Overview / appendix sample

ENERLYTICS
Kraftwerke | Invest - Essentials
February 5, 2014 | Q1-2014 Edition
project overview 1/4
>> new fossil power plants in Germany >100MW
last update: Feb 4, 2014
power plants (lignite)
gross
output
year of commissioning, phase
and probability of realization*
Profen
660 MW
2020 in planning
Mibrag
Process of approval is underway (19. April 2012) // first permissions are expected until the end of 2014 // planned start of construction: 2015 // still lack of investors
Niederaußem BoA 4/BoAplus, Bergheim
1100 MW
RWE
open
in planning
On 7. October 2011 RWE Power submitted a proposal to the Cologne district government to change the regional plan // District government started the process of changing the regional plan
Lausitz
2000 MW
Vattenfall
open
in planning
Decision not before 2018
power plants (hard coal)
gross
output
year of commissioning, phase
and probability of realization*
RDK 8, Karlsruhe
912 MW
2014 under construction
800 MW
800 MW
2014 under construction
2014 under construction
EnBW
On schedule // commercial operation starts 2014
Westfalen Block D & E (Gekko), Hamm-Uentrop
RWE and 23 municipality partners
Increase of costs and delays caused some displeasure // DEW managing director called it “money destruction machine” // RWE made some concessions which all partners accepted // commercial operation
starts May 2014 (Block E) and June (Block D)
Moorburg 1 & 2, Hamburg
820 MW
820 MW
Vattenfall
2014 under construction
2014 under construction
Technical problems caused delays // procedure of licensing the planned district heating network not completed yet // an alternative and likely scenario to the extension of the district heating network is a
further CCPP north of the river Elbe // Commissioning of Block B is expected to take place in the beginning 2014, Block A in mid 2014
Mannheim Block 9, Mannheim-Neckarau
911 MW
GKM
2015 under construction
Technical problems caused huge delays // Environmental group BUND takes legal action against the environmental approval // commissioning date likely to be from May 2013
Wilhelmshaven
800 MW
GDF SUEZ / BKW FMB
2014 trial operation
Technical problems caused delays (esp. T24 steel) // commissioning date likely to be from 2014
Datteln Block 4
1100 MW
E.ON
2016 under construction
Plan revision procedures encounter heavy resistance and the outcome still remains uncertain // // in view of the Trianel-ruling the City of Datteln remains optimistic // decision for Plan revision procedures in December 2013 // commercial operation likely not before 2016
probability of realization (best guess)
unlikely
possibly
© Enerlytics | www.enerlytics.de | [email protected]
probably
for sure
E01
ENERLYTICS
Kraftwerke | Invest - Essentials
February 5, 2014 | Q1-2014 Edition
project overview 2/4
>> new fossil power plants in Germany >100MW
last update: Feb 4, 2014
power plants (hard coal)
gross
output
year of commissioning, phase
and probability of realization*
Dow Chemical, Stade
900 MW
2018 in planning
800 MW
open
no information
900 MW
open
no information
Dow Chemical
EnBW withdrew from the project // Dow will continue on its own
Industriepark Brunsbüttel
GETEC Energie
Project has been put on hold
Lünen
STEAG
We believe that the project ist no longer being pursued or has been put on hold // project does not appear on a semiofficial list released by the BDEW in April 2013
Herne
750 MW
STEAG
open
no information
We believe that the project ist no longer being pursued or has been put on hold // project does not appear on a semiofficial list released by the BDEW in April 2013
Stade
1100 MW
E.ON
open
in planning
Process of approval is underway (19. April 2012) // Project has been put on hold
power plants (natural gas)
gross
output
year of commissioning, phase
and probability of realization*
Bremen
445 MW
2014 under construction
600 MW
2016 building decision
swb, Mainova, Bahn, TOBI, ovag
Financing had been secured // The foundation stone was laid in November 2011 // commissioning date 2014
Lausward, Düsseldorf
Stadtwerke Düsseldorf
Siemens will be the manufacturer // commissioning date likely to be from end 2016 // technical details will be announced at a later date // financing has been secured // natural gas will be supplied by
Statoil for 15 years
Niehl 3, Köln
RheinEnergie
