Construction NHAI targets 6000 km of tendering Your success is our success July 2, 2014 Re-bidding of stalled contracts and new orders (EPC+BOT) likely to push awarding activity upwards in 2HFY15E/FY16E; NHAI targets 6000km In FY13 and FY14, project award activity fell sharply and was at its lowest levels since FY05, with the exception of FY09. Both BOT (build-operate-transfer) and EPC (engineering, procurement and construction) project awards by the NHAI declined to 1116km/213km in FY13/FY14 from 6380km in FY12. We have seen a surge in ordering activity in BOT mode between FY09 and FY12, while the contribution of projects awarded in EPC mode was negligible. However, in FY13-14, we noticed the tapering off awarding activity, with 14 BOT projects worth Rs150bn/1822km failing to attract any bids. This led to awarding of only 1116km of BOT projects as against the original target of 8800km. Given the prevailing financial and structural challenges in the sector, the NHAI aims to tender projects worth Rs2300km via the EPC route, and we see scope of new orders to emerge through the EPC route and potential re-bidding of stalled contracts, as well as some new projects, which are likely to keep push tendering activity upwards in FY15E-16E. Premium restructuring scheme: Cashflow mismatch to get resolved for developers Emkay Global Financial Services Ltd. Panel approved that developers will allow converting their premium owed to the government (NHAI) into a loan versus earlier methodology of deferring premium to 75% during first 3 years of the construction period and 50% of the premium for the remaining years for six-laning projects. This, in our view, is a much better framework as far as the accountability of developers is concerned (the earlier policy would have created litigation and also had no mechanism to gauge the premium not paid on projects getting mobilized in the same project or used fresh equity for new road project or else getting utilized for some other purpose). The panel has said that the bailout for rescheduling of the premium owed to the government should be restricted to developers with toll collections insufficient to service debt, maintenance and premium obligations of the project. According to the Panel recommendations the rescheduled premium will be treated as a revenue shortfall loan by NHAI. The shortfall in the premium due can be backloaded to the later years of the concession, but will invite an interest charged at the rate of 2% point more than the bank rate, which implies an interest rate of 10.75-11%. The panel has recommended that a maximum penalty of 0.5% of the total project cost be imposed if a developer avails of the option to reschedule the premium obligation; however, it involves a caveat that penalty will be charged where the NHAI is not at default, whereas in 80% of the cases the NHAI has remained at default in terms getting clearances. Given that 32 projects qualified for premium restructuring, of which 8-9 projects (sixlaning, starts paying premium from the appointed date) got the approval for premium restructuring is an attempt to resolve the cashflow mismatch (taking sub-debt to fund losses), the developer would have faced in early stages of commissioning (partly due to aggressive bids). However, the developer pledge towards the equity commitment remains in the project (which was not present in the earlier scheme). We believe the heightened risk perception about BOT projects, due to which financial institutions became reluctant to take additional exposure in highway BOT projects to address this issue, the NHAI has given priority to debt servicing requirements over the NHAI premium payments. 