UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New England Power Generators Association v. ISO New England Inc. ) ) ) ) Docket No. EL15-25-000 COMMENTS OF THE ELECTRIC POWER SUPPLY ASSOCIATION Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”), 18 C.F.R. § 385.212 (2012), the Electric Power Supply Association (“EPSA”)1 hereby comments on the December 3, 2014 complaint (“NEPGA Complaint”) submitted by the New England Power Generators Association (“NEPGA”) against ISO New England Inc. (“ISO-NE” or “the ISO”) in the above-captioned proceeding. NEPGA requests that FERC issue an order finding the ISO-NE Tariff provisions relating to the Peak Energy Rent (“PER”) Adjustment unjust and unreasonable, and directing the ISO to modify the Tariff provisions on PER Adjustments for the Capacity Commitment Periods 5 through 8 and eliminate the PER Adjustment for Capacity Commitment Period 9 and beyond. NEPGA requests action by the Commission in advance of the upcoming Forward Capacity Auction (“FCA”) for the 2018/2019 Capacity Commitment Period (“FCA 9”) in order to ensure certainty for market participants seeking to bid into FCA 9. EPSA supports 1 EPSA is the national trade association representing competitive power suppliers, including generators and marketers. These suppliers, who account for nearly 40 percent of the installed generating capacity in the United States, provide reliable and competitively priced electricity from environmentally responsible facilities serving global power markets. EPSA seeks to bring the benefits of competition to all power customers. The comments contained in this filing represent the position of EPSA as an organization, but not necessarily the views of any particular member with respect to any issue. 1 NEPGA’s complaint and encourages the Commission to grant the relief requested and order ISO-NE to amend its Tariff as discussed below. I. BACKGROUND On December 2, 2014, NEPGA filed the instant complaint requesting that the Commission order the ISO to amend its Tariff to adjust the strike price for the PER Adjustment impacting Capacity Commitment Periods 5 through 8 and eliminate the PER Adjustment altogether starting with Capacity Commitment Period 9. Under the current ISO-NE Tariff, the PER Adjustment, which was introduced as part of the ISO’s Locational Installed Capacity proposal in 2006, obligates capacity suppliers to rebate a portion of their capacity revenues based on the real-time energy prices. Initially, the PER Adjustment was designed to serve as a hedge for load against price spikes in the energy market and to help mitigate any incentives to create price spikes from economic or physical withholding by removing profits gained from a rise in energy prices above a pre-determined level. The PER Adjustment provides a rebate from capacity suppliers to load for the difference between the PER Strike Price and the real-time energy price on a rolling, twelve-month average basis. In October of this year, the Commission directed the ISO to increase the Reserve Constraint Penalty Factors (“RCPFs”) as part of a larger capacity market redesign effort.2 Such increased RCPFs will impact the real-time prices which factor into the determination of the PER Adjustments. As indicated above, the ISO is in the process of redesigning the Forward Capacity Market (“FCM”) and, as part of that redesign, is implementing new “Pay for Performance” rules that link a provider’s capacity revenues 2 ISO New England Inc., 149 FERC ¶ 61,009 at P 23 (2014). 2 directly to that providers’ performance during real-time reserve deficiencies. As part of the proceeding adopting the ISO-NE redesigns, including the Pay for Performance rules, both the ISO and the Commission noted that the PER Adjustment under the current market design and structure were outside the scope of the market redesign proceedings and should be considered in a separate proceeding. The ISO further noted that it initiated a stakeholder process to consider changes to the PER Adjustment. However, absent 60% or better stakeholder support, the ISO elected not to file its proposal to amend the PER Adjustment with the Commission. In light of the forthcoming FCA 9, the first auction that will operate under the redesigned FCM including the Pay for Performance obligation, NEPGA filed the instant complaint seeking relief from the unjust and unreasonable market rules in the ISO-NE Tariff. II. COMMENTS EPSA supports the NEPGA complaint and requests that the Commission issue an order granting the relief requested. EPSA agrees with NEPGA that the Tariff provisions on PER Adjustment are unjust and unreasonable and the Commission should direct the ISO to modify the PER Adjustment for Capacity Commitment Periods 5 through 8 to avoid unjust and unreasonable results and eliminate the PER Adjustment for Capacity Commitment Periods 9 and beyond due to the redesigns of the FCM in ISO-NE including the implementation of the Pay for Performance rules starting with FCA 9. 