450 MW
2016 building decision
300 MW
2016 in planning
Decision to build was made in September 2012 // maufacturer will be Alstom
Lichterfelde, Berlin
Vattenfall
Permissions are granted // maufacturer will be Iberdrola // GE will deliver gas-turbine // construction will begin in 2014 // commissioning date planned to be from 2016
Chemiepark Leverkusen
550 MW
Repower
2016 in planning
Process of approval is underway (19. April 2012) // delays due to uncertain economical and political conditions // beginning of construction planned to start from the end of 2013 // building time expected
to be 2,5 years
probability of realization (best guess)
unlikely
possibly
© Enerlytics | www.enerlytics.de | [email protected]
probably
for sure
E02
ENERLYTICS
Kraftwerke | Invest - Essentials
February 5, 2014 | Q1-2014 Edition
project overview 3/4
>> new fossil power plants in Germany >100MW
last update: Feb 4, 2014
power plants (natural gas)
gross
output
year of commissioning, phase
and probability of realization*
Chemiepark Uerdingen, Krefeld Uerdingen
1200 MW
2020 in planning
Trianel / Currenta und Partner
Investment decision depends on regulation, capacity markets and economic conditions - not before end of 2014 // beginning of construction deleayed for three years // about 50 investors expressed interest
to have a share in the plant // commissioning date planned to be from 2019/2020
Kiel
Stadtwerke Kiel
200 MW
2016 in Planung
500 MW
2017 in planning
20 gas-fired engines à 10 MW // replacement of an old coal fired power plant // perfomance audit until the middle of 2012
Wedel
Vattenfall
“Innovative” power plant with thermal store // replacement of an old power plant in Hamburg Wedel and an alternative to the planned extension of the district heating network as part of the new power
plant in Moorburg // perfomance audit not finished yet // final decision probably not before 2015 // we believe that the probability of realization is well possible due to broad public support
Marzahn, Berlin
Vattenfall
300 MW
2018 in planning
300 MW
2020 in planning
800 MW
2018 in planning
commissioning date planned to be 2018
Klingenberg, Berlin
Vattenfall
Process of approval is underway (19. April 2012) // commissioning date planned to be from 2020
Haiming, Burghausen
OMV Power International
Permissions are granted // Project is still active and alive // investment expectations cannot be fulfilled yet due to uncertain economical and political conditions // main milestones have been postboned //
decision to build has been postboned to 20105 // commissioning date planned to be between 2017 and 2019
Oberrhein, Karlsruhe
1200 MW
MiRO / Trianel
2020 in planning
Joint Power plant // could be a replacement of an old nucelar power plant (Philippsburg 2) // construction could start 2016 // commissioning date planned to be from 2020
Leipheim
1200 MW
Stadtwerke Ulm/Neu-Ulm
2019 in planning
A referendum decided to build a new power plant // final decision 2015 // beginning of construction could commence in 2015 // commissioning date planned to be from 2019
Mecklar-Marbach, Ludwigsau
1100 MW
Dong Energy
open
for sale
Process of approval is underway (19. April 2012) // Iberdrola withdrew from the project and sold it to Dong Energy // Meanwhile Dong Energy also withdrew from the project and is trying to sell it
Duisburg, Duisburg-Wanheim
600 MW
Stadtwerke Duisburg
open
in planning
Joint Power plant // replacement of an old coal fired power plant of Steag in Duisburg Walsum // decision has been postponed due to uncertain economical and political conditions
Chempark Marl
600 MW
Infracor
open
no information
Planning concept on the way from 2013 says the city of Marl // type of fuel unknown but probably not coal // many questions remain to be answered // no decision yet
Weiher, Quierschied
500 MW
STEAG
open
no information
Permissions are granted // replacement of an old coal fired power plant // gas-pipeline is currently being installed // no decision yet
probability of realization (best guess)
unlikely
possibly
© Enerlytics | www.enerlytics.de | [email protected]
probably
for sure
E03
ENERLYTICS
Kraftwerke | Invest - Essentials
February 5, 2014 | Q1-2014 Edition
project overview 4/4
>> new fossil power plants in Germany >100MW
last update: Feb 4, 2014
power plants (natural gas)
