cores)
#3 constructing (without cores)
Anode Power Supply
#1 ready
#2 constructing
Final Amplifier
#1 ready
#2, #3 constructing
Driver Amplifier
design based on CERN type
Vacuum
Outline
•Chambers: SUS316L
electrolytic polish (E-P), baking---> outgassing rate 1×10-8 Pa•m/s
vacuum pressure < 1×10-6 Pa
•Gasket:HELICOFLEX delta type /quick clamp chains
•Bellows: titanium with rf shield
•Ceramic break to cut current induced: connected to bellows/pump ports
Status
•BM chambers(96): 15 finish and 25 in process of
welding-assemble (transition and flanges)
•QM+SX+ST chambers(~430): 132 E-P, 42 baking, 98 ready
•bellows: 300/~420 ready
•Clamps: 290/~1700 ready, •gate valves: 18/18
•seals: 10/~2200, •ion pumps 20/~130, •pump port : under design
Test
effect of stray field of BM and QM on pumps
•Ion pump: slight decrease of pumping speed --> usable
•TMP: serious heating by eddy current of rotating fins
--> can not be pumped when BM and QM are operated
Injection
kickers (distributed type)
#: 7
rise/fall time 150ns/900ns
flat top 150ns (900ns)
60kV/6kA
power supply: almost completed
magnets: design finished
Septum magnets
SEPH normal type
pattern rise/flat 0.5s/0.64s
t/H/W/L(mm) B(T)/I(A)/turn
57/98/900×2
1.5/2.9k/40
SEPL opposite field type
cores:out vacuum
half sine operation 2.5ms width
t/H/W/L(mm) B(T)/I(A)/turn
8/120/700
0.56/53.5k/1
power supply: under construction
magnets
: under construction
3GeV Dump System
Extraction timing must be scheduled in advance
purpose: study of injection beam
kickers (lamped)
# 3
rise/top 1000ns/6000ns <-- 1000ns
B=0.1T, L=0.8m
magnets: soon completed
w/o vacuum chambers
power supply: utilize existing one
Septum magnets
•SEPL normal type, cores: out vacuum
(ready) t/H/W/L(mm) B(T)/I(A)/turn
14/101/180/726 0.54/3.35k/14
•SEPH
(ready)
normal type, cores: out vacuum
t/H/W/L(mm) B(T)/I(A)/turn
39/93/220/900×2 1.5/3.35k/36
•power supply series excitation
(ready) rise/top/fall(s) 0.5/0.16/0.5
àunder excitation test
to 3kW dump
SEPH
Slow Extraction
Bumps
ESS
Septum magnets
30GeV extraction @T=0
one more year to fix the design
bumps
smaller beam loss
thinner septum
wire
lower tension-->large shift by electric field
week for damage by electric discharge -----difficult!
ribbon high tension --> small shift by electric field
(AGS) strong for damage by electric discharge
large average mass--> large radiation
“Rutherford Scatterer” with low average mass density and w/o electric field
・hit particles are mainly scattered out,
nuclear reaction (radiation) rate is small
・makes low beam density area downstream
・wires with large spacing are available
wires bend (due to electric field) free
stray electric field free
feasibility check ----> MARS, GIANT simulation, R&D of ribbon ESS
scatterer
ribbon ESS
Fast Extraction and Abort
750W dump
•Fast extraction beam is bent inward
Abort beam is bent outward anytime during acceleration
àBipolar kickers and septum magnets
àSeptum magnets are pattern-operated
àKicker voltage over 30% of maximum can be pattern-operated
Lower energy, the voltage is set to 30%, a number of fired kickers are adjusted
• Capacity of abort dump is 750W
à Abort frequency is limited by MPS/PPS
• For abort at low energy, extraction efficiency is ~2/3
à Abort frequency at low energy is limited
Kickers for fast extraction and Abort
(will be constructed in FY2004)
Symmetric Blumlein PFN Circuit
Magnet (distributed type)
Number
6
Magnetic Field 1 kG
Rise-up Time < 1.1 µs
Flat-top Time > 4.3 µs
Core Material Ferrite
Aperture
100 x 100 mm2
Power Supply
Type Symmetric Blumlein PFN
bipolar operation
PFN Voltage
40 kV
PFN Current 8000 A
Switching Element IGBT
IGBT switching module
•Small-scaled model test for experimental proof
of bipolar kicker shows it works as expected.
