OKLAHOMA DEPARTMENT OF TRANSPORTATION 2015 to 2022 Construction Work Plan SH-99 over Sand & Unnamed Creeks FFY 2021 Bridge & Approaches $ 3,500,000 FFY 2018 Right Of Way $ 224,169 FFY 2018 Utilities $ 112,085 $ 3,836,254 US-177 from SH-105 N. 5.01 mi. to Payne C/L FFY 2021 Widen, Resurface & Bridge $12,687,600 FFY 2017 Right Of Way $ 2,318,430 FFY 2017 Utilities $ 1,224,070 $16,230,100 Division 3 – Sheet 1 of 2 SH-105 over Headquarters Creek FFY 2016 Bridge & Approaches $ 1,930,838 Note: The depicted information is based on project data currently available. Project estimates and schedules will remain subject to further refinement as more definitive data becomes available. SH-18 over Dry Creek & Dry Creek Overflow FFY 2018 Bridge & Approaches $ 3,117,400 FFY 2015 Right Of Way $ 128,750 FFY 2015 Utilities $ 153,264 $ 3,399,414 SH-177 from 1 mi. S. of SH-40A N. 5 mi. to Jct. SH-105 FFY 2022 Right Of Way $ 3,000,000 FFY 2022 Utilities $ 2,000,000 $ 5,000,000 SH-66 over Bell Cow Creek FFY 2015 Bridge Rehabilitation $ 1,000,000 SH-18B over Quapaw Creek FFY 2016 Bridge Rehabilitation $ 1,091,800 SH-66B over Captain Creek FFY 2018 Bridge & Approaches FFY 2016 Right Of Way FFY 2016 Utilities SH-102 over Captain Creek FFY 2018 Bridge Rehabilitation SH-99 over Salt Creek FFY 2020 Bridge & Approaches FFY 2017 Right Of Way FFY 2017 Utilities $ 2,180,000 $ 231,081 $ 115,540 $ 2,526,621 US-270 over US-270B FFY 2016 Bridge Rehabilitation I-40 at MP 187 FFY 2019 Interchange FFY 2016 Right Of Way FFY 2016 Utilities $ 1,199,000 SH-66 from Oklahoma C/L E. 3.25 mi. to SH-102 FFY 2019 Widen & Resurface $ 8,111,600 FFY 2016 Right Of Way $ 462,552 FFY 2016 Utilities $ 231,276 $ 8,805,428 US-62 over Unnamed Creek FFY 2016 Bridge & Approaches $ 1,743,378 SH-102 from US-62 N. 2.1 mi. FFY 2016 Grade, Draining, Bridge & Surface $ 6,252,924 US-177 over Brush Creek FFY 2017 Bridge & Approaches $ 2,090,744 US-62/SH-102 Intersection FFY 2015 Grade, Drain & Surface $ 1,983,200 SH-3E over Rock Creek FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities SH-99A over Turkey Creek FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities US-62 from 0.65 mi. W. of Lincoln C/L E. 2.78 mi. FFY 2016 Grade, Draining, Bridge & Surface $10,388,374 I-40 over Unnamed Creek FFY 2021 Utilities $ 50,000 I-40 from Oklahoma C/L E. 8 mi. FFY 2021 Resurface $16,000,000 SH-102 from SH-9 N. 3.06 mi. FFY 2019 Widen & Resurface $16,600,000 $ 2,142,112 $ 1,190,062 $19,932,174 $ 3,502,715 $ 28,000 $ 64,300 $ 3,595,015 $ 1,060,000 SH-99A over E. Gar Creek FFY 2016 Bridge & Approaches $ 2,246,945 SH-48 over I-40 FFY 2017 Bridge & Approaches $ 4,488,782 $ 2,225,017 $ 40,000 $ 53,700 $ 2,318,717 $ 1,964,519 $ $ $ 150,000 100,000 250,000 SH-84 over N. Canadian River FFY 2017 