SPECIAL CONDITIONS OF CONTRACT [SCC] SPECIAL CONDITIONS OF CONTRACT 1. NAME OF WORK: 1.1. Supply, Installation and commissioning of Guided Wave Radar (GWR) type Level Gauging system including interface with DCS at GAIL, Usar as per scope of work, terms and conditions mentioned in this tender document and as per direction of Engineer In-Charge (EIC). 1.2. It consists of 3 nos. of GWR type Level Transmitters & Probe in LPG Mounded storage tanks to be replaced in place of existing Servo Level Gauge System and 1 no. of GWR type Level Transmitter & Probe in newly installed Naphtha Storage Tank. 2. LOCATION OF SITE: 2.1. The proposed work is to be executed at GAIL (India) Ltd., LPG Recovery Plant – Usar, P.O: Malyan, Dist: Raigad, Maharashtra, Pin Code: 402203 located at about 12 km from Alibag, Maharashtra. 3. DELIVERY AND COMPLETION TIME: After placement of the Purchase Order the Contractor shall take immediate steps to get all the materials at their works as early as possible and shall inform GAIL to test the items whenever ready. To ensure that the supply items are of recent origin, not supplied by the original Supplier earlier than six months, necessary documents shall be produced and attached as evidence. The supplier shall take steps for site clearance and the facilities needed at site to avoid any delay in the execution of work at Site. The delivery and completion time is as below: 3.1. Overall Contract Period: The overall contract period is 12 months from the date of issue of Fax of Acceptance (FOA) or Purchase Order (PO) whichever is issued first. 3.2. For Supply Portion: All the materials under supply portion shall be supplied within 12 weeks from the date of issue of Fax of Acceptance (FOA) or Purchase Order (PO) whichever is issued first. 3.3. For Works: The installation, commissioning and handing over of the system for each Storage Tank shall be completed within 1 week from the date of intimation of Site Readiness from GAIL for that particular tank. However, GAIL will intimate for site readiness for each tank during the tenure of the Contract period as soon as the tank is ready for installation. 4. PAYMENT TERMS: 4.1. Supply Portion 90% payment towards supply shall be released after receipt and acceptance of all the materials as per Purchase Order at GAIL, Usar Site. Balance 10% payment towards supply will be released after successful completion of installation and commissioning of the entire work. However, if the installation and commissioning is delayed due to non-availability of the site readiness by purchaser within the Contract period then this balance amount of 10% will be released by GAIL after nine months from the date of material acceptance at site against submission of bank guarantee for equivalent amount. This BG will be valid for 06 months initially and will be extended till completion of successful installation, commissioning, testing and handing over the system to GAIL, duly certified by EIC. Rescheduling of installation and commissioning will be intimated by EIC (Engineer-In-Charge). 4.2. Works Portion: 100% Payment towards installation & commissioning applicable for individual tanks will be released as and when the Level Guaging system for that particular tank is completed based on certification by the EIC. 4.3. The payments shall be made within 15 days of receipt of the invoice after due certification by EIC for works portion and by Contract & Procurement Department for supply portion. The vendor on submitting the bill thereof will be entitled to receive a payment approved and passed by the Engineer-in-Charge, whose certificate of such approval and passing of the sum so payable shall be final and conclusive against the vendor. Payment shall be subject to statutory deductions as applicable. 5. GUARANTEE: 5.1. All the materials supplied under this contract shall be guaranteed for 24 months from the date of shipment by the Bidder or 12 months from the date of successful commissioning of the system, whichever is earlier. 