Schedule2 BHP 2013 True-up 5-31

Page 1 of 10
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Black Hills Power, Inc.
May 30, 2014
Schedule 2 - Interest on Under/(Over) Recovery:
1
2
3
4
5
6
Black Hills Power (BHP):
Authorized Revenue Requirement
2013 Collected Revenue
True-up Amount - Under/(Over) Recovery
Future Value Factor (1+i)^18
True-up Amount to be (Refunded)/Paid based on 2013 Actual Loads
7
8
9
10
11
12
Gillette:
Authorized Revenue Requirement
2013 Collected Revenue
True-up Amount - Under/(Over) Recovery
Future Value Factor (1+i)^18
True-up Amount to be (Refunded)/Paid based on 2013 Actual Loads
13
14
15
16
17
18
Cheyenne Light:
Authorized Revenue Requirement
2013 Collected Revenue
True-up Amount - Under/(Over) Recovery
Future Value Factor (1+i)^18
True-up Amount to be (Refunded)/Paid based on 2013 Actual Loads
19
20
21
22
23
24
Black Hills Wyoming:
Authorized Revenue Requirement
2013 Collected Revenue
True-up Amount - Under/(Over) Recovery
Future Value Factor (1+i)^18
True-up Amount to be (Refunded)/Paid based on 2013 Actual Loads
25
26
27
28
29
30
Basin:
Authorized Revenue Requirement
2013 Collected Revenue
True-up Amount - Under/(Over) Recovery
Future Value Factor (1+i)^18
True-up Amount to be (Refunded)/Paid based on 2013 Actual Loads
30
31
33
34
35
36
WMPA:
Authorized Revenue Requirement
2013 Collected Revenue
True-up Amount - Under/(Over) Recovery
Future Value Factor (1+i)^18
True-up Amount to be (Refunded)/Paid based on 2013 Actual Loads
37
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Where: i = average interest rate as calculated below
38 Interest on Amount of Refunds or Surcharges Interest 35.19a for Current Year
39
40
Month
Year
41
January
2013
42
February
2013
43
March
2013
44
April
2013
45
May
2013
46
June
2013
47
July
2013
48
August
2013
49
September
2013
50
October
2013
51
November
2013
52
December
2013
53
January
2014
54
February
2014
55
March
2014
56
April
2014
57
Average Interest Rate
Interest 35.19a
for Month
0.28%
0.25%
0.28%
0.27%
0.28%
0.27%
0.28%
0.28%
0.27%
0.28%
0.27%
0.28%
0.28%
0.25%
0.28%
0.27%
0.2731%
1,660,052
1,776,051
(115,999)
1.05
(121,799)
130,888
143,655
(12,767)
1.05
(13,405)
601,062
642,135
(41,073)
1.05
(43,127)
260,384
276,779
(16,395)
1.05
(17,215)
1,034,689
1,381,542
(346,853)
1.05
(364,196)
66,747
87,491
(20,744)
1.05
(21,781)
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Black Hills Power, Inc.
May 30, 2014
Line
No.
1 BHP Schedule 2 Tariff:
2
3
4
5
6
7
8
9
10
True-up " Not Later than June 1 of each year, Transmission provider will calculate and post to its OASIS the
actual Summed Reactive billing Loads on the Transmission System during each month of the preceding calendar
year and the difference between that actual amount and the previously projected amount for the same calendar year.
If the Aggregate annual Reactive Revenue Requirement has changed during that calendar year pursuant to a Section
205 or 206 rate change accepted by FERC, the actual and differential load information will be broken out by the
period(s) before and after the effective date(s) of such change. From such calculations, the Transmission Provider
will calculate a true-up adjustment designed to reverse any under-collection or over-collection of the revenue
requirements identified in Section 2 and 3. The true-up adjustment and related calculations shall be posted to the
Transmission Provider's OASIS no later than June 1."
11
12
13
14
15
16
17
18
" Interest on any over-recovery of the revenue requirements shall be determined based on FERC's regulations
at 18 C.F.R. 35.19a. Interest on any under-recovery of the net revenue requirement shall be determined using
the interest rate equal to Black Hills Power's actual short-term debt costs capped at the applicable FERC refund
interest rate. In either case, the interest payable shall be calculated as follows. The interest rate will be
determined using the applicable rate averaged across the sixteen (16) months, January of the year prior through
the April of the year in which the true-up occurs. That interest rate will be applied, with quarterly compounding, to the
principal amount (i.e., the over or under recovery in the net revenue requirement) for the eighteen (18) months during
which that over or under recovery exists."
