PJM Upgrade Request Queue X4-036 250MW

PJM Upgrade Request
Queue X4-036
250MW
Braidwood
System Impact Study Report
March 2014
© PJM Interconnection 2014. All rights reserved.
1
PJMDOCS-#767311-v1-X4-036_SIS_Report.DOC
Preface
The intent of this System Impact Study is to determine a plan, with cost and construction
time estimates, for the Network Upgrades necessary to provide the Incremental Auction
Revenue Rights (IARRs) associated with the Upgrade Request as provided by the New
Service Customer pursuant to Section 7.8 of Schedule 1 of the Operating Agreement and
Part VI of the PJM Tariff.
In some instances, a New Service Customer with an associated Upgrade Request may not
be responsible for 100% of the identified Network Upgrade cost because other
transmission network uses exist. An estimate of the sharing of the Network Upgrade
costs will be provided.
© PJM Interconnection 2014. All rights reserved.
2
PJMDOCS-#767311-v1-X4-036_SIS_Report.DOC
Queue Position X4-036 250 MW Braidwood – Cook Upgrade Request
System Impact Study Report
General
The New Service Customer, Exelon Generation Company, LLC has requested evaluation
of the required Network Upgrades to support awarding to the New Service Customer
IARRs, in the amount of 250 MW, having specified a source location of Braidwood, and
the sink location as Cook.
Network Upgrades
Cost Summary
This Upgrade Request was studied in conjunction with other Upgrade Requests in order
to provide the least cost option for all requests. This study resulted in identifying the
following required reinforcements in order to grant the IARRs associated with the X4036 project.
Item
Limiting Constraint
17ROXANA138 KV STA17R1
n4102
2.4
n4103
2.4
n4112
0.2
ComEd
66 E FRN345 KV 11601
ComEd
7 STATE 138 KV STA17R1
NIPSCO limit – NIPSCO mitigation
required
-
**
77 MAZON138 KV 0108 2
ComEdNIPSCO
Tie
ComEd
Reconductor 10.2 miles of 138kV
line 0108 from Mazon to LaSalle to
achieve new ratings of 208/264/275
n4113
17.75
77 MAZON138 KV 1205 4
ComEd
n4114
9.75
86 DAVIS138 KV TR83CTS
86 DAVIS345 KV TR83CTP
945 CRET345 KV CRESTJ1
ComEd
Reconductor 5.7 miles of 138kV
line 1205 from Mazon to Dresden to
achieve new ratings of 292/321/433
Install 4th autotransformer at Davis
Creek
Install 4th autotransformer at Davis
Creek
NIPSCO limit – NIPSCO mitigation
required
-
**
IPL Limit – IPL mitigation required.
-
**
3
4
5
6
7
10
11
Replace 345kV bus tie 3-4 at
Braidwood.
Replace 345kV bus tie 14-15 at
Braidwood.
Replace station conductor on 345kV
line 11601 to achieve new ratings of
1660/1917/2488
20 BRAID345 KV 2003
2
9
Estimated
Cost ($M)
**
20 BRAID345 KV 2001
1
8
PJM Network
Upgrade Number
-
TO
ComEdNIPSCO
Tie
ComEd
Breed-Wheatland 345 kV
line l/o Rockport-Jefferson
765 kV line
ComEd
ComEdNIPSCO
Tie
AEP –
IPL Tie
Estimated mitigation
NIPSCO limit – NIPSCO mitigation
required
n4115
14.6
© PJM Interconnection 2014. All rights reserved.