5.2. All work performed under this contract shall be free from defects and shall remain so for a period of at least one (1) year from the date of acceptance of the system. The full cost of maintenance, labor and materials required to correct any defect during this one-year period shall be included in the submitted bid. 6. ENGINEER-IN-CHARGE: 6.1. Nominated person from respective indenting department at GAIL Usar will be the EngineerIn-Charge (EIC) for this job. 7. PRICE REDUCTION SCHEDULE (PRS): 7.1. In case of delay in delivery of materials beyond contractually agreed delivery schedule, the Price reduction schedule will be applicable @ 0.5% of Material value (Supply Portion excluding taxes & duties) per week of delay or part thereof, subject to a ceiling of 5% (Five Percent) of the total order value. 7.2. The portion of supply completed in all respect which can be used for commercial operation shall not be considered for applying PRS. 7.3. In case of delay in installation and commissioning beyond contractually agreed installation and commissioning schedule, price reduction schedule will be applicable @ 0.5% of total installation and commissioning value (excluding taxes & duties) per 24 hrs of delay or part thereof from the date of intimation of site readiness of particular Tank by GAIL, subject to a ceiling of 5% (Five percent) of the total order value. 7.4. However, the total price reduction against delay in delivery of materials as well as delay in installation and commissioning will be limited to a ceiling of 5% (Five percent) of the total order value. 8. PUNITIVE FINES FOR VIOLATION OF SAFETY RULES AND REGULATIONS: Punitive fines on contractors are imposed for repetitive violation of safety rules & regulations during execution of jobs. Objective of punitive fines is to work as deterrent for contractors in violation of safety rules & regulation and to improve safety atmosphere in general at all site. The guidelines for imposition are described below: 8.1. For first time violation of safety rules & regulation by the Contractor, HOD (F&S) of GAIL, Usar will issue a warning letter to Contractor with intimation to OIC of GAIL, Usar and EIC. 8.2. In case of second time violation of safety rules & regulations by same Contractor, OIC, Usar will call contractor in person and will have a meeting to discuss reason for repetitive 8.3. violation along with EIC and HOD (F&S). A warning letter will also be issued by EIC to Contractor. In case of further violation, punitive fines will be imposed on contractor. Amount of fine will be decided as per severity of violation of safety. However, minimum fine would be Rs. 10,000/- and in multiple of Rs. 10,000/-, thereafter. This will be limited to 5% of the total order value, as maximum cumulative penalty. 9. SCOPE OF GAIL: 9.1. Electricity and water for installation and commissioning shall be provided free of cost by GAIL. 9.2. GAIL will assist in identifying the location of existing system components. 9.3. Necessary configuration in DCS end for Modbus communication with GWR Level Gauges shall be done by GAIL. 10. TRAVEL, BOARDING & LODGING EXPENSES: 10.1. The Contractor shall arrange on his own for Travel, Boarding and Lodging of their Site manpower. All expenses towards this shall be borne by the Contractor and the quoted contract price is deemed to have included the cost towards these expenses. SCOPE OF WORK (SOW) & TECHNICAL SPECIFICATIONS SCOPE OF WORK (SOW) & TECHNICAL SPECIFICATIONS GUIDED WAVE RADAR TYPE TANK LEVEL GAUGING SYSTEM AT GAIL USAR TABLE OF CONTENTS: 1.0 2.0 3.0 4.0 5.0 6.0 INTRODUCTION EXISTING SYSTEM PROPOSED SYSTEM DESCRIPTION EXECUTION PHILOSOPHY SCOPE OF WORK TECHNICAL SPECIFICATIONS 1.0. INTRODUCTION: 1.1. GAIL (India) Ltd., Usar intends to replace the existing Servo Level Gauging System by a suitable Guided Wave Radar Type Tank Gauging System at its Usar LPG Recovery Plant. In addition to that one more Guided Wave Radar type Tank Gauging System is required for the newly installed Naphtha Storage Tank. 2.0. EXISTING SYSTEM: 2.1. The existing system consists of three numbers Servo Level Gauges (Make: Motherwell) installed in three LPG Mounded Storage Tanks A, B & C. The level signals from these Level Gauges are displayed at two locations for monitoring i.e. one at LPG Mounded Storage Control Room (LPG MST CR) located nearby the LPG MSTs and another at Central Control Room (CCR) where it has been interfaced with GAIL’s existing DCS (Make: Yokogawa, Model: Centum VP). The approximate distance of LPG MST CR is 200 m and that of CCR is 1000 m from the existing Servo Level Gauges. 