1 Sector Update Emkay © Construction Sector Update Premium restructuring may not be enough, re-bid of projects the prudent option Premium restructuring scheme is a mechanism opted by NHAI To bailout some of the commissioned projects (majority six-laning), which were facing funding constraints, due to pay premium outgo. However, we believe that the mechanism will benefit already commissioned projects given on premium, which would help concessionaires not to fund losses, which otherwise would have taken place. However, it may not be sufficient to improve viability of projects due to aggressive bids, especially on road projects like Kishangarh-Udaipur- Ahmedabad (KUA). The premium restructuring is short-term measure to kick-start the stuck projects on assumption that traffic will improve in latter part of the concession period, which will not benefit under construction projects, as it gives no incentives for the developers to start their projects. Will benefit projects that are commissioned like Ahmedabad-Vadodra, TumkurChitradurga owned by IRB Infrastructure (will improve the NPV/project valuation). About 72% of the projects are not commissioned tendered in FY12, and 53% of projects were given on premium, where the project cost has escalated, which gives no incentive for these developers, considering the financial tightness of some of the developers holding these projects to apply for premium restructuring principle. The projects are broadly categorized into four segments: a) projects wherein developers are prepared to make progress based on the original bidding parameters as long as the NHAI fulfills its obligations, b) projects that need to be terminated with a penalty in cases, where the concessionaire has defaulted, c) projects that would be terminated and re-bid, but without a penalty in cases where the concessionaire has defaulted and the NHAI has failed to meet its obligations, and d) projects wherein concessionaires may be willing to make progress with some changes to bidding conditions (such as premium restructuring). Recently, the NHAI scrapped four road projects without penalising the developer as wildlife clearance was still pending. Kota-Jhalawar road project (80km, a 4-laning project won by Keti Construction) Meerut-Bulandshahr (60km, a 4-laning project won by C&C Construction) Rampur-Kathgodam (93km, a 4-laning project won Era Infrastructure) Agra-Etawah (125km, a 6-laning project, won by Ramky Infrastructure) Amravati-Jalgoan , Jalgoan Maharashtra (483 km given back by L&T ) We have noticed that developers are weighed down by economically unviable road projects as a result of aggressive biddings and due to lack incentives to help them keep the projects in their kitty (in some cases the performance guarantee was not submitted, which forms 1% of the project cost). We believe the solution to kick-start these projects that are weighed down due to financial closure is to re-invite them for re-bidding, which would attract serious developers and discover a new premium or a grant base. 72% of projects awarded in FY12 yet to commence construction The NHAI awarded 16,889km of road projects over FY10-14, both in BOT and EPC mode, with 96% of the projects on a BOT basis. However, the strong tendering activity did not corroborate the real progress on the execution front. We have observed that of the total 47 projects tendered during FY12, only thirteen projects commenced construction activity till June 2014, increasing the average time to begin construction after a BOT project is awarded to 27 months (the difference between the LOA date and till date). Among the 11 projects tendered in FY13, only two have started construction, which implies that the average time to commence construction is 12-15 months, as 80% of the projects