South Carolina Department of Transportation Innovative Projects

South Carolina Department of Transportation
Design-Build Projects Section
January 16, 2015
Design-Build Projects In Development
I-26 REHABILITATION (MM 60-75) – NEWBERRY COUNTY
Project Description:
RFQ Date:
RFP Industry Review Date:
Final RFP Date:
Bid Opening:
Other Information:
Interstate resurfacing, cross-slope correction, and bridge jacking /
replacement.
December 11, 2014
February 2015 (Anticipated)
May 2015 (Anticipated)
August 2015 (Anticipated)
I-26 REHABILITATION (MM 89 - 101) – LEXINGTON / RICHLAND COUNTIES
Project Description:
Interstate resurfacing, cross-slope correction, and bridge jacking /
replacement.
RFQ Date:
April 2016 (Anticipated)
RFP Industry Review Date:
June 2016 (Anticipated)
Final RFP Date:
August 2016 (Anticipated)
Bid Opening:
November 2016 (Anticipated)
Other Information:
US 21 BRIDGE REPLACEMENT OVER HARBOR RIVER – BEAUFORT COUNTY
Project Description:
Replace the US 21 moveable bridge over Harbor River with a
fixed-span bridge.
RFQ Date:
June 2016 (Anticipated)
RFP Industry Review Date:
August 2016 (Anticipated)
Final RFP Date:
October 2016 (Anticipated)
Bid Opening:
January 2017 (Anticipated)
Other Information:
Page 1 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
PORT ACCESS ROAD FROM I-26 (EXIT 218) TO NEW PORT TERMINAL – CHARLESTON COUNTY
Project Description:
Modification of Exit 217 and Exit 218 on I-26 and the construction
of a new direct access roadway from I-26 to the new port terminal
on the former Charleston Naval Complex site.
RFQ Date:
Spring/Summer 2015 (Anticipated)
RFP Industry Review Date:
Fall 2015 (Anticipated)
Final RFP Date:
Winter 2016 (Anticipated)
Bid Opening:
Spring/Summer 2016 (Anticipated)
Other Information:
The Environmental Impact Statement can be viewed at
www.porteis.com. Project schedule is based on Port Authority
terminal opening date of December 31, 2019.
I-85 WIDENING
PHASE 1 FROM S-57 (GOSSETT ROAD) TO SC 105 (HYATT STREET) & PHASE 2 FROM SC 105 (HYATT
STREET) TO SC 18 (SHELBY HIGHWAY) – SPARTANBURG AND CHEROKEE COUNTIES
Project Description:
The project includes widening the interstate from 4
to 6 lanes for approximately 16 miles. Project includes improving
interchanges at SC 110, S‐11‐39, S‐11‐82, SC 18; replacing the
railroad crossing at mile marker 80.8 near exit 80; and raising the
S‐11‐131 bridge overpass. Removing local access along interstate
ramps and treatment of slip ramps will also be considered during
project.
RFQ Date:
January 2016 (Anticipated)
RFP Industry Review Date:
May 2016 (Anticipated)
Final RFP Date:
June 2016 (Anticipated)
Bid Opening:
September 2016 (Anticipated)
Other Information:
Phase one and two will be developed together and awarded as
one project.
Page 2 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
I-85 WIDENING
PHASE 3 FROM SC 18 (SHELBY HIGHWAY) TO US 29 (CHEROKEE STREET) – CHEROKEE COUNTY
Project Description:
The project includes widening the interstate from 4 to 6 lanes for
approximately 10 miles. Project includes improving interchanges
at S‐11‐83, SC 5/198, S‐11‐99, US 29, and potential replacement of
the railroad crossing at mile marker 101. Removing local access
along interstate ramps and treatment of slip ramps will also be
considered during project.
RFQ Date:
TBD
RFP Industry Review Date:
TBD
Final RFP Date:
TBD
Bid Opening:
TBD
Other Information:
Preliminary engineering and environmental document will be
developed concurrently with phase one and phase two. Phase
three will be developed and awarded as a design-build
construction project once construction funding is identified.
I-20 WIDENING FROM US 378 TO LONGS POND ROAD – LEXINGTON COUNTY
Project Description:
Widening of Interstate 20 from just west of US 378 to west of S204 (Longs Pond Road). Project also includes the
replacement/widening of the eastbound and westbound I-20
mainline bridges over Norfolk Southern Railroad.
RFQ Date:
January 29, 2015 (Anticipated)
RFP Industry Review Date:
July 2015 (Anticipated)
Final RFP Date:
October 2015 (Anticipated)
Bid Opening:
January 2016 (Anticipated)
Other Information:
Page 3 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
I-77 WIDENING FROM I-20 TO KILLIAN ROAD – RICHLAND COUNTY
Project Description:
Widening of Interstate 77 from Interstate 20 to S-52 (Killian Road)
and rehabilitation of the northbound and southbound lanes of
Interstate 77 from S-52 (Killian Road) to S-59 (Blythewood Road).
