South Carolina Department of Transportation Design-Build Projects Section January 16, 2015 Design-Build Projects In Development I-26 REHABILITATION (MM 60-75) – NEWBERRY COUNTY Project Description: RFQ Date: RFP Industry Review Date: Final RFP Date: Bid Opening: Other Information: Interstate resurfacing, cross-slope correction, and bridge jacking / replacement. December 11, 2014 February 2015 (Anticipated) May 2015 (Anticipated) August 2015 (Anticipated) I-26 REHABILITATION (MM 89 - 101) – LEXINGTON / RICHLAND COUNTIES Project Description: Interstate resurfacing, cross-slope correction, and bridge jacking / replacement. RFQ Date: April 2016 (Anticipated) RFP Industry Review Date: June 2016 (Anticipated) Final RFP Date: August 2016 (Anticipated) Bid Opening: November 2016 (Anticipated) Other Information: US 21 BRIDGE REPLACEMENT OVER HARBOR RIVER – BEAUFORT COUNTY Project Description: Replace the US 21 moveable bridge over Harbor River with a fixed-span bridge. RFQ Date: June 2016 (Anticipated) RFP Industry Review Date: August 2016 (Anticipated) Final RFP Date: October 2016 (Anticipated) Bid Opening: January 2017 (Anticipated) Other Information: Page 1 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section PORT ACCESS ROAD FROM I-26 (EXIT 218) TO NEW PORT TERMINAL – CHARLESTON COUNTY Project Description: Modification of Exit 217 and Exit 218 on I-26 and the construction of a new direct access roadway from I-26 to the new port terminal on the former Charleston Naval Complex site. RFQ Date: Spring/Summer 2015 (Anticipated) RFP Industry Review Date: Fall 2015 (Anticipated) Final RFP Date: Winter 2016 (Anticipated) Bid Opening: Spring/Summer 2016 (Anticipated) Other Information: The Environmental Impact Statement can be viewed at www.porteis.com. Project schedule is based on Port Authority terminal opening date of December 31, 2019. I-85 WIDENING PHASE 1 FROM S-57 (GOSSETT ROAD) TO SC 105 (HYATT STREET) & PHASE 2 FROM SC 105 (HYATT STREET) TO SC 18 (SHELBY HIGHWAY) – SPARTANBURG AND CHEROKEE COUNTIES Project Description: The project includes widening the interstate from 4 to 6 lanes for approximately 16 miles. Project includes improving interchanges at SC 110, S‐11‐39, S‐11‐82, SC 18; replacing the railroad crossing at mile marker 80.8 near exit 80; and raising the S‐11‐131 bridge overpass. Removing local access along interstate ramps and treatment of slip ramps will also be considered during project. RFQ Date: January 2016 (Anticipated) RFP Industry Review Date: May 2016 (Anticipated) Final RFP Date: June 2016 (Anticipated) Bid Opening: September 2016 (Anticipated) Other Information: Phase one and two will be developed together and awarded as one project. Page 2 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section I-85 WIDENING PHASE 3 FROM SC 18 (SHELBY HIGHWAY) TO US 29 (CHEROKEE STREET) – CHEROKEE COUNTY Project Description: The project includes widening the interstate from 4 to 6 lanes for approximately 10 miles. Project includes improving interchanges at S‐11‐83, SC 5/198, S‐11‐99, US 29, and potential replacement of the railroad crossing at mile marker 101. Removing local access along interstate ramps and treatment of slip ramps will also be considered during project. RFQ Date: TBD RFP Industry Review Date: TBD Final RFP Date: TBD Bid Opening: TBD Other Information: Preliminary engineering and environmental document will be developed concurrently with phase one and phase two. Phase three will be developed and awarded as a design-build construction project once construction funding is identified. I-20 WIDENING FROM US 378 TO LONGS POND ROAD – LEXINGTON COUNTY Project Description: Widening of Interstate 20 from just west of US 378 to west of S204 (Longs Pond Road). Project also includes the replacement/widening of the eastbound and westbound I-20 mainline bridges over Norfolk Southern Railroad. RFQ Date: January 29, 2015 (Anticipated) RFP Industry Review Date: July 2015 (Anticipated) Final RFP Date: October 2015 (Anticipated) Bid Opening: January 2016 (Anticipated) Other Information: Page 3 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section I-77 WIDENING FROM I-20 TO KILLIAN ROAD – RICHLAND COUNTY Project Description: Widening of Interstate 77 from Interstate 20 to S-52 (Killian Road) and rehabilitation of the northbound and southbound lanes of