were tendered in 1HFY13. Of 47 projects which were tendered in FY12, 53% (25 projects) were tendered out in premium mechanism, of which two projects are allowed for premium restructuring and 13 (27%) projects have started construction (which includes the two projects given principle approval for premium restructuring), which implies that large number of projects to come for re-bidding . Emkay Research July 2, 2014 2 Sector Update Construction Exhibit 1: Out 47 projects tendered during FY12, only thirteen projects commenced construction till date Construction Start date Premium Km Type May-11 45 BOT Apr-12 Aug-11 163 BOT May-13 Transitory-OJSC corporation May-11 176 Annuity Apr-12 Madhucon projects Nov-11 64 BOT Keti construction Apr-11 88 BOT Era infra-OJSC-SIBMOST Nov-11 93 BOT Y MH/KNT Border Sangareddy L&T IDPL Nov-11 145 BOT Y Hospet Chitradurga Ramkey infra Nov-11 120 BOT Y 4-laning Solapur-Bijapur Sadbhav eng Mar-12 110 BOT Y 4-laning of Cuttcuk-Aangul Ashoka Buildcon Nov-11 12 BOT Y 4-laning of UP Harayana border-Yamunagar-Saha-Barwala Gammon Infra Mar-12 107 BOT 4-laining of Solapur-Maharashtra/KTK section Coastal-srie Consortium Dec-11 100 BOT 4-laning of Rohtak-Jind Vijai infra Dec-11 48 BOT Oct-13 4-laining of Mulbagal-Karnatka/AP Border JSR Construction Mar-12 22 BOT May-13 4-laining of Kiratpur ner chowk IL&FS transportation Feb-12 84 BOT Nov-13 Beawer-Pali-indwara L&T IDPL May-11 244 BOT Dec-11 2-laining with PS Motihari-Raxaul Tantia-Jiangsu Jan-11 69 BOT Oct-11 4-laning of Punjab-Harayana border-Jind Unity Infra Mar-12 68 BOT 2-laning of Jowai-Meghalaya/Assam border Simplex infra Mar-12 102 BOT Patna Buxar Gammon infra Nov-11 124 BOT 4- laning of Obedullnganj-Betul Transitory Feb-12 125 BOT 4-laning of Khagaria-Bakhtiarpur Navayuga Engineering Mar-12 112 4-laning of Hoskote-Dobbaspet Transitory-OJSC Consortium Mar-12 80 BOT 4-laining of Jalgaon-Maharashtra/Gujarat L&T IDPL Mar-12 208 BOT 4-laining of Amravati-Jalgoan L&T IDPL Mar-12 275 BOT Jabalpur to Lakhanadone Gannon Dunkerley Jul-11 80 BOT 4-laning of Gwalior-Shivpuri Essel infraprojects Sep-11 125 BOT Y 4-laning of Shivpuri-Dewas GVK Transportation Sep-11 330 BOT Y 4-laning of Raipur-Bilaspur IVRCL Asset holding Nov-11 126 BOT Rehabitation & upgradation to Birmitrapur to barkote Gammon infrastructure Mar-12 125 BOT Y 4-laning to Hospet-Bellary-Karnataka/AP PNC Infratech-BF utility Oct-11 95 BOT Y 4-laning of Mahulia to Behgora to Kharagpur Simplex infrastructure Dec-11 127 BOT Y 4-laning of Gomti-Chauraha-udaipur Sadbhav Engg, Arvee Mar-12 79.3 BOT 4-laning of Meerut-Bulandshahar C&C construction Sep-11 66 BOT 4-laning of Lucknow-Sultanpur Essar-Atlanta(JV) Oct-11 125 BOT 2-laning of Muzaffarpur-Barauni KNR, frischmann prabhu Oct-11 107 BOT Lucknow-Raibareli Essel infratructure Nov-11 70 Annuity 4-laning of Angul, Sambalpur Abhijit Roads Nov-11 153 BOT 4-laining of Jabalpur-Katni-Rewa Soma Tollways Aug-11 225 BOT Jul-12 6-laning of Gundugolanu-Rajamundry IVRCL asset & holding Mar-12 120 BOT Jul-12 6-laning of Anandapuram-visakapatnam-Anakapalli Transtroy-OJSC corporation Mar-12 58 BOT Ahmedabad to Vadodra IRB infrastructure Apr-11 102 BOT 6-lanining of Aurangabad-Barwa Adda KMC construction Mar-12 221 BOT Vijaywada-Gundugolanu Gammon Infra Feb-12 103 BOT Eatawah-Chakeri (Kanpur) Oriental structural Nov-11 160 BOT Agra-Etawah Bypass Ramky Infra Nov-11 124 BOT 6-laning of Kishangarh-Udaipur-Ahmedabad GMR Infra Sep-11 555 BOT Projects Bidder Nagpur-Wainganga bridge JMC projects, Artefact projects Panikholi-Rimoli Gayatri projects 2 laning of Kisnagiri-Tindivanam Vijaywada-Machhlioatnam Kota -Jhalwar Rampur-Kathgodam Award date Y Y Y Y Y Y Apr-13 Y Y Jan-13 Y Y Source: Emkay Research, NHAI Emkay Research