•Test of IGBT switching module will start soon.
(Turn-on rise time/voltage/current 160ns/40kV/8kA)
Series # in module
Parallel #
48
3
Septum magnets for fast extraction and Abort
(will be constructed in FY2004)
t/H/W/L(mm)
SM11-22
7/71/80/875
SM30
30/98/120/1225
SM31
43/93/110/1660
SM32A,33A 62/101/140/1900
SM32E,33E 62/61/140/1900
Va cuu m Cha mb er
for Ab ort Be am
Va cuum C ham ber
for Circu latin g Be am
B(T)/I(A)/turn
0.43/6031/4
1.38/4484/48
1.66/4095/30
1.66/4447/30
1.66/4477/18
Vacuu m C ham ber
for Extra cted Beam
Curre nt fl ow di rectio n
SM11-22
SM30
SM32A
Preparation section
PQ1
PQ2A
PQ2B
PQ3B
PQ4A
P Q 5 PV2 P H 3
PQ3A
P D 1
1.92 deg. bend
PH2
PH1
PD2
1.92 deg. bend
PV1
PQ4B
A
ル
サブトンネ
室
電 気 ヤード
制御
電気
室
Neutrino Facility
Arc section
WC
出入管
理
UQ1
SM1
UQ2
UD2
電源棟
ST1
ST2
コンプレ
ッサー
室
タンク
冷凍
液体窒素
UD1
UQ3
機室
B
ル
サブトンネ
UV2
低温棟
UQ4
SM2
UH1
UQ5
保安林伐
採 エリア
UH2
ND1
UH3
輸送道
路
土盛
レベ T P
り上 面は ル + 9 .3 m
ニュー
T + 10
へ。
トリノ建屋P
. 8m保
離れ る
を 輸送道 存するた
路側
め法面発生
(
方 へ5
0202 向 m移 動
へ3
。
07小 林 ) 。
m、8間 道
隆
路から
建屋
壁面
伐採
よ 5m離
面積 り
れたと
計:0.
ころま
286
で 保安林
a
h
伐採 。
ST3 ST4
機械
ヤー
バッフ
ァタン
ク
カードル
置場
UV1
ド
NM1
5,800
l/
980 min (低 温
設備
l /min
( 磁石電源
)
)
Cさ
W当な広
適
Proton beam transport
•Preparation section (normal conducting magnets)
with collimators (750W)
• Arc section (combined function type
superconducting magnets )
• Final focusing (FF) section
(normal conducting magnets)
FF section
37 .5m
4%slop
e
4%slop
e
C
ネル
トン
サブ
電気室
電 源 ヤード
ND2
DQ2
DD1
DD2
DSH
DQ3 D Q 4
シ
ャ
ッ
タ
ー
DSV
DQ1
電源室
サブトンネル D
Horn1
DD3
Horn2
~4, 500l/ min( 磁石汚染 )
トンネル
空調
T 換
S 気
NM2
ヤード
冷却棟
放射化物保管室
Target
Station
130.0
20.0
130m
60.0
3.0
6.6
6.6
decay pipe
3.0
5.6
5.6
30.0
2.50
1.50
μピット1
2.50
3.50
3.50
1.50
3.00
4.00
1.50
3.5 7 . 0
2.00
02.
8.00
4.5
5.0 5.0
μピット
測定室
15.0
5.0
μピット2
280m
3.0
3.6 2 . 4
2.4 3.6
μ ピット 1
鉄置場
3.0
4.6
4.6
13.5
Construction group organization
• 3rd Phys. Div. IPNS,KEK
• Cryo. G., IPNS, KEK
• Cryo. Sci. C., KEK
• Rad. Sci. C., ARL, KEK
• Mech., Eng., C., ARL, KEK
• JAERI
• U.Tokyo
• Kyoto U.
25,000
µ-pit
Near detector
Neutrino Facility Technical Advisory Committee (ν-TAC)
Dec. 12-13, 2003
Final_NuTAC_Report.pdf
ν-TAC recommends
better interaction between the 50 GeV ring group and
the neutrino facility design group
MR Schedule
FY2004
Tunnel/Buildings/Utility
Field measurement
Installation
Machine commissioning
Beam commissioning
Injection/acceleration
Slow extraction
Fast extraction
FY2005
FY2006
FY2007
FY2008