2.2. One Naphtha Storage Tank has been newly installed without stilling well. The approximate distance of LPG MST CR is 250 m and that of CCR is 1000 m from the Naphtha Storage Tank. 3.0. PROPOSED SYSTEM DESCRIPTION: 3.1. All the three Level gauges along with the Signal Repeaters at LPG MST CR & CCR as mentioned above in SOW clause 2.1 are to be replaced with new Guided Wave Radar Level Gauging system. However the existing cable, junction boxes, stilling well, etc. shall be retained for the new system. 3.2. One GWR Level Gauge is to be installed and commissioned in the newly installed Naphtha storage Tank and its signals are to be repeated at both LPG MST CR and CCR. 3.3. Signals of all the four GWR Level Transmitters shall be interfaced with existing DCS (Make: Yokogawa, Model: Centum VP) through RS485 Modbus communication either directly from the Level Transmitters or using suitable intermediate accessory instruments like Media Converter. 3.4. Schematic diagram of the proposed system is given in Annexure-1. One 2Pair x 1.5 sqmm cable exists between the existing Motherwell LT and LPG MST CR and one more 2Pair x 1.5 sqmm cable exists between the existing Motherwell LT and CCR. These cables shall be reused for this proposed system. 3.5. For power supply and signal interfacing of the GWR LT installed at Naphtha Storage tank the existing spare pairs of 1.5 sq. mm size available in cables which have already been laid between the Naphtha Storage tank and LPG MST CR shall be used. 3.6. 3.7. 110 VAC (+/-5%), and 50Hz (+/- 5%) UPS supply is available at both LPG MST CR and CCR. Bidder shall be responsible for all further power distribution for functional requirements of the system. Any other voltage levels/DC voltage, if necessary shall be derived from this UPS supply by the bidder. The Vendor shall design the new system in such a way that the requirement of cables for the new system is met using the existing cables as mentioned above. However, if there is a requirement of additional cables or any special type of cable suitable for the offered system, then the same shall be supplied and laid by the Bidder. 4.0. EXECUTION PHILOSOPHY: 4.1. The Vendor shall deliver all the items at one go at GAIL, Usar Site. 4.2. The GWR Level gauging system shall be installed and commissioned in all the three LPG Mounded storage tanks during their internal inspection one by one. The internal inspection of one of the MSTs has been planned tentatively in the month of October 2014. It is expected that the internal inspection of all the three MSTs shall be completed within 9 months starting from Oct 2014. 4.3. The GWR Level gauging system shall be installed and commissioned in the Naphtha Storage Tank (Capacity: 50 KL) on mutually agreed dates. 5.0. SCOPE OF WORK: The scope of work for this job shall broadly comprise of the following as minimum: 5.1. The scope of work include but not limited to Design & Supply of Guided Wave RADAR tank level gauging system including all sensors/transmitters, converters/controllers/monitors, junction boxes, glands and any other hardware & software as necessary and Fabrication, Packing, Forwarding, Clearance of all material including Transportation, Delivery, Installation, Field Testing, Pre commissioning & Commissioning including after sales support of New System as per the Technical specifications and handing over the system in good working condition to GAIL. 5.2. All the items required for the proper operation of complete system shall be furnished by vendor, even if not specifically called for in the specification. This shall include – Documentation, Test reports, on-site Training, Warrantee & Guarantee, Spare Parts, Service Support, Factory acceptance test (FAT), Site acceptance test (SAT). 