19
2013 Schedule 2 True-up Rates - June 1, 2014
20
21
22
23
24
25
26
27
28
29
Hourly ($/kW Hour)
Daily ($/kW Day)
On-Peak Off-Peak
On-Peak Off-Peak
BHP Charge
0.00037
0.00021 0.00590 0.00500
Gillette Charge
0.00003
0.00002 0.00050 0.00040
CLFP Charge
0.00013
0.00008 0.00210 0.00180
BHW Charge
0.00006
0.00003 0.00090 0.00080
Basin Charge
0.00023
0.00013 0.00370 0.00310
WMPA Charge
0.00001
0.00001 0.00020 0.00020
Total Charge
0.00083
0.00048 0.01330 0.01130
2013 Actual Load:
908,000
30
2013 Schedule 2 Rates - OASIS
31
32
33
34
35
36
37
38
39
40
Service
Service
Hourly ($/kW Hour)
Daily ($/kW Day)
On-Peak Off-Peak
On-Peak Off-Peak
BHP Charge
0.00034
0.00019 0.00540 0.00460
Gillette Charge
0.00003
0.00002 0.00040 0.00040
CLFP Charge
0.00012
0.00007 0.00190 0.00170
BHW Charge
0.00005
0.00003 0.00080 0.00070
Basin Charge
0.00026
0.00015 0.00420 0.00360
WMPA Charge
0.00002
0.00001 0.00030 0.00020
Total Charge
0.00082
0.00047 0.01300 0.01120
2013 Projected Load:
990,000
Weekly ($/kW Monthly ($/kW
Week)
Month)
0.03520
0.00280
0.01270
0.00550
0.02190
0.00140
0.07950
0.15240
0.01200
0.05520
0.02390
0.09500
0.00610
0.34460
Weekly ($/kW Monthly ($/kW
Week)
Month)
0.03220
0.00250
0.01170
0.00510
0.02510
0.00160
0.07820
0.13970
0.01100
0.05060
0.02190
0.10880
0.00670
0.33870
Yearly
($/kW
Year)
1.82830
0.14410
0.66200
0.28680
1.13950
0.07350
4.13420
Yearly
($/kW
Year)
1.67680
0.13220
0.60710
0.26300
1.30590
0.08090
4.06590
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power, Inc.
May 30, 2014
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
7
Total Revenue Requirement for Reactive Power
$1,660,052 Black Hills Power
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$1.8283
$ per kW - Year (Ln 11/ Ln 12)
10
$0.1524
$ per kW - Month (Ln 13 / 12)
11
$0.0352
$ per kW - Week (Ln 13 / 52)
12
13
$0.0050
$0.0059
$ per kW - day off peak (Ln 13 / 365)
14
15
$0.00021
$0.00037
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
$ per kW - day on peak (Ln 13 / 312)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
Black Hills Power, Inc.
May 30, 2014
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
7
Total Revenue Requirement for Reactive Power
$130,888 Gillette
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$0.1441
$ per kW - Year (Ln 11/ Ln 12)
10
$0.0120
$ per kW - Month (Ln 13 / 12)
11
$0.0028
$ per kW - Week (Ln 13 / 52)
12
13
$0.0004
$0.0005
$ per kW - day off peak (Ln 13 / 365)
14
15
$0.00002
$0.00003
$ per kW - day on peak (Ln 13 / 312)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
Black Hills Power, Inc.
May 30, 2014
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
7
Total Revenue Requirement for Reactive Power
$601,062 Cheyenne Light
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$0.6620
$ per kW - Year (Ln 11/ Ln 12)
10
$0.0552
$ per kW - Month (Ln 13 / 12)
11
$0.0127
$ per kW - Week (Ln 13 / 52)
12
13
$0.0018
$0.0021
$ per kW - day off peak (Ln 13 / 365)
14
15
$0.00008
$0.00013
$ per kW - day on peak (Ln 13 / 312)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
Black Hills Power, Inc.
May 30, 2014
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
7
Total Revenue Requirement for Reactive Power
$260,384 Black Hills Wyoming
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$0.2868
$ per kW - Year (Ln 11/ Ln 12)
10
$0.0239
$ per kW - Month (Ln 13 / 12)
11
$0.0055
$ per kW - Week (Ln 13 / 52)
12
13
$0.0008
$0.0009
$ per kW - day off peak (Ln 13 / 365)
14
15
$0.00003
$0.00006
$ per kW - day on peak (Ln 13 / 312)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power, Inc.
May 30, 2014
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
7
Total Revenue Requirement for Reactive Power
$1,034,689 Basin
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$1.1395
$ per kW - Year (Ln 11/ Ln 12)
10
$0.0950
$ per kW - Month (Ln 13 / 12)
11
$0.0219
$ per kW - Week (Ln 13 / 52)
12
13
$0.0031
$0.0037
$ per kW - day on peak (Ln 13 / 312)
14
15
$0.00013
$0.00023
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
$ per kW - day off peak (Ln 13 / 365)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
Black Hills Power, Inc.