Interstate 77 from S-52 (Killian Road) to S-59 (Blythewood Road). Project also includes the widening of I-77 northbound/southbound bridges over I-20 mainline and CD, I-77 northbound/southbound bridges over I-20 westbound ramp to I-77 southbound, I-77 northbound/southbound bridges over Windsor Lake Boulevard, I-77 northbound/southbound bridges over Windsor Lake and Jackson Creek, and I-77 northbound/southbound bridges over Edgewater Drive and Little Jackson Creek. RFQ Date: October 23, 2014 RFP Industry Review Date: July 2015 (Anticipated) Final RFP Date: October 2015 (Anticipated) Bid Opening: December 2015 (Anticipated) Other Information: Unless otherwise noted, all bid openings will be held at 10:00 AM on the date noted. SCDOT Headquarters 955 Park Street, Room 306 Columbia, SC 29201 Page 4 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section Design-Build Projects Under Contract FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE E” – ENGINEERING DISTRICT 4 (Project Pending Commission Approval – Not Under Contract) Project Description: Total of thirteen (13) bridge replacements o S-12-77 over Fishing Creek – Chester County o S-12-141 over Rocky Creek – Chester County o SC 200 over Wateree Creek – Fairfield County o SC 9 (EBL) over Catawba River – Chester/Lancaster County o SC 200 over Cane Creek – Lancaster County o S-46-22 over Steele Creek – York County o S-46-64 over Allison Creek – York County o S-46-347 over Stony Fork Creek – York County o S-46-732 over Calabash Branch – York County o I-85 (SBL & NBL) over Norfolk Southern Railroad – Cherokee County o S-11-41 over Peoples Creek – Cherokee County o S-46-103 over Fishing Creek – York County Design-Build Contractor: United Infrastructure Group (Pending Commission Approval) Award Amount: $52,707,000 (Pending Commission Approval) CEI Services: TBD Bid Summary Report: United Infrastructure Crowder Construction Group Company Guaranteed Maximum Cost to Complete (A) $52,707,000.00 $56,253,000.00 Construction Time in Calendar Days (b) S-12-77 over Fishing Creek S-12-141 over Rocky Creek SC 200 over Wateree Creek SC 9 (EBL) over Catawba River SC 200 over Cane Creek S-46-22 over Steele Creek S-46-64 over Allison Creek S-46-347 over Stony Fork Creek S-46-732 over Calabash Branch S-46-103 over Fishing Creek I-85 over Norfolk Southern Railroad S-11-41 over Peoples Creek Construction Time Cost (B) Total Adjusted Bid 245 232 242 434 237 320 205 149 154 269 475 167 240 220 220 440 200 220 140 125 120 240 525 115 $7,032,500.00 $59,739,500.00 $6,442,500.00 $62,695,500.00 Page 5 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section US 701 BRIDGE REPLACEMENT OVER GREAT PEE DEE RIVER – GEORGETOWN / HORRY COUNTIES (Not Under Contract) Project Description: Total of three bridges including the crossing of the Great Pee Dee River, Yauhannah Lake, and the Great Pee Dee overflow. Design-Build Contractor: PCL Award Amount: $47,543,200 CEI Services: By SCDOT/Supplement staffing with Consultant Bid Summary Report: PCL Lane Carolina Bridge – Flatiron Cape Romain JV Guaranteed Maximum $47,543,200.00 $59,337,195.00 $60,755,000.00 $51,539,194.00 Cost to Complete (A) Construction Time in 850 882 1128 689 Calendar Days Total Cost for B $3,400,000.00 $3,528,000.00 $4,512,000.00 $2,756,000.00 Total Bid (A+B) = $50,943,200.00 $62,865,195.00 $65,267,000.00 $54,295,194.00 Quality Points 63.0 35.0 52.0 61.5 Quality Credit 3.15% 1.75% 2.60% 3.08% Percentage Quality Value $1,497,610.80 $1,038,400.91 $1,579,630.00 $1,584,830.22 Total Adjusted Bid $49,445,589.20 $61,826,794.09 $63,687,370.00 $52,710,363.78 I-85/385 SYSTEM INTERCHANGE – GREENVILLE COUNTY Project Description: Improvements to major system interchange to include ramps and mainline. Design-Build Contractor: Flatiron Constructors, Inc. / Zachry Construction Corporation Award Amount: $231,116,087 CEI Services: Infrastructure Consulting & Engineering, PLLC Bid Summary Report: Flatiron / Zachry Fluor / Lane Skanska Guaranteed Maximum Cost $231,116,087.00 $235,325,309.00 $253,909,000.00 to Complete (A) Construction Time in 1035 880 1034 Calendar Days Total Cost for B $25,875,000.00 $22,000,000.00 $25,850,000.00 Total Bid (A+B) = $256,991,087.00 $257,325,309.00 $279,759,000.00 Quality Points 30.5 22.5 49.0 Quality Credit Percentage 1.22% 0.90% 1.96% Quality Value $2,819,616.26 $2,117,927.78 $4,976,616.40 Total Adjusted Bid $254,171,470.74 $255,207,381.22 $274,782,383.60 Page 6 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section SC 41 OVER WANDO RIVER – BERKELEY / CHARLESTON COUNTIES Project Description: Replace the SC 41 movable bridge over the Wando River with a fixed span bridge. Design-Build Contractor: PCL/Carolina Bridge Award Amount: $30,400,000 CEI Services: HDR, Inc. Bid Summary Report: Archer Western / PCL / Carolina Bridge / United / Banks / Baker Terracon / ICA Cape Romain / ICE Guaranteed Maximum Cost $45,845,000 $30,400,000 $32,700,000 to Complete (A) Quality Points 9.5 12.0 9.5 Quality Credit Percentage 1.90% 2.40% 1.90% Quality Value $871,055 $729,600 $621,300 Total Adjusted Bid $44,973,945 $29,670,400 $32,078,700 I-95/US 301 INTERCHANGE Project Description: Improvements to the I-95/US 301 interchange and construction of the US 301 Connector in Orangeburg County. Design-Build Contractor: McCarthy Award Amount: $30,925,000 CEI Services: ICA, Inc. Bid Summary Report: McCarthy Superior United / Lane / HDR Improvement Construction Banks / CECS Co. / Baker Guaranteed Maximum $30,925,000 $35,145,000 $35,950,125 $34,805,000 Cost to Complete (A) Construction Time in 440 1000 900 838 Calendar Days Total Cost for B $3,300,000 $7,500,000 $6,750,000 $6,285,000 Total Bid (A+B) = $34,225,000 $42,645,000 $42,700,125 $41,090,000 Quality Points 12 10 8 8 Quality Credit 3.60% 3.00% 2.40% 2.40% Percentage Quality Value $1,113,300 $1,054,350 $862,803 $835,320 Total Adjusted Bid $33,111,700 $41,590,650 $41,837,322 $40,254,680 Page 7 of 9 Items in RED indicate changes since last update CR Jackson / ICA $34,091,000 595 $4,462,500 $38,553,500 12 3.60% $1,227,276 $37,326,224 South Carolina Department of Transportation Design-Build Projects Section I-26 WIDENING/REHABILITATION – LEXINGTON/CALHOUN COUNTIES Project Description: Ten (10) miles of widening combined with ten (10) miles of rehabilitation for a 20-mile total project length. Design-Build Contractor: Anderson Columbia / Boggs Joint Venture Award Amount: $75,750,000 CEI Services: By SCDOT Bid Summary Report: McCarthy Anderson Columbia / United / Jackson JV Improvement Boggs JV Guaranteed Maximum Cost $78,659,000 $75,750,000 $81,300,000 to Complete (A) Construction Time in 530 710 850 Calendar Days Total Cost for B $5,300,000 $7,100,000 $8,500,000 Total Bid (A+B) = $83,959,000 $82,850,000 $89,800,000 Quality Points 24 21 21 Quality Credit Percentage 4.80% 4.20% 4.20% Quality Value $3,775,632 $3,181,500 $3,414,600 Total Adjusted Bid $80,183,368 $79,668,500 $86,385,400 FEDERAL AID BRIDGE REPLACEMENTS PACKAGE “D” - ENGINEERING DISTRICT 6 Project Description: Total of five (5) bridge replacements in Package “D” o S-967 over Abbapoola Creek in Charleston County o S-66 over Tributary to Calfpen Creek in Colleton County o S-17 over Zig Zag Creek in Jasper County o S-108 (two locations) over Cypress Creek in Jasper County Design-Build Contractor: United Contractors Award Amount: $9,554,500 CEI Services: By SCDOT FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE C” - ENGINEERING DISTRICTS 2 AND 4 Project Description: Total of seven (7) bridge replacements in Package “C” o SC Route 308 over Duncan Creek in Laurens County o SC Route 72 over Cane Creek in Union County o S-134 over Buffalo Creek in Union County o S-279 over Fairforest Creek in Union County o S-602 over Pinckney Creek in Union County o S-816 over Wolf Creek in York County o S-64 over McAlpine Creek in Lancaster County Design-Build Contractor: United Contractors Award Amount: $14,081,500 CEI Services: By SCDOT Page 8 of 9 Items in RED indicate changes since last update South Carolina Department of Transportation Design-Build Projects Section FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE B” – ENGINEERING DISTRICT 4 Design-Build Procurement for this project was canceled on June 7, 2013. FEDERAL AID BRIDGE REPLACEMENTS “PACKAGE A” – ENGINEERING DISTRICTS 4 AND 5 Project Description: Total of three (3) bridge replacements o S-22 over Thompson Creek in Chesterfield County o S-24 over Pawley’s Swamp in Horry County o SC Route 41 over Marsh Creek in Marion County Design-Build Contractor: HRI Bridge Award Amount: $7,743,851 CEI Services: By SCDOT Page 9 of 9 Items in RED indicate changes since last update
© Copyright 2024 ExpyDoc