5.3. Bidders can assess the scope of work prior to pre-bid conference. The necessary entry pass to the plant area will be provided on request. 5.4. The value of work under this contract shall be as per tentative Bill of Materials mentioned in Scope of work. 5.5. MATERIAL SUPPLY: 5.5.1. Supply of Guided Wave Radar type Tank Level Gauging System with Signal Repeater at LPG MST CR and CCR. 5.5.2. Interfacing Instruments and accessories for interfacing the GWR LTs with GAIL DCS of Yokogawa Centum VP through RS-485 Modbus communication. 5.5.3. Supply of software, if any, with license valid for lifetime for configuration of the GWR Level Transmitters and the Interfacing instruments. 5.5.4. Supply of instrument mounting accessories like brackets, structural supports, canopy and cable, cable glands, conduits, studs, nuts, bolts, etc. 5.5.5. Supply of terminal strip of Dowel / clip-on or equivalent make to connect wires & lugs as per requirement. 5.5.6. Any other material which are not covered above but are necessary for successful installation & commissioning. 5.5.7. Supply of required commissioning spares (Refer Spares Philosophy). Balance of commissioning spares is to be handed over to GAIL after installation and commissioning. 5.6. TENTATIVE BILL OF MATERIAL: S.N. ITEM DESCRIPTION 1 2 3 Sensor / Probe for LPG MST Sensor / Probe for Naphtha Tank Transmitter (Integral with probe) Interfacing Instruments and accessories for interfacing the GWR LTs with GAIL DCS of Yokogawa Centum VP through RS-485 Modbus. 4 INSTALLATION LOCATION Inside Stilling Well Without Stilling Well Tank Top QUANTITY 3 nos. 1 no. 4 nos. LPG MST CR and CCR 1 Lot 5 Mounting Accessories Field Area 1 Lot. 6 Service Support: Installation, Commissioning, Training etc. GAIL Usar 1 Lot. 5.7. INSTALLATION: 5.7.1. Installation of GWR Level Gauges, Signal Repeaters. 5.7.2. Glanding, ferruling, termination and tagging of all the cables. 5.7.3. Installation of the software, if any. 5.7.4. Installation of permanent Tag Plates on all devices in the field, JBs and the panel. 5.7.5. Installation of any other sensor, device and hardware not mentioned here specifically but is required for completion of the job. 5.7.6. Any other job which is not covered above but are necessary to be done for successful installation & commissioning. 5.8. TESTING, INSPECTION & ACCEPTANCE: 5.8.1. All material/services/works involved in this job shall be inspected by the Bidder appropriately. Bidders should have the required facilities for testing the quoted equipment / material as per International standards at their premises and also agree for inspection by GAIL or any other agency nominated by GAIL or any third party agency. In case the bidder is not the manufacturer, a certificate from the manufacturer to the effect that the manufacturer possesses the required facilities for testing the quoted equipment/ material should be enclosed along with the technocommercial bid. 5.8.2. Factory Acceptance Test (FAT): Before dispatch of the materials to GAIL, the working and functioning of the entire system in an integrated way shall be simulated and exhibited by the bidder in his woks in presence of authorized GAIL Engineers. After successful completion of FAT necessary permission shall be given by GAIL on writing to dispatch the material to site. Delay, if any, due to unsuccessful FAT shall be in bidder’s account and bidder shall be held responsible for delay in delivery beyond schedule, if any. However, upon receiving request for FAT on writing, GAIL shall depute their engineer within 10 days for FAT. Delay, if any, in deploying GAIL Engineers for FAT shall be on GAIL’s account. Bidder shall send the FAT procedure mentioning all the tests to be performed and documents / formats in advance to GAIL for their approval to avoid any future ambiguity in this regard. All the items shall be dispatched to GAIL, Usar Site after the FAT is cleared by GAIL unless it is waived off by GAIL. 5.8.3. Site Acceptance Test (SAT): After installation, integration and successful commissioning of the system at site, Bidder’s engineers jointly with GAIL’s Engineers shall conduct SAT to exhibit proper functioning of the system, as per the tendered requirement. Bidder shall send the SAT procedure and documents / formats in advance to GAIL for their approval to avoid any future ambiguity in this regard. Only after completion of SAT, the job can be considered as complete. 5.9. GENERAL INSTRUCTION FOR INSTALLATION & COMMISSIONING: 5.9.1. The installation and commissioning job of System at site shall be carried out as per OEM recommended practices by the authorized and trained engineers of the Bidder. Supply of all material, equipment, labour etc. required for the job shall be in bidder’s scope. 5.9.2. It will be of bidder’s responsibility to install the new System at site and commission the same. The vendor shall make all lifting and shifting arrangement. If necessary, the vendor shall make site survey and assess all work involved for installation and commissioning before commercial offer is submitted. 5.9.3. Vendor shall submit detailed execution schedule. 5.9.4. Vendor shall supply and install all electrical accessories like cables, fittings, sockets, MCB, fuses, switches, circuit breakers etc. for satisfactory commissioning of the equipment. GAIL shall be providing the power supply as per load requirement stated in the bid. 5.9.5. The vendor shall make his own arrangement for tools and tackles for installation, commissioning & calibration. All such material shall be shown at the plant main gate and certified copy of the material taken inside the plant premises will be submitted to the engineer-in-charge on demand. 5.9.6. Vendor shall provide safety gears such as cotton clothes, safety helmet, safety shoes, gloves, safety belt, etc. to all of his employees at his own cost. No personnel will be allowed inside plant without wearing safety gears. 5.9.7. The work is to be carried out in “Restricted Area” and the vendor will have to work as per the instruction of the Engineer In-Charge and should obtain the permission in writing in a standard format. Employees working under him are liable for physical check by the competent authority as decided by the EIC, at any time 5.10. INSTALLATION REQUIREMENTS: 5.10.1. Bidder shall offer services of the installation team which would install the instruments /equipment in the designated area of plant, lay the interconnecting cables, terminate, loop check, test and commission the system. All technical personnel assigned to the site by the bidder shall be experienced and fully conversant with the system as well as designed configuration. Bidder’s responsibility at site shall include all activities necessary to be performed to complete the job as per bid. 5.10.2. System shall be installed such that it is easily accessible for calibration and maintenance. All components of the system, which require regular maintenance and / or monitoring, shall be easily accessible to the operations and maintenance personnel with minimum wiring removal and no special tools. 5.11. TRAINING: A training program shall be organized by Bidder on Guided Wave RADAR type Tank Level Gauging System either at Site or at the Bidder’s facility. Training shall be imparted for minimum 6 GAIL Engineers of Instrumentation discipline. . If the training is arranged by the Bidder at their facility then the travel, boarding & lodging arrangement for GAIL personnel will be in the scope of GAIL. The training shall preferably be arranged before offering it for FAT / SAT. In general following topics shall be covered in the training session as minimum: 5.11.1. System hardware details 5.11.2. Software features of the system including Programming / Configuration / Operation 