May 30, 2014
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
7
Total Revenue Requirement for Reactive Power
$66,747 WMPA
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$0.0735
$ per kW - Year (Ln 11/ Ln 12)
10
$0.0061
$ per kW - Month (Ln 13 / 12)
11
$0.0014
$ per kW - Week (Ln 13 / 52)
12
13
$0.0002
$0.0002
$ per kW - day on peak (Ln 13 / 312)
14
15
$0.00001
$0.00001
$ per kW - day off peak (Ln 13 / 365)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Ancillary Services, Schedule No. 2 REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION SOURCE SERVICES
Line
No.
1
2
3
4
5
6
Black Hills Power, Inc.
May 30, 2014
Black Hills Power Revenue Requirement
Gillette Revenue Requirement
Cheyenne Light Revenue Requirement
Black Hills Wyoming Revenue Requirement
Basin Revenue Requirement
WMPA Revenue Requirement
$1,660,052
$130,888
$601,062
$260,384
$1,034,689
$66,747
7
Total Revenue Requirement for Reactive Power
$3,753,822 Total
8
Common Use AC Facility Transmission Load (2013 Actual Load)
908,000
Common Use System AC Facilities Ln.17
9
Annual Reactive Power Charges
$4.1342
$ per kW - Year (Ln 11/ Ln 12)
10
$0.3445
$ per kW - Month (Ln 13 / 12)
11
$0.0795
$ per kW - Week (Ln 13 / 52)
12
13
$0.0113
$0.0133
$ per kW - day off peak (Ln 13 / 365)
14
15
$0.00047
$0.00083
Settlement agreement January 14, 2011, paragraph 8
Settlement agreement January 14, 2011, paragraph 8
CLFP FERC application dated May 22, 2009 (see Page 2)
BHW FERC application dated August 25, 2009 (see Page 3)
Application accepted by FERC July 29, 2013
Application accepted by FERC July 29, 2013
$ per kW - day on peak (Ln 13 / 312)
365 days
6 days * 16 hours * 52 weeks
$ per kW - hour off peak (Ln 13 / 8760)
$ per kW - hour on peak (Ln 13 / 4992)
4992 hours
Common Use System AC Facilities
Black Hills Power, Inc.
May 30, 2014
Joint Tariff Rates
Common Use AC Facilities
2013 Projected Load Data
Line
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
January
February
March
April
May
June
July
August
September
October
November
December
BHP
TOTAL
LOAD
296
292
272
250
261
319
345
342
284
255
285
308
BASIN
TOTAL
LOAD
410
408
410
385
368
357
373
363
360
389
405
419
SD
WEST
LOAD
2
3
3
2
3
3
4
4
4
4
2
3
CITY OF
GILLETTE
LOAD
67
65
59
55
59
74
84
79
71
58
66
68
FIRM
POINT TO POINT
LOAD
165
160
160
100
100
100
100
100
100
100
100
100
CHEYENNE
LIGHT CUS
LOAD
80
80
80
140
140
140
140
140
140
140
140
140
TOTAL
COMMON USE
AC LOAD
1020
1008
984
932
931
993
1046
1028
959
946
998
1038
292
387
3
67
115
125
990
16
17
ANNUAL AVERAGE MW
18
19
20
2013 Actual Load Data
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
BHP
TOTAL
LOAD
BASIN
TOTAL
LOAD
SD
WEST
LOAD
CITY OF
GILLETTE
LOAD
FIRM
POINT TO POINT
LOAD
CHEYENNE
LIGHT CUS
LOAD
TOTAL
COMMON USE
AC LOAD
January
February
March
April
May
June
July
August
September
October
November
December
265
285
273
242
236
302
318
324
328
261
278
316
420
371
351
356
301
310
321
327
310
326
355
375
3
3
2
2
2
4
3
4
4
3
3
3
57
45
54
47
37
54
58
62
64
46
52
62
165
140
140
140
140
140
140
140
140
140
140
140
80
80
80
80
80
80
80
80
80
80
80
80
990
924
900
867
796
890
920
937
926
856
908
976
ANNUAL AVERAGE MW
286
344
3
53
142
80
908
37
38
39
40
41
42
2013 Projected vs Actual Load Data Difference
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
January
February
March
April
May
June
July
August
September
October
November
December
ANNUAL AVERAGE MW
BHP
TOTAL
LOAD
BASIN
TOTAL
LOAD
SD
WEST
LOAD
CITY OF
GILLETTE
LOAD
FIRM
POINT TO POINT
LOAD
CHEYENNE
LIGHT CUS
LOAD
TOTAL
COMMON USE
AC LOAD
31
7
-1
8
25
17
27
18
-44
-6
7
-8
-10
37
59
29
67
47
52
36
50
63
50
44
-1
0
1
0
1
-1
1
0
0
1
-1
0
10
20
5
8
22
20
26
17
7
12
14
6
0
20
20
-40
-40
-40
-40
-40
-40
-40
-40
-40
0
0
0
60
60
60
60
60
60
60
60
60
30
84
84
65
135
103
126
91
33
90
90
62
7
44
0
14
-27
45
83