1. Commission Should Order ISO-NE to Adjust PER Strike Price for Capacity Commitment Periods 5 Through 8 3 EPSA agrees with NEPGA’s assertion that the PER Adjustment is unjust and unreasonable and will substantially and adversely impact capacity suppliers. In light of the increase in RCPFs ordered by the Commission this year, the ISO-NE Tariff provision on the PER Adjustment will lead to increased costs for capacity suppliers without a corresponding increase in benefits. As NEPGA points out, the Commission has a statutory duty to ensure just and reasonable rates which, under these circumstances, requires the Commission to balance the interests between suppliers and load under the PER Adjustment rules. NEPGA proposes that the Commission can restore the transacted outcome that existed between capacity suppliers and load in Capacity Commitment Periods 5 through 8 in light of the increased RCPFs and the impact that will have on the PER Adjustment, by mandating that the ISO implement the strike price for the PER Adjustment as it relates to the Capacity Commitment Periods 5 through 8. These are the Capacity Commitment Periods for which the FCA has already occurred, but the energy has not yet been called for or delivered. The Commission previously recognized the need to adjust the PER Strike Price in order to ensure just and reasonable rates and that the PER Adjustments function as intended.3 Similar to the actions the Commission has previously taken to ensure the rates remain just and reasonable, EPSA supports Commission action in these circumstances to order the ISO to adjust the strike price for the PER Adjustment for the Capacity Commitment Periods 5 through 8. Such remedial action by the ISO will mitigate the substantial impact on capacity suppliers from 3 ISO New England Inc., 134 FERC ¶ 61,128 at P 24 (2011). 4 increased RCPFs and ensure that rates under the PER Adjustment mechanism are returned to a level consistent with the original capacity sale. 2. Commission Should Order ISO-NE to Eliminate the PER Adjustment Mechanism/Rule for Capacity Commitment Period 9 and Beyond The Commission should grant NEPGA’s request and order ISO-NE to eliminate the PER Adjustment starting with the Capacity Commitment Period resulting from the upcoming FCA 9. ISO-NE has recognized that the implementation of a Pay for Performance obligation eliminates the need for a PER Adjustment, and has begun a stakeholder process to consider whether the PER Adjustment should be eliminated for FCA 10, recognizing the unjust and unreasonable impact that such a mechanism would have on future Capacity Commitment Periods in light of the redesigned FCM that includes the Pay for Performance obligations. As such, EPSA agrees with NEPGA’s assertion that it would be unjust and unreasonable to allow the PER Adjustment to persist through the FCA 9 and beyond. As NEPGA explains in its complaint, the Pay for Performance obligations replicate the purposes of the PER Adjustment by eliminating the potential gain from physical withholding and “all resources will be subject to a Capacity Performance Payment calculated using an administratively determined penalty rate … for both FCA 9 and FCA 10.”4 Therefore, the reasons supporting the elimination of the PER Adjustment for FCA 10 exist for FCA 9 and the Commission should require ISO-NE to eliminate the PER Adjustment for the upcoming FCA 9. Given the recent market redesigns and the duplicative impact of the Pay for Performance obligations, EPSA sees no reason why the PER Adjustment should be permitted to overstay its welcome and impact the prices in the FCA 9. 4 NEPGA Complaint at 25. 5 Therefore, EPSA supports NEPGA’s complaint and joins its request that the Commission order ISO-NE to revise its Tariff to eliminate the PER Adjustment in advance of the upcoming FCA and for all subsequent FCAs. III. CONCLUSION WHEREFORE, for the foregoing reasons, EPSA respectfully requests that the Commission consider EPSA’s comments in support of NEPGA’s complaint and requests that the Commission find the ISO- NE Tariff provisions on PER Adjustment unjust and unreasonable and issue an order directing the ISO to modify the PER Adjustment for Capacity Commitment Periods 5 through 8 to avoid unjust and unreasonable results and eliminate the PER Adjustment for Capacity Commitment Periods 9 and beyond in advance of the upcoming FCA 9. Respectfully submitted, _______________________________________ Nancy Bagot, Vice President of Regulatory Affairs Melissa Mitchell, Director of Regulatory Affairs and Counsel Electric Power Supply Association 1401 New York Avenue, NW, 12th Floor Washington, DC 20005 (202) 628-8200 Dated: December 22, 2014 6 CERTIFICATE OF SERVICE I hereby certify that I have served a copy of the comments via email upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., December 22, 2014. ________________________________ Nancy Bagot, VP of Regulatory Affairs 7
© Copyright 2024 ExpyDoc