5.11.3. Calibration of the system 5.11.4. Maintenance & trouble shooting 5.12. DOCUMENTATION: SN Description of Document 1 2 System Configuration Bill of Material System specifications including all sub-system components and bought out items System Power consumption details List of commissioning spares Recommended spare parts for 2 years continuous O&M Earth Schemes Wiring diagrams Test Reports System configuration & programming manuals Operation & Maintenance Manual Overall Spare parts summary QA / QC Plan 3 4 5 6 7 8 9 10 11 12 13 Along After PO with Bid Placement (01 (2 Copies: Hard 01 Soft & copy) 01 Hard) X (i) X(a) X (i) X(a) Final “AsBuilt” (4 Copies: 01 Soft & 03 Hard) X X X (i) X(i) X X (i) X(i) X X (i) X(a) X X (i) X(i) Legends: X : Required as Final documentation X(i) : Required for Information only X(a) : Required for Approval of GAIL X(a) X(a) X X X(i) X X(i) X(i) X(i) X X X 6.0. TECHNICAL SPECIFICATIONS: 6.1. GENERAL REQUIREMENTS: This specification together with the data sheets attached herewith, describes the requirements for the design, manufacture, inspection, testing and supply of the complete system and other associated control functions including all hardware as necessary, for installation in a hazardous industrial process plant. 6.2. CODES & STANDARDS: The design of the system shall conform to the latest edition of the following standards, codes and recommended practices. In the event of any conflict between this specification, related standards, codes, etc. the Bidder should refer the matter to the Engineer-in-charge for clarification and only after obtaining the same should proceed with the manufacture of the items in question. 6.2.1. IEC 61508 - 1 6.2.2. IEC 61511 - 1 6.2.3. Chapter 10 of ‘IOC Fire Accident Investigation Report’ submitted by M.B.Lal Committee 6.3. SPARES PHILOSOPHY: 6.3.1. Mandatory / Commissioning Spares: For installation, testing, commissioning of system vendor shall provide some mandatory commissioning spares. These commissioning spares shall be properly & separately packaged with clear marking- ‘Commissioning Spares’. Bidder shall be required to supply items as part of mandatory spares based on its own past experience for similar system. 6.3.2. Price List of Recommended Spares: Vendor shall also provide a separate Priced list of recommended spare parts for two years normal operation and maintenance. This list should take into account related factors of ‘system’ reliability, effect of downtime upon normal operation & safety and availability of servicing facilities. GAIL shall consider the list as reference in future and if required shall procure it separately at later stage. 6.4. SPECIFICATION FOR GUIDED WAVE RADAR LEVEL GAUGE FOR LPG MOUNDED STORAGE TANK SPECIFICATION FOR GUIDED WAVE RADAR LEVEL GAUGE FOR LPG MOUNDED STORAGE TANK BIDDER ACCEPTANCE / S.N. DESCRIPTION SPECIFICATION COMMENTS TANK DETAIL - GENERAL 1 TANK TYPE Pressurized Mounded Storage Tank 2 APPLICATION LPG Liquid with Vapour 3 TAG NO. 20-LT 9001 / 9003 / 9005 4 INTERNAL DIAMETER 7.1 Mtr 5 LENGTH 79 Mtr 6 STILLING WELL DIAMETER 7 GAUGE MOUNTING 6" Sch 80 (Dwg. attached as Annexure-2) Top on Nozzle (Dwg. Attached as Annexure-3, location at LT1) 8 OPERATING PRESSURE 7 – 8 kg/sqcm.g 9 OPERATING TEMPERATURE 22 - 30 Deg C 10 SPECIFIC GRAVITY 0.55 11 DIELECTRIC CONSTANT 1.6 to 1.9 12 AREA CLASSIFICATION 13 PESO APPROVAL Eex d (ia) IIB + H2 T6 as per EEC/89/336 For use in hazardous areas coming under purview of the Petroleum Rules, 2002 administered by PESO. SENSOR & TRANSMITTER - Qty =03 nos. 14 TYPE GUIDED WAVE RADAR, Contact Type 15 APPLICATION Liquid Hydro Carbon - LPG 16 MAKE Vendor to Specify 17 MODEL Vendor to Specify 18 SENSOR / PROBE Coaxial suitable to service 19 APPROVAL ATEX II 1/2G EEx ia IIC T6 , XA 20 PROCESS CONNECTION Flanged 6", 300 lbs, RF top on stilling well 21 OUTPUT 4-20 mA HART or Vendor standard 22 HOUSING Aluminium, coated IP65 NEMA 4X 23 MEASURING RANGE 0 to 7100 mm 24 ACCURACY (+/-) 2 mm or better at reference condition 25 CABLE