gross
output
year of commissioning, phase
and probability of realization*
RDK 6S, Karlsruhe
465 MW
open
no information
400 MW
open
no information
400 MW
open
no information
EnBW
Permissions are granted // repowering of block 6 (RDK 6S) // project has been postponed
Premnitz
EDF
Process of approval is underway (19. April 2012) // Alpiq withdrew from the project and sold it to EDF Deutschland
Sachsen-Anhalt, Calbe
GDF SUEZ Energie Deutschland
Process of approval is underway (19. April 2012) // no news for a long time // we believe that the project ist no longer being pursued or has been put on hold
Meppen
unkown (former NUON)
450 MW
open
no information
1300 MW
open
no information
500 MW
open
no information
800 MW
2018 no information
We believe that the project ist no longer being pursued or has been put on hold
Gersteinwerk, Werne
RWE Power
Process of approval is underway // Scoping Jan 2013 // final decision depends on economic conditions
Augsburg
PQ Energy / Blackstone
Process of approval is not underway yet // Scoping Jan 2013 // final decision depends on economic conditions
Schweinfurt
PQ Energy / Blackstone
Process of approval is not underway yet // final decision depends on economic conditions
Lubmin
Energiewerke Nord
1800 MW
open
no information
open
open
no information
Process of approval is underway
Herne
STEAG
Process of approval for a gas pipeline is underway // STEAG wants to keep an option for this locaion
probability of realization (best guess)
unlikely
possibly
probably
for sure
Note
All the information contained in this newsletter has been gathered with the greatest care. In spite of that, we do not take any liability for correct, complete and up-to-date content. Most information contained are based
on official communications from project developers, associations, national authorities and professional media. Sometimes we deviated with regard to project specific probabilities of realization and expected commissioning years (first year of commercial operation) which we determined in an expert-review under consideration of all current news, economic and political conditions (“best-guess”).
© Enerlytics | www.enerlytics.de | [email protected]
E04
ENERLYTICS
Kraftwerke | Invest - Essentials
February 5, 2014 | Q1-2014 Edition
power plants | under construction
>> new fossil power plants in Germany >100MW
Last Update: Feb 2014
Moorburg 1 & 2 (Vattenfall)
2x820 MW | 2014
Kiel
Wilhelmshaven (GDF SUEZ / BKW FMB)
800 MW | 2014
Schwerin
Hamburg
Bremen (swb et al)
445 MW | 2014
Bremen
Datteln 4 (E.ON)
1100 MW | 2016
Berlin
Potsdam
Hannover
Magdeburg
Westfalen Block D & E (RWE et al)
2x800 MW | 2014 / 2014
Lausward (SW Düsseldorf)
600 MW | 2016
Düsseldorf
Niehl 3 (RheinEnergie)
450 MW | 2016
Dresden
Erfurt
Wiesbaden
Mainz
Mannheim Block 9 (GKM)
911 MW | 2015
Saarbrücken
Capacity
RDK 8 (EnBW)
912 MW | 2014
100-500 MW
Stuttgart
500-1000 MW
>1000 MW
München
Fuel
Phase
Natural Gas
in planning
Hard Coal
under contruction
Lignite
© ENERLYTICS
Contact: Niels Schulz | [email protected]
Note
All the information contained in this newsletter has been gathered with the greatest care. In spite of that, we do not take any liability for correct, complete and up-to-date content. Most information contained are based
on official communications from project developers, associations, national authorities and professional media. Sometimes we deviated with regard to project specific probabilities of realization and expected commissioning years (first year of commercial operation) which we determined in an expert-review under consideration of all current news, economic and political conditions (“best-guess”).
KW Walsum 10, KW Lünen, KW Dow Stade, KW Hüerth Knapsack 2, KW Boxberg R, Neurath BoA 2 and 3, KW Lingen, HKW Hannover and GuD Irsching 4 have been removed because they went into operation.
© Enerlytics | www.enerlytics.de | [email protected]
E05
Kraftwerke | Invest - Essentials
ENERLYTICS
February 5, 2014 | Q1-2014 Edition
power plants | in planning
>> new fossil power plants in Germany >100MW
Last Update: Feb 2014
Stade (Dow Chemical)
900 MW | 2018
Kiel (Stadtwerke Kiel)
200 MW | 2016
Kiel
Wedel (Vattenfall)
300 MW | 2017
Hamburg
Schwerin
HKW Klingenberg (Vattenfall)
300 MW | 2020
Bremen
HKW Marzahn (Vattenfall)
300 MW | 2018
Premnitz (EDF)