July 2, 2014 3 Construction Sector Update EPC to propel momentum in FY15E-16E As awarding activity has stagnated in FY13 and FY14 for various reasons discussed above, the NHAI is trying to make progress to get the order momentum back on track via awarding EPC projects. In FY14E the NHAI has awarded six projects of 728km via the EPC route. We have seen that that there has been aggressive bidding across EPC projects, since the EPC qualification document, as per our understanding, encourages participation with no cap on the number of bidders (it is leant that some bidders have quoted at a 30% discount to the NHAI benchmark cost) in small-size projects of Rs3bn (20 bidders) and project size of Rs3-5bn (10 bidders). We believe that the total opportunity size for EPC projects would be Rs148bn. The government plans to set up a finance corporation with a corpus of Rs1 trn, in partnership with Japanese investors, to fund projects in the road sector. The Japanese partners are likely to have a 26% stake in the corporation, with assured returns of 9%. Toll revenue of around Rs50bn, which the road transport ministry gets, would be securitised to raise money. We believe that if stalled projects earlier given on BOT projects, which according to us would be around 2269km, giving opportunity size Rs340bn, considering that 50% of this comes via EPC route (NHAI can lower the project cost if gets tendered via EPC by 10%-12%) might create financial constraint for NHAI, which can be resolved by further bond raising. We consider this aggressive bidding in EPC projects as generation of negative value for bidders, as: a) scalability of margins is capped in EPC, b) project value is at risk due to delays in land acquisition (this would increase overheads), and c) if any change in scope of work, which ultimately would put project completion at risk. Emkay Research July 2, 2014 4 Sector Update Construction Exhibit 2: EPC Projects to get tendered Road Stretch State (kms) Cost (Rs.mn) Bheem-Parsoli including Bheem & Parsoli Bypass Parsoli-Gulabpura Jhalawar-Rajasthan/ Madhya Pradesh Border Merta City-Lambia-Jaitaran-Raipur Raipur-Bheem (Jassa Khera) Ambedkarnagar-Raebareilly (2 lane) Raebareilly-Banda (2 lane) Ladnu Nimbi Jodhan-Degna-Merta City (2 lane) Bhilwara-Ladpura (2 lane) Padhi-Dahod (2 lane) Unaira-Gulabpura (2 lane) Sitarganj-Tanakpur (2 lane) Karauli-Dholpur (2 lane) Biharsharif-Barbigha-Mokama (2 lane) Chhapra-Rewaghat-Muzzaffarpur (2 lane) Patna-Gaya-Dhobi (4 lane) Jalandhar-Amritsar (6 lane) Thanjavur-Pudukkotai (2 lane) Tirumayam-Mannamadurai (2 lane) Bareilly-Sitarganj (2 lane) Uncha Nagar-Khanuawa-Roppas-Dholpur (4 lane) Bar-Bilara-Jodhupur (2 lane) Barmer-Sanchor-Gujarat Border (2 lane) Two laning of NH-222 with ajunction at NH-211 To Manwath Widening & streghtening of Jodhpur-Barmer section Two laning of Malshej Ghat-Ane Ghat Two laning of AneGhat-Ahmednagar Bypass section Two laning of Panchalakona-Yerpedu Rajasthan Rajasthan Rajasthan Rajasthan Rajasthan Uttar Pradesh Uttar Pradesh Rajasthan Rajasthan Rajasthan Rajasthan Uttarakhand Rajasthan Bihar Bihar Bihar Punjab Tamil Nadu Tamil Nadu UP Rajasthan Rajasthan Rajasthan 33.0 36.3 62.2 52.8 32.4 155.9 133.3 139.0 67.8 85.6 214.0 52.2 100.9 56.3 75.0 127.2 20.0 55.2 77.7 74.5 75.0 125.0 154.0 1,000 1,140 1,770 1,580 1,490 4,960 3,510 3,680 2,370 2,790 5,710 2,200 2,890 1,940 3,050 10,270 4,930 1,700 2,520 2,970 - Maharashtra 102.0 Rajasthan Maharashtra Maharashtra Tamil Nadu Total Status Awardee Awarded Awarded Awarded Awarded Awarded Bids invited Bids invited Awarded Bids invited Proposal given RFP stage Awarded - GR Infraprojects GR Infraprojects Dilip Buildcon GR Infraprojects GR Infraprojects 3270 Awarded L&T 85.6 60.6 51.4 84.0 