ENTRY 1/2" NPT Threaded 26 FUNCTIONAL SAFETY SIL 2 in compliance with IEC 61508/IEC 61511-1 & Overfill Safe functionality. OTHERS - 01 lot. Communication Feature 27 with existing Yokogawa DCS at GAIL, Usar 28 Configuration Software & Accessories The Bidder shall supply and commission all the devices / accessories necessary for interfacing all the GWR Level Guages through RS485 Modbus Communication with the existing Yokogawa make Centum VP model DCS installed at GAIL, Usar. The Bidder shall supply necessary software along with lifetime valid license and necessary accessories such as interface cable for doing configuration & troubleshooting of the GWR Level Guages. 29 ACCESSORIES All Mounting Accessories as per Technical specifications, Special Condition of Contract & Detailed Scope of Work 30 SERVICE SUPPORT Training, Installation & Commissioning as per scope. 6.5. SPECIFICATION FOR GUIDED WAVE RADAR LEVEL GAUGE FOR NAPHTHA STORAGE TANK SPECIFICATION FOR GUIDED WAVE RADAR LEVEL GAUGE FOR NAPHTHA TANK BIDDER ACCEPTANCE / S.N. DESCRIPTION SPECIFICATION COMMENTS TANK DETAIL - GENERAL 1 TYPE Pressurized Bullet 2 APPLICATION Naphtha Liquid 3 TAG NO. 4 TANK INTERNAL DIAMETER 2400 mm 5 TANK LENGTH 11.56 m 6 STILLING WELL DIAMETER Not existing now 7 GAUGE MOUNTING Top 8 OPERATING PRESSURE 1 – 1.5 kg/sqcm.g 9 OPERATING TEMPERATURE 20 - 35 Deg C 10 SPECIFIC GRAVITY 0.69 11 DIELECTRIC CONSTANT 2 12 AREA CLASSIFICATION 13 PESO APPROVAL EEx d (ia) IIB + H2 T6 as per EEC/89/336 For use in hazardous areas coming under purview of the Petroleum Rules, 2002 administered by PESO. SENSOR & TRANSMITTER - Qty =01 no. 14 TYPE GUIDED WAVE RADAR, Contact Type 15 APPLICATION Liquid Hydro Carbon - Naphtha 16 MAKE Vendor to Specify 17 MODEL Vendor to Specify 18 SENSOR / PROBE Coaxial or suitable to service 19 APPROVAL ATEX II 1/2G EEx ia IIC T6 , XA 20 PROCESS CONNECTION Flanged 2", 150 lbs, RF top 21 OUTPUT 4-20 mA HART or Vendor standard 22 HOUSING Aluminium, coated IP65 NEMA 4X 23 MEASURING RANGE 0 to 2400 mm 24 ACCURACY (+/-) 2 mm or better at reference condition 25 CABLE ENTRY 1/2" NPT Threaded 26 FUNCTIONAL SAFETY SIL 2 in compliance with IEC 61508/IEC 61511-1 & Overfill Safe functionality. OTHERS - 01 lot. Communication Feature 27 with existing Yokogawa DCS at GAIL, Usar 28 Configuration Software & Accessories 29 ACCESSORIES 30 SERVICE SUPPORT The Bidder shall supply and commission all the devices / accessories necessary for interfacing all the GWR Level Gauges through RS485 Modbus Communication with the existing Yokogawa make Centum VP model DCS installed at GAIL, Usar. The Bidder shall supply necessary software along with lifetime valid license and necessary accessories such as interface cable for doing configuration & troubleshooting of the GWR Level Gauges. All Mounting Accessories as per Technical specifications, Special Condition of Contract & Detailed Scope of Work Training, Installation & Commissioning as per scope Annexure-2 Annexure-3a Annexure – 3b SCHEDULE OF RATES (SOR) SUPPLY PORTION SN ITEM DESCRIPTION UOM QTY 1 Supply of GWR Level Probe & Transmitter for LPG Mounded Storage Tanks (7100 mm dia) with all accessories like cable glands, RFP Canopy, Gasket, EACH Nut & Bolts etc. including the items required for interfacing with GAIL DCS as per tender documents. 3 2 Supply of GWR Level Probe & Transmitter for Naphtha Storage Tank (2400 mm dia) with all accessories like cable glands, RFP Canopy, Gasket, Nut EACH & Bolts etc. including the items required for interfacing with GAIL DCS as per tender documents. 1 UNIT RATE (Rs.) AMOUNT (Rs.) UNIT RATE (Rs.) AMOUNT (Rs.) WORKS PORTION SN ITEM DESCRIPTION UOM QTY 1 Installation & Commissioning of GWR Level Probe & Transmitter for each LPG Mounded Storage Tank (7100 mm dia) EACH including interfacing with GAIL DCS as per tender documents. 3 2 Installation & Commissioning of GWR Level Probe & Transmitter for Naphtha Storage Tank (2400 mm dia) including EACH interfacing with GAIL DCS as per tender documents. 1
© Copyright 2024 ExpyDoc