Project also includes the widening of I-77 northbound/southbound
bridges over I-20 mainline and CD, I-77 northbound/southbound bridges
over I-20 westbound ramp to I-77 southbound, I-77
northbound/southbound bridges over Windsor Lake
Boulevard, I-77 northbound/southbound bridges over Windsor
Lake and Jackson Creek, and I-77 northbound/southbound bridges
over Edgewater Drive and Little Jackson Creek.
RFQ Date:
October 23, 2014
RFP Industry Review Date:
July 2015 (Anticipated)
Final RFP Date:
October 2015 (Anticipated)
Bid Opening:
December 2015 (Anticipated)
Other Information:
Unless otherwise noted, all bid openings will be held at 10:00 AM on the date noted.
SCDOT Headquarters
955 Park Street, Room 306
Columbia, SC 29201
Page 4 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
Design-Build Projects Under Contract
FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE E” – ENGINEERING DISTRICT 4
(Project Pending Commission Approval – Not Under Contract)
Project Description:
Total of thirteen (13) bridge replacements
o S-12-77 over Fishing Creek – Chester County
o S-12-141 over Rocky Creek – Chester County
o SC 200 over Wateree Creek – Fairfield County
o SC 9 (EBL) over Catawba River – Chester/Lancaster County
o SC 200 over Cane Creek – Lancaster County
o S-46-22 over Steele Creek – York County
o S-46-64 over Allison Creek – York County
o S-46-347 over Stony Fork Creek – York County
o S-46-732 over Calabash Branch – York County
o I-85 (SBL & NBL) over Norfolk Southern Railroad – Cherokee
County
o S-11-41 over Peoples Creek – Cherokee County
o S-46-103 over Fishing Creek – York County
Design-Build Contractor:
United Infrastructure Group (Pending Commission Approval)
Award Amount:
$52,707,000 (Pending Commission Approval)
CEI Services:
TBD
Bid Summary Report:
United Infrastructure
Crowder Construction
Group
Company
Guaranteed Maximum Cost to Complete (A)
$52,707,000.00
$56,253,000.00
Construction Time in Calendar Days (b)
S-12-77 over Fishing Creek
S-12-141 over Rocky Creek
SC 200 over Wateree Creek
SC 9 (EBL) over Catawba River
SC 200 over Cane Creek
S-46-22 over Steele Creek
S-46-64 over Allison Creek
S-46-347 over Stony Fork Creek
S-46-732 over Calabash Branch
S-46-103 over Fishing Creek
I-85 over Norfolk Southern Railroad
S-11-41 over Peoples Creek
Construction Time Cost (B)
Total Adjusted Bid
245
232
242
434
237
320
205
149
154
269
475
167
240
220
220
440
200
220
140
125
120
240
525
115
$7,032,500.00
$59,739,500.00
$6,442,500.00
$62,695,500.00
Page 5 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
US 701 BRIDGE REPLACEMENT OVER GREAT PEE DEE RIVER – GEORGETOWN / HORRY COUNTIES
(Not Under Contract)
Project Description:
Total of three bridges including the crossing of the Great Pee Dee
River, Yauhannah Lake, and the Great Pee Dee overflow.
Design-Build Contractor:
PCL
Award Amount:
$47,543,200
CEI Services:
By SCDOT/Supplement staffing with Consultant
Bid Summary Report:
PCL
Lane
Carolina Bridge –
Flatiron
Cape Romain JV
Guaranteed Maximum
$47,543,200.00
$59,337,195.00
$60,755,000.00
$51,539,194.00
Cost to Complete (A)
Construction Time in
850
882
1128
689
Calendar Days
Total Cost for B
$3,400,000.00
$3,528,000.00
$4,512,000.00
$2,756,000.00
Total Bid (A+B) =
$50,943,200.00
$62,865,195.00
$65,267,000.00
$54,295,194.00
Quality Points
63.0
35.0
52.0
61.5
Quality Credit
3.15%
1.75%
2.60%
3.08%
Percentage
Quality Value
$1,497,610.80
$1,038,400.91
$1,579,630.00
$1,584,830.22
Total Adjusted Bid
$49,445,589.20
$61,826,794.09
$63,687,370.00
$52,710,363.78
I-85/385 SYSTEM INTERCHANGE – GREENVILLE COUNTY
Project Description:
Improvements to major system interchange to include ramps and
mainline.
Design-Build Contractor:
Flatiron Constructors, Inc. / Zachry Construction Corporation
Award Amount:
$231,116,087
CEI Services:
Infrastructure Consulting & Engineering, PLLC
Bid Summary Report:
Flatiron / Zachry
Fluor / Lane
Skanska
Guaranteed Maximum Cost
$231,116,087.00
$235,325,309.00
$253,909,000.00
to Complete (A)
Construction Time in
1035
880
1034
Calendar Days
Total Cost for B
$25,875,000.00
$22,000,000.00
$25,850,000.00
Total Bid (A+B) =
$256,991,087.00
$257,325,309.00
$279,759,000.00
Quality Points
30.5
22.5
49.0
Quality Credit Percentage
1.22%
0.90%
1.96%
Quality Value
$2,819,616.26
$2,117,927.78
$4,976,616.40
Total Adjusted Bid
$254,171,470.74
$255,207,381.22
$274,782,383.60
Page 6 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
SC 41 OVER WANDO RIVER – BERKELEY / CHARLESTON COUNTIES
Project Description:
Replace the SC 41 movable bridge over the Wando River with a
fixed span bridge.
