Geocean Kalinda Shallow Water Pipelay Barge Specification

GEOCEAN KALINDA
Pipe Lay Barge
SHALLOW WATER
PIPE LAY BARGE
Classification: BV/BKI
Year built: 2002 – Conversion 2008
Flag: Indonesia
Dimensions:
Mooring system:
Pipelay system:
Deck area:
Crane:
86m x 27.5m
8-pt mooring
from 6” to 42”
30 ton tensioner
550 m2
250 ton
Marine
Expertise and Innovation
Quartier du Brégadan - ZA Technoparc - CS 60001 - 13711 Cassis Cedex - France
Tel: +33 (0) 442 18 02 18 - Fax: +33 (0) 442 18 02 20 - [email protected] - www.geocean.fr
GEOCEAN KALINDA
Pipe Lay Barge
PRINCIPAL DIMENSIONS
LOA
86m
BREADTH
27.5m
DEPTH MLD
5.5m
OPERATING DRAFT
1.6m minimum
DEADWEIGHT
3 800t
ANCHORS & MOORING SYSTEM
MOORING ARRANGEMENT
8-point mooring system
MOORING WINCHES
4 x double drum air winches
Integrated monitoring system (Tension & payout meter)
50t capacity (77t brake)
MOORING WIRES
8 x 1 200m x 38mm
ANCHORS
6 x 3.5t (+ 4 spares) + 2 x 5t Flipper delta anchors
POWER & SERVICES
DIESEL GENERATOR SET
6 x 350kW – CUMMINS – 415V/3Ph/50Hz
EMERGENCY GENERATOR SET
1 x 60kW – CUMMINS – 415V/3Ph/50Hz
COMPRESSOR
2 x 1 100m3/h (650cfm)
EQUIPMENT & PUMP
FUEL OIL
2 x 20m3/h
FRESH WATER
1 x 20m3/h
BALLAST WATER
1 x 100m3/h
TANK CAPACITY
FUEL OIL
234m3 (double wall tank)
FRESH WATER
388m3
BALLAST WATER
1 x 782 + 1 x 392m3 + 1 x 320m3
FACILITIES
CONTROL ROOM
1 x 40’ + 1 x 20’
OFFICES
4 x 20’
MESS ROOM
40 person
RESTROOM/SHOWERS
1 x 20’
HSE/FIRST AID OFFICE
2 x 20’
SAFETY
LIFE RAFTS
8 x 25 person
FIRE PUMP
1 x 100m3/h
EMERGENCY FIRE PUMP
1x
50m3/h
TELECOM
COMMUNICATION
1 x THURAYA
Quartier du Brégadan - ZA Technoparc - CS 60001 - 13711 Cassis Cedex - France
Tel: +33 (0) 442 18 02 18 - Fax: +33 (0) 442 18 02 20 - [email protected] - www.geocean.fr
GEOCEAN KALINDA
Pipe Lay Barge
DECK
DECK STRENGTH
10t/m2
DECK AREA
Approx. 550m2
DECK TUGGER WINCHES
1 x 10t + 1 x 5t
PIPELAY
CAPACITY
From 6’’ to 42’’
TENSIONER
1 x 30t – SAS – 25m/min
A/R WINCH
1 x 30t – SAS – 25m/min (Fitted with 500m of 38mm diameter wire)
STINGER
15m fix + 24m ballasting with integrated monitoring system
(Load cells, depth, angle and subsea camera)
WORK STATIONS
6 work stations (Typ. 3 x welding, 1 x NDT/repair, 2 x field joint coating)
WELDING SYSTEM
Can accommodate manual, semi-automatic and fully automatic
DAVIT
6 x 25t
CRANE
MAIN CRANE
BOOM LENGTH
250t crawler
45m
Quartier du Brégadan - ZA Technoparc - CS 60001 - 13711 Cassis Cedex - France
Tel: +33 (0) 442 18 02 18 - Fax: +33 (0) 442 18 02 20 - [email protected] - www.geocean.fr
Shore Approach
Pipelay
Above Water Tie-In
Riser Installation
Quartier du Brégadan - ZA Technoparc - CS 60001 - 13711 Cassis Cedex - France
Tel: +33 (0) 442 18 02 18 - Fax: +33 (0) 442 18 02 20 - [email protected] - www.geocean.fr