3
PJMDOCS-#767311-v1-X4-036_SIS_Report.DOC
Item
PJM Network
Upgrade Number
-
Estimated
Cost ($M)
**
AMIL limit – AMIL mitigation
required
-
**
AMILAEP
AMIL limit – AMIL mitigation
required
-
**
AMIL
AMIL limit – AMIL mitigation
required
-
**
TO
AMIL
Estimated mitigation
AMIL limit – AMIL mitigation
required
12
Limiting Constraint
Brokaw-N Leroy 138 kV l/o
Clinton-Oreana-GooseCrk
345 kV
BUNSONV3345 KV EUGBUN1
AMIL
13
14
Bunsonville-Eugene 345 kV
l/o Casey-Breed 345 kV
15
BUNSONVILLESIDNEY34
5IP4501FLOCASEYBREED
345
Burnham-Munster 345 flo
Dumont-Wilton Center 765
ComEdNIPSCO
NIPSCO limit – NIPSCO mitigation
required
-
**
Burr Oak 345/138 XFMR
(flo) Burr Oak - Leesburg
345
NIPSCO
NIPSCO limit – NIPSCO mitigation
required
-
**
Crete - St John 345 flo
Burnham - Munster 345
ComEdNIPSCO
NIPSCO limit – NIPSCO mitigation
required
-
**
NIPSCO limit – NIPSCO mitigation
required
-
**
-
**
n4116
0.145
16
17
18
19
Crete-St Johns Tap 345 kV
l/o Dumont-Wilton Center
765 kV line
NIPSCO
NIPSCO limit – NIPSCO mitigation
required
20
DuneAcres-MicCty1 138kV
l/o WltnCntr-Dumont
765+Pwrtn 5/Joliet 7 (SPS)
ComEd
21
East Frankfort-Goodings
Grove (11602) 345 kV line
Upgrade station conductor at East
Frankfort and Goodings Grove
EUGENE 345 KV EUGBUN1
AEPAMIL
AMIL limit – AMIL mitigation
required
-
**
EUGENE 345 KV EUGCAY1
Holland-Neoga 345 l/o
Newton-Casey 345
MICHIGA2138 KV LAPMIC1
Michigan City-Laporte
138kV (flo) Wilton Center
765kV
AEP-DEI
DEI Limit – DEI mitigation required
-
**
AMIL
AMIL limit – AMIL mitigation
required
NIPSCO limit – NIPSCO mitigation
required
NIPSCO limit – NIPSCO mitigation
required
-
**
-
**
-
**
NEWCARLI138 KV NEWTRA1
AEPNIPSCO
n4109
0.004
22
23
24
25
26
NIPSCOAEP
NIPSCOAEP
27
AMIL
28
Prairie State-W Mt Vernon
345 kV l/o St FrancisLutesville 345 kV
AMIL
29
PrairieState_WestMtVermon
_FLO_CoffeenRoxford345
Sag study required
if normal rating needs fixed, rebuild
required
AMIL limit – AMIL mitigation
required
AMIL limit – AMIL mitigation
required
1
-
**
-
**
© PJM Interconnection 2014. All rights reserved.
4
PJMDOCS-#767311-v1-X4-036_SIS_Report.DOC
Item
30
31
32
33
34
Limiting Constraint
Rising 345/138 XFMR 1
(flo) Clinton - Brokaw
345kV
Rising_XFMR_TR1_FLO_K
incaid_Latham_BlueMound3
45
Roxana-Praxair 138 kV l/o
Gary Ave-Sheffield 345 kV
Roxana-Praxair 138 kV l/o
Roxana-Mitchell Yard 138
kV
State Line-Wolf Lake 138 flo
Wilton Center-Dumont 765
Stillwell_Dumont345_flo_W
iltonCenter_Dumont765
PJM Network
Upgrade Number
-
Estimated
Cost ($M)
**
AMIL limit – AMIL mitigation
required
-
**
NIPSCO limit – NIPSCO mitigation
required
NIPSCO limit – NIPSCO mitigation
required
-
**
-
**
TO
AMIL
Estimated mitigation
AMIL limit – AMIL mitigation
required
AMIL
NIPSCO
NIPSCO
ComEdNIPSCO
Replace ComEd circuit breaker at
State Line raises the rating to 561.
n4118
1.2
NIPSCOAEP
Sag study required
if normal rating needs to be fixed,
rebuild required
n4111
0.0344
9
35
Total estimated costs: $25.7334M
Notes:
 Detailed Engineering & Construction Estimates TBD during Facility Study
 Estimates for time required to construct the reinforcements will be identified during
the Facilities Study
 The above estimates do not include 1) tax gross-up, 2) Real estate and permitting
costs.
 The total estimated cost listed above includes only the sag study cost for Items 27 and
35. Should the sag studies determine that further mitigation is needed, the costs will
increase up to the estimate provided for rebuilding the lines. This could add up to
another $10M on top of the total estimated costs listed above.
 ** - All MISO mitigations and cost estimates will be provided as a part of the
Facilities Study per PJM-MISO JOA
© PJM Interconnection 2014. All rights reserved.
5