Bridge & Approaches $ 4,843,352 SH-9 over Fish Creek FFY 2018 Bridge & Approaches $ 2,507,218 SH-48 over Little Wewoka Creek FFY 2022 Bridge & Approaches $ 2,000,000 FFY 2020 Right Of Way $ 175,000 FFY 2020 Utilities $ 100,000 $ 2,275,000 SH-9 from 36th Ave E. E. to 72nd Ave E. FFY 2015 Grade, Draining, Bridge & Surface $17,160,400 SH-9 over Wewoka Creek FFY 2015 Bridge & Approaches $ 6,150,100 SH-9 over Unnamed Creek FFY 2016 Bridge & Approaches $ 1,907,148 SH-9 from 8.58 mi. E. of SH-3E E. 1 mi. FFY 2019 Grade, Drain & Surface $ 1,988,800 SH-9 from 72nd Ave E. E. to 108th Ave E. FFY 2020 Grade, Draining, Bridge & Surface $12,000,000 FFY 2017 Right Of Way $ 713,432 FFY 2017 Utilities $ 356,715 $13,070,147 US-270 over Magnolia Creek FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities US-77 from 7.4 mi. N. of SH-39 N. 3.25 mi. FFY 2017 Grade, Draining, Bridge & Surface $16,456,076 US-77 from 4.05 mi. N. of SH-39 N. 2.5 mi. FFY 2015 Grade, Drain & Surface $ 8,609,300 SH-99 from 3.05 mi. S. of US-270 S. 8 mi. FFY 2019 Right Of Way $ 2,400,000 FFY 2019 Utilities $ 800,000 $ 3,200,000 $ 2,575,000 US-77 from SH-39 In Lexington N. 4.05 mi. FFY 2019 Grade, Draining & Surface $13,459,500 US-270 under Union Pacific RR FFY 2020 Grade, Drain & Surface $ 2,500,000 FFY 2017 Right Of Way $ 327,000 FFY 2017 Utilities $ 109,000 $ 2,936,000 US-270 over Unnamed Creek FFY 2022 Right Of Way FFY 2022 Utilities $ $ $ 150,000 100,000 250,000 SH-39 from 6.5 mi. E. of Cleveland C/L E. to US-177 FFY 2019 Widen, Resurface & Bridge $ 5,012,280 FFY 2021 Widen, Resurface & Bridge $ 4,370,200 FFY 2016 Right Of Way $ 1,375,668 FFY 2016 Utilities $ 1,540,654 $12,298,802 September 8, 2014 SH-99A over Snake Creek FFY 2017 Bridge Rehabilitation SH-48 over Unnamed Creek FFY 2022 Right Of Way FFY 2022 Utilities $ 9,500,000 $ 109,000 $ 54,500 $ 9,663,500 SH-39 from 7 mi. E. of US-77 E. 4.43 mi. FFY 2019 Widen, Resurface & Bridge $10,500,000 FFY 2016 Right Of Way $ 864,279 FFY 2016 Utilities $ 624,446 $11,988,725 800,000 50,000 850,000 US-75 from Seminole Ave. N. 2.87 mi. FFY 2020 Right Of Way $ 750,000 FFY 2020 Utilities $ 1,000,000 $ 1,750,000 100,000 50,000 150,000 SH-39 from 2 mi. E. of US-77 E. 5 mi. FFY 2016 Widen, Resurface & Bridge $ 9,658,516 $ $ $ US-75 from 7.07 mi. N. of Hughes C/l N. 4.23 mi. to N.of I-40 FFY 2021 Widen, Resurface and Bridge $10,500,000 FFY 2018 Right Of Way $ 840,636 FFY 2018 Utilities $ 1,120,849 $12,461,485 SH-9 from 108th Ave E. E. to 156th Ave E. FFY 2020 Right Of Way $ 2,250,000 FFY 2020 Utilities $ 750,000 $ 3,000,000 US-77 over Choteau Creek FFY 2016 Bridge & Approaches $ 2,532,552 SH-9 over Two Unnamed Creeks FFY 2016 Bridge & Approaches $ 3,009,145 Pending funding by others SH-9 over Little River FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities US-62 over Boley Creek FFY 2017 Bridge & Approaches SH-9 over Unnamed Creek FFY 2016 Bridge & Approaches I-44 from S. of 89th St. N. to .5 Mi. N. of 89th St. FFY 2021 Reconstruct-Added Lanes $ 6,500,000 FFY 2018 Right Of Way $ 224,169 FFY 2018 Utilities $ 784,594 $ 7,508,763 I-35 under Indian Hills Road FFY 2020 Bridge & Approaches FFY 2017 Right Of Way FFY 2017 Utilities SH-48 over Walnut & Little Walnut Creeks FFY 2017 Bridge & Approaches $ 3,869,106 I-40 from 8 mi. E. of Seminole C/L E. 5.86 mi. (EB only) FFY 2020 Resurface $ 5,850,000 $ 9,561,700 $ $ $ $ 1,319,277 $ 35,000 $ 20,000 $ 1,374,227 I-40 from 8 mi. E. of Seminole C/L E. 5.86 mi. (WB only) FFY 2019 Resurface $ 5,850,000 SH-9 from E. end of Pecan Creek Bridge E. 5.55 mi. FFY 2022 Grade, Drain & Surface $16,650,000 FFY 2019 Right Of Way $ 1,500,000 FFY 2019 Utilities $ 500,000 $18,650,000 SH-37 over Unnamed Creek FFY 2019 Right Of Way FFY 2019 Utilities $ 2,507,218 $ 91,237 $ 53,045 $ 2,651,500 SH-99A over Sand Creek FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities SH-102 from 3.06 mi. N. of SH-9 N. to 0.35 mi. S. of I-40 FFY 2015 Widen & Resurface $11,701,500 SH-9 from SH-102 E. 5.49 mi. FFY 2020 Grade, Drain & Surface FFY 2017 Right Of Way FFY 2017 Utilities $ 3,264,906 $ 2,544,000 $ 148,400 $ 5,957,306 I-40 over Unnamed Creek FFY 2022 Bridge & Approaches FFY 2019 Utilities Pending funding by others $ 7,149,064 $ 2,133,130 Pending funding by others US-62 from 0.05 mi. E. of SH-102 E. 0.46 mi. FFY 2015 Widen & Resurface $ 1,857,000 I-40 over County Road FFY 2017 Bridge & Approaches $ 1,535,700 $ 93,280 $ 230,974 $ 1,859,954 US-270 over Unnamed Creek FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities $ 3,511,108 $ 29,458 $ 74,675 $ 3,615,241 SH-99 over Salt & Sandy Creeks FFY 2017 Bridge & Approaches $ 9,005,866 SH-9A over Mud Creek FFY 2017 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities SH-56 over Jumper Creek FFY 2016 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities SH-39 over Unnamed Creek FFY 2022 Right Of Way FFY 2022 Utilities $ 3,170,990 $ 64,787 $ 37,904 $ 3,273,681 $ 3,227,814 $ 142,000 $ 44,275 $ 3,414,089 $ $ $ 150,000 100,000 250,000 $ 2,735,682 $ 44,000 $ 89,200 $ 2,868,882 US-270 over Wewoka Creek & Railroad FFY 2017 Bridge & Approaches $ 7,122,670 FFY 2015 Right Of Way $ 416,934 FFY 2015 Utilities $ 343,201 $ 7,882,805 FFY 2020 FFY 2018 FFY 2015 FFY 2015 US-270 from SH-270A E. to US-270B Grade, Drain & Surface $15,300,000 Bridge & Approaches $ 4,360,000 Right Of Way $ 1,951,253 Utilities $ 729,755 $22,341,008 US-270 under Union Pacific RR FFY 2021 Grade, Drain & Surface $ 2,000,000 FFY 2018 Right Of Way $ 168,127 FFY 2018 Utilities $ 112,085 $ 2,280,212 SH-31A