Design-Build Contractor:
PCL/Carolina Bridge
Award Amount:
$30,400,000
CEI Services:
HDR, Inc.
Bid Summary Report:
Archer Western /
PCL / Carolina Bridge /
United / Banks /
Baker
Terracon / ICA
Cape Romain / ICE
Guaranteed Maximum Cost
$45,845,000
$30,400,000
$32,700,000
to Complete (A)
Quality Points
9.5
12.0
9.5
Quality Credit Percentage
1.90%
2.40%
1.90%
Quality Value
$871,055
$729,600
$621,300
Total Adjusted Bid
$44,973,945
$29,670,400
$32,078,700
I-95/US 301 INTERCHANGE
Project Description:
Improvements to the I-95/US 301 interchange and construction of
the US 301 Connector in Orangeburg County.
Design-Build Contractor:
McCarthy
Award Amount:
$30,925,000
CEI Services:
ICA, Inc.
Bid Summary Report:
McCarthy
Superior
United /
Lane / HDR
Improvement
Construction
Banks
/ CECS
Co. / Baker
Guaranteed Maximum
$30,925,000
$35,145,000
$35,950,125
$34,805,000
Cost to Complete (A)
Construction Time in
440
1000
900
838
Calendar Days
Total Cost for B
$3,300,000
$7,500,000
$6,750,000
$6,285,000
Total Bid (A+B) =
$34,225,000
$42,645,000
$42,700,125
$41,090,000
Quality Points
12
10
8
8
Quality Credit
3.60%
3.00%
2.40%
2.40%
Percentage
Quality Value
$1,113,300
$1,054,350
$862,803
$835,320
Total Adjusted Bid
$33,111,700
$41,590,650
$41,837,322
$40,254,680
Page 7 of 9
Items in RED indicate changes since last update
CR Jackson /
ICA
$34,091,000
595
$4,462,500
$38,553,500
12
3.60%
$1,227,276
$37,326,224
South Carolina Department of Transportation
Design-Build Projects Section
I-26 WIDENING/REHABILITATION – LEXINGTON/CALHOUN COUNTIES
Project Description:
Ten (10) miles of widening combined with ten (10) miles of
rehabilitation for a 20-mile total project length.
Design-Build Contractor:
Anderson Columbia / Boggs Joint Venture
Award Amount:
$75,750,000
CEI Services:
By SCDOT
Bid Summary Report:
McCarthy
Anderson Columbia /
United / Jackson JV
Improvement
Boggs JV
Guaranteed Maximum Cost
$78,659,000
$75,750,000
$81,300,000
to Complete (A)
Construction Time in
530
710
850
Calendar Days
Total Cost for B
$5,300,000
$7,100,000
$8,500,000
Total Bid (A+B) =
$83,959,000
$82,850,000
$89,800,000
Quality Points
24
21
21
Quality Credit Percentage
4.80%
4.20%
4.20%
Quality Value
$3,775,632
$3,181,500
$3,414,600
Total Adjusted Bid
$80,183,368
$79,668,500
$86,385,400
FEDERAL AID BRIDGE REPLACEMENTS PACKAGE “D” - ENGINEERING DISTRICT 6
Project Description:
Total of five (5) bridge replacements in Package “D”
o S-967 over Abbapoola Creek in Charleston County
o S-66 over Tributary to Calfpen Creek in Colleton County
o S-17 over Zig Zag Creek in Jasper County
o S-108 (two locations) over Cypress Creek in Jasper County
Design-Build Contractor:
United Contractors
Award Amount:
$9,554,500
CEI Services:
By SCDOT
FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE C” - ENGINEERING DISTRICTS 2 AND 4
Project Description:
Total of seven (7) bridge replacements in Package “C”
o SC Route 308 over Duncan Creek in Laurens County
o SC Route 72 over Cane Creek in Union County
o S-134 over Buffalo Creek in Union County
o S-279 over Fairforest Creek in Union County
o S-602 over Pinckney Creek in Union County
o S-816 over Wolf Creek in York County
o S-64 over McAlpine Creek in Lancaster County
Design-Build Contractor:
United Contractors
Award Amount:
$14,081,500
CEI Services:
By SCDOT
Page 8 of 9
Items in RED indicate changes since last update
South Carolina Department of Transportation
Design-Build Projects Section
FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE B” – ENGINEERING DISTRICT 4
Design-Build Procurement for this project was canceled on June 7, 2013.
FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE A” – ENGINEERING DISTRICTS 4 AND 5
Project Description:
Total of three (3) bridge replacements
o S-22 over Thompson Creek in Chesterfield County
o S-24 over Pawley’s Swamp in Horry County
o SC Route 41 over Marsh Creek in Marion County
Design-Build Contractor:
HRI Bridge
Award Amount:
$7,743,851
CEI Services:
By SCDOT
Page 9 of 9