400 MW | ??
Berlin
Potsdam
Hannover
Magdeburg
Chempiepark Uerdingen (Trianel / Currenta)
1200 MW | 2020
HKW Lichterfelde (Vattenfall)
300 MW | 2016
Düsseldorf
Chemiepark Leverkusen (Repower)
550 MW | 2016
Dresden
Erfurt
Profen (MIBRAG)
660 MW | 2020
Niederaußem BoA 4plus (RWE)
1100 MW | ??
Wiesbaden
Mainz
Saarbrücken
Capacity
100-500 MW
Haiming (OMV)
800 MW | 2018
Stuttgart
500-1000 MW
Oberrhein (MiRO/ Trianel)
1200 MW | 2020
>1000 MW
München
Fuel
Phase
Natural Gas
in planning
Hard Coal
under contruction
Leipheim (SW Ulm/Neu-Ulm)
1200 MW | 2019
Lignite
© ENERLYTICS
Contact: Niels Schulz | [email protected]
Note
All the information contained in this newsletter has been gathered with the greatest care. In spite of that, we do not take any liability for correct, complete and up-to-date content. Most information contained are based
on official communications from project developers, associations, national authorities and professional media. Sometimes we deviated with regard to project specific probabilities of realization and expected commissioning years (first year of commercial operation) which we determined in an expert-review under consideration of all current news, economic and political conditions (“best-guess”).
Some projects do not appear on this map either because we think they have a probability of realization below 10% or because they have been cancelled.
© Enerlytics | www.enerlytics.de | [email protected]
E06
Kraftwerke | Invest - Essentials
ENERLYTICS
February 5, 2014 | Q1-2014 Edition
power plants | overall view
>> new fossil power plants in Germany >100MW
Last Update: Feb 2014
Stade (Dow Chemical)
900 MW | 2018
Moorburg 1 & 2 (Vattenfall)
2x820 MW | 2014
Kiel (Stadtwerke Kiel)
200 MW | 2016
Kiel
Wilhelmshaven (GDF SUEZ / BKW FMB)
800 MW | 2014
Wedel (Vattenfall)
300 MW | 2017
Schwerin
Hamburg
HKW Klingenberg (Vattenfall)
300 MW | 2020
Bremen (swb et al)
445 MW | 2014
Bremen
Datteln 4 (E.ON)
1100 MW | 2016
HKW Marzahn (Vattenfall)
300 MW | 2018
Premnitz (EDF)
400 MW | ??
Berlin
Potsdam
Hannover
Magdeburg
Chempiepark Uerdingen (Trianel / Currenta)
1200 MW | 2020
HKW Lichterfelde (Vattenfall)
300 MW | 2016
Westfalen Block D & E (RWE et al)
2x800 MW | 2014 / 2014
Lausward (SW Düsseldorf)
600 MW | 2016
Düsseldorf
Chemiepark Leverkusen (Repower)
550 MW | 2016
Niehl 3 (RheinEnergie)
450 MW | 2016
Niederaußem BoA 4plus (RWE)
1100 MW | ??
Dresden
Erfurt
Profen (MIBRAG)
660 MW | 2020
Wiesbaden
Mainz
Mannheim Block 9 (GKM)
911 MW | 2015
Saarbrücken
Capacity
RDK 8 (EnBW)
912 MW | 2014
100-500 MW
Haiming (OMV)
800 MW | 2018
Stuttgart
500-1000 MW
Oberrhein (MiRO/ Trianel)
1200 MW | 2020
>1000 MW
München
Fuel
Phase
Natural Gas
in planning
Hard Coal
under contruction
Leipheim (SW Ulm/Neu-Ulm)
1200 MW | 2019
Lignite
© ENERLYTICS
Contact: Niels Schulz | [email protected]
Note
All the information contained in this newsletter has been gathered with the greatest care. In spite of that, we do not take any liability for correct, complete and up-to-date content. Most information contained are based
on official communications from project developers, associations, national authorities and professional media. Sometimes we deviated with regard to project specific probabilities of realization and expected commissioning years (first year of commercial operation) which we determined in an expert-review under consideration of all current news, economic and political conditions (“best-guess”).
Some projects do not appear on this map either because we think they have a probability of realization below 10% or because they have been cancelled.
© Enerlytics | www.enerlytics.de | [email protected]