over Unnamed Creek FFY 2020 Right Of Way FFY 2020 Utilities US-75 over Salt Creek FFY 2020 Bridge & Approaches FFY 2017 Right Of Way FFY 2017 Utilities $ $ $ 125,000 75,000 200,000 $ 1,423,900 $ 67,840 $ 228,218 $ 1,719,958 OKLAHOMA DEPARTMENT OF TRANSPORTATION 2015 to 2022 Construction Work Plan Division 3 – Sheet 2 of 2 SH-76 from SH-130 N. 3 mi. to SH-37 FFY 2022 Grade, Drain & Surface $17,964,900 FFY 2019 Right Of Way $ 2,056,604 FFY 2019 Utilities $ 514,151 $20,535,655 Pending funding by others I-35/SH-9 Interchange FFY 2022 Interchange FFY 2019 Right Of Way FFY 2019 Utilities $ 7,175,000 $10,283,019 $ 848,349 $18,306,368 SH-76 over N. Fork Walnut Creek FFY 2015 Bridge & Approaches $ 2,956,300 SH-76 over Walnut Creek FFY 2016 Grade, Draining, Bridge & Surface $ 5,394,625 SH-74B over Unnamed Creek FFY 2018 Bridge Rehabilitation $ I-35 from MM 104.5 to MM 105.5 & MM 98.5 to MM 99.5 FFY 2015 Cable Barrier $ 400,000 SH-74 over I-35 FFY 2018 Bridge Rehabilitation I-35 SB Ramp at SH-74 FFY 2016 Grade, Drain & Surface FFY 2015 Utilities Ladd Road over I-35 FFY 2018 Grade, Draining, Bridge & Surface FFY 2015 Right Of Way FFY 2015 Utilities $ 1,188,100 $ 1,407,598 $ 20,263 $ 1,427,861 I-35 from SH-59 N. 2.4 mi. FFY 2019 Resurface I-35 from 2.25 mi. N. of Garvin C/L N. 2.25 mi. FFY 2022 Resurface $ 6,750,000 $ 8,732,208 $ 51,000 $ 261,962 $ 9,045,170 I-35 from MM 75.97 to MM 79.43 FFY 2022 Resurface $10,400,000 US-77 over Owl Creek FFY 2015 Bridge & Approaches US-77 over Washita River FFY 2019 Bridge & Approaches FFY 2016 Right Of Way FFY 2016 Utilities 109,000 SH-39 from Grady C/L E. 1 mi. to SH-76 FFY 2022 Grade, Drain & Surface $ 2,400,000 FFY 2019 Right Of Way $ 211,480 FFY 2019 Utilities $ 158,610 $ 2,770,090 $ 2,060,000 SH-74 over I-35 FFY 2015 Bridge Rehabilitation $ 1,166,000 SH-59 over Criner Creek FFY 2017 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities SH-59 over Panther Creek FFY 2015 Bridge Rehabilitation $ 2,248,800 $ 3,750,000 $ 159,135 $ 53,045 $ 3,962,180 SH-19 from 2.40 mi. NE of US-77 NE & E. 4.88 mi. FFY 2021 Widen, Resurface & Bridge $10,908,100 FFY 2018 Right Of Way $ 1,308,000 FFY 2018 Utilities $ 560,425 $12,776,525 US-77 over S. Canadian River & Railroad FFY 2018 Bridge & Approaches $36,400,000 FFY 2016 Right Of Way $ 119,684 FFY 2016 Utilities $ 1,442,457 $37,962,141 US-77 over Walnut Creek FFY 2015 Bridge Rehabilitation $ 4,800,000 SH-19 over Peavine Creek FFY 2019 Bridge & Approaches FFY 2016 Right Of Way FFY 2016 Utilities $ 1,896,100 $ 45,099 $ 173,457 $ 2,114,656 SH-74 over Beef Creek FFY 2015 Bridge & Approaches $ 1,125,200 I-35 from SH-145 N. 4.38 mi. FFY 2021 Resurface SH-19 over Beef Creek FFY 2017 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities $ 9,000,000 $ 1,220,060 $ 34,000 $ 35,100 $ 1,289,160 I-35 over Washita River FFY 2016 Bridge & Approaches $ 9,234,877 SH-74 over Unnamed Creek FFY 2019 Bridge & Approaches $ 1,166,000 SH-29 over Salt Creek FFY 2022 Right Of Way FFY 2022 Utilities $ $ $ SH-29 over Salt Creek Tributary FFY 2022 Right Of Way $ FFY 2022 Utilities $ $ 150,000 100,000 250,000 150,000 100,000 250,000 I-35 from SH-19 N. 3.21 mi. FFY 2020 Reconstruct-No Added Lanes $14,265,000 I-35 over Rush Creek FFY 2015 Bridge Rehabilitation $ 2,756,000 US-77 over Rush Creek FFY 2018 Bridge & Approaches FFY 2015 Right Of Way FFY 2015 Utilities $ 7,736,384 $ 842,025 $ 56,135 $ 8,634,544 SH-74 over 2 Unnamed Creeks FFY 2016 Bridge & Approaches $ SH-17A over I-35 FFY 2015 Bridge Rehabilitation 821,837 $ 1,751,000 I-35 from 4.21 mi. N. of SH-7 N. 6.19 mi. to SH-29 FFY 2021 Reconstruct-No Added Lanes $18,000,000 $ 2,669,200 SH-48 over Unnamed Creek FFY 2022 Bridge & Approaches FFY 2020 Right Of Way FFY 2020 Utilities US-75 over Caney Creek FFY 2020 Bridge & Approaches FFY 2017 Right Of Way FFY 2017 Utilities SH-24 from 3.43 mi. W. of SH-74 N. 2.62 mi. FFY 2022 Grade & Drain $ 2,250,000 FFY 2020 Right Of Way $ 300,000 FFY 2020 Utilities $ 150,000 $ 2,700,000 $ 6,048,263 SH-1 from 1.5 mi. S. of SH-3 N. to SH-3 FFY 2020 Grade, Drain & Surface $ 4,597,800 FFY 2016 Right Of Way $ 231,080 FFY 2016 Utilities $ 115,540 $ 4,944,420 US-75 over Rock Creek FFY 2015 Bridge & Approaches $ 8,430,859 SH-74 over Washita River FFY 2016 Bridge & Approaches $ 4,585,500 SH-99 over Walnut & 2 Unnamed Creeks FFY 2016 Widen, Resurface & Bridge $10,110,995 $ 1,030,000 $ 7,719,200 SH-19 over Big Sandy Creek FFY 2015 Bridge & Approaches SH-99 from 3.5 mi. N. of SH-99A N. 2 mi. FFY2019 Widen & Resurface $ 4,000,000 FFY2015 Right-of-Way $ 1,219,252 FFY2015 Utilities $ 1,839,432 $ 7,058,684 $ 3,415,744 $ 100,000 $ 395,300 $ 3,911,040 SH-76 over Washita River FFY 2015 Bridge & Approaches SH-19 from 4.3 mi. E. of Garvin C/L E. 5.64 mi. FFY 2017 Widen & Resurface $21,026,266 SH-99 from 5.5 mi. N. of SH-99A N. to SH-3 FFY 2018 Widen & Resurface $ 5,450,000 SH-76 from 3 mi. N. of SH-19 N. 5 mi. FFY 2021 Grade, Drain & Surface $ 8,332,100 FFY 2016 Right Of Way $ 538,048 FFY 2016 Utilities $ 789,068 $ 9,659,216 SH-76 from SH-19 N. 3 mi. FFY 2016 Grade, Draining, Bridge & Surface SH-19 from 1 mi. E. of US-177 E. 4.6 mi. FFY 2018 Widen, Resurface & Bridge $12,353,188 $ 1,398,200 $ 30,740 $ 77,698 $ 1,506,638 SH-131 over Unnamed Creek FFY 2021 Right Of Way FFY 2021 Utilities US-77 over Unnamed Creek & Washita River Overflow FFY 2020 Grade, Draining, Bridge & Surface $ 4,838,200 FFY 2017 Right Of Way $ 804,540 FFY 2017 Utilities $ 630,700 $ 6,273,440 US-77 over Washita River FFY 2017 Bridge & Approaches SH-7 over Pecan Creek FFY 2019 Bridge & Approaches FFY 2016 Right Of Way FFY 2016 Utilities SH-7 over Keel Creek FFY 2020 Bridge & Approaches FFY 2017 Right Of Way FFY 2017 Utilities $ 1,822,700 $ 27,810 $ 148,217 $ 1,998,727 $ $ $ $ $ 8,872,200 SH-48 over Elm & 2 Unnamed Creeks FFY 2022 Bridge & Approaches $ 3,500,000 FFY 2020 Right Of Way $ 375,000 FFY 2020 Utilities $ 200,000 $ 4,075,000 SH-48 over Elm & Tell Creeks FFY 2022 Bridge & Approaches FFY 2020 Right Of Way FFY 2020 Utilities 693,100 28,620 86,178 807,898 SH-99 from 0.61 mi. N. of SH-22 N. 5.31 mi. FFY 2020 Grade, Drain & Surface $13,700,000 FFY 2017 Right Of Way $ 2,738,863 FFY 2017 Utilities $ 855,880 $17,294,743 $ 7,091,649 Pending funding by others SH-22 over Unnamed Creek FFY 2022 Right Of Way FFY 2022 Utilities SH-22 over Butcher Pen Creek FFY 2015 Bridge & Approaches $ $ $ $ $ $ 100,000 50,000 150,000 SH-43 over Muddy Boggy Creek & Muddy Boggy Overflow FFY 2018 Bridge Rehabilitation $ 3,270,000 SH-99 from 5.64 mi. N. of SH-22 N. 4.19 mi. FFY 2019 Grade, Drain & Surface $ 5,886,100 SH-99 over Washita River FFY 2018 Bridge & Approaches $ 1,000,000 $ 100,000 $ 50,000 $ 1,150,000 150,000 100,000 250,000 $ 2,538,600 $ 2,000,000 $ 200,000 $ 100,000 $ 2,300,000 SH-43 over Mill Creek FFY 2019 Bridge & Approaches $ 3,227,272 US-75 over Briar Creek FFY 2019 Bridge Rehabilitation $ 700,000 SH-48 from 1 mi. S. of Johnston C/L N. 6 mi. FFY 2022 Widen & Resurface $14,000,000 FFY 2019 Right Of Way $ 600,000 FFY 2019 Utilities $ 450,000 $15,050,000 US-75 over Coal Creek FFY 2015 Bridge & Approaches $ 2,467,400 SH-48 over Delaware & Walnut Creeks FFY 2022 Bridge & Approaches $ 2,500,000 FFY 2019 Right Of Way $ 275,000 FFY 2019 Utilities $ 150,000 $ 2,925,000 US-99 over Sandy, Buzzard & Big Sandy Creeks FFY 2016 Bridge & Approaches $ 2,389,600 SH-48 over Sandy Creek FFY 2022 Bridge & Approaches FFY 2019 Right Of Way FFY 2019 Utilities $ 1,000,000 $ 100,000 $ 50,000 $ 1,150,000 SH-48 over Sandy Creek FFY 2022 Bridge & Approaches FFY 2020 Right Of Way FFY 2020 Utilities $ 1,500,000 $ 175,000 $ 100,000 $ 1,775,000 SH-48 over Unnamed Creek FFY 2022 Bridge & Approaches FFY 2019 Right Of Way FFY 2019 Utilities $ 1,000,000 $ 100,000 $ 50,000 $ 1,150,000 SH-48 from Atoka C/L N. 7.37 mi. to SH-48A FFY 2022 Widen & Resurface $12,390,000 FFY 2019 Right Of Way $ 3,700,000 FFY 2019 Utilities $ 1,600,000 $17,690,000 SH-78 from 5.38 mi. N. of Bryan C/L N. 4 mi. FFY 2021 Widen & Resurface $ 9,500,000 FFY 2017 Right-of-Way $ 654,000 FFY 2017 Utilities $ 327,000 $10,481,000 Note: The depicted information is based on project data currently available. Project estimates and schedules will remain subject to further refinement as more definitive data becomes available. September 8, 2014
© Copyright 2025 ExpyDoc