2120 2930 Awarded Awarded Sadbhav eng Ashoka Buildcon 2090 Awarded KNR Construction 2,388.92 72,880.00 Dinesh chandra R aggarwal Infracon Zignego Company -GHV India VIL Source: NHAI, Emkay Research Exhibit 3: Other EPC projects to get tendered Road Stretch Ramanathapuram-Dhanushkodi Ranchi-Birmitrapur Jharkhand Ranchi-Nagar Udaipur-Kumdal Naya Kheda-Jhadol- Som-Nalwa Daiya-Idar Uncha Nagla-Khanuawa-Roppas-Dholpur Bareilly-Sitarganj Pathalgaon-Chattisgarh/ Jharkhand border Ambikapur-Pathlgaon Indo Nepal Border-Ghaghra Bridge Barabanki-Bahraich-Nanapar-Rupaidiha Gorakhpur-Ferenda-Nautanwa-Sonouli Pundlbari-Baxirhat Bilaspur-Ambikapur Kattipudi-Digmaru Digmarru-Ongole Andhra Pradesh Kollam-Kazhuthurty Kerala Kozikhode-Palakkad Kerala AP border-Nirmal Baxirhat-North Salmara Assam Dimapur-Numaligarh Assam Kollam-Kumily Kerala State NH Length km Tamil Nadu Jharkhand Jharkhand Rajasthan Rajasthan Uttar Pradesh Chhattisgarh Chhattisgarh Uttar Pradesh Uttar Pradesh Uttar Pradesh West bengal Chhattisgarh Andhra Pradesh Andhra Pradesh Kerela Kerela Andhra Pradesh Assam Assam Kerela 49 23 75 58E 123 74 78 78 233 28C 29E 31 111 214 214A 208 213 222 31 39 220 70 198 265 154 80 87 131 84 122 152 99 46 190 65 255 82 75 54 100 100 191 2600 Total (Km) Source: NHAI, Emkay Research Emkay Research July 2, 2014 5 Sector Update Construction Features of EPC model concession agreement It is stringent on technical criteria, where EPC contracts have set minimum criteria of 2.5x the estimated project cost for projects and construction business (both highways and other core sectors combined) carried out by the bidder over the past 5 financial years. This compares with the BOT contract requirement of 1x the project cost’s worth of project business (highways and other core sectors) accumulated over the past 5 years. Leeway provided on financial net worth. The concession agreement currently provides leeway in terms of minimum net-worth threshold, which is at 10% of the project cost as against 25% of the project cost for BOT contracts. DLP (defect liability period) of 2 years on completion of the project highway and additional DLP for major bridges and structures of 3 years (total 5 years). Defined maintenance period of 2 years after the completion of work; 1.5% and 2% of the contract price to be paid to the contractor in the first and second year, respectively. Incentive for the contractor for early completion in the form of a bonus. The contractor cannot sub-contract any work in more than 70% of the total project length. The EPC contract allows for a JV of maximum three players, with the lead member responsible for satisfying 60% of technical and financial requirements (others have to satisfy 30% of requirements). This is in addition to the weighted score exceeding the technical and financial requirements. Damages up to 1% of the project cost would be paid by the authority on account of any delay from their side. Exhibit 4: BOT Projects to be tendered Road Stretch State (kms) Cost (Rs.mn) Barwa Adda-Panagarh West Bengal 122.9 16,650 Jabalpur-Lakhnadon Madhya Pradesh Bhavnagar-Verawal (4 lane) Gujarat Yadgiri-Warangal (4 lane) Andhra Pradesh Hospet-Hubli (4 lane) Karnataka Status Work Awarded to ITNL 80.8 7,770 Bids invited 260.0 32,400 Bids invited 99.0 9,570 143.3 12,930 NA Bids to be reinvited Numaligarh-Jorhat (4 lane) Assam 51.2 5,850 No bids received Ghoshpukur-Salsabari (4 lane) West Bengal 154.9 22,120 Bids to be invited Karaikudi-Ramanathapuram (2 lane) Tamil Nadu 80.0 3,360 Bids to be reinvited Demoh-Dibrugarh (4 lane) Assam 46.0 4,730 No bids received Jorhat-Demoh (4 lane) Assam 81.8 8,750 No bids received Chas-Ramgarh (2/4 lane) Jharkhand 78.3 2,980 Approved by SFC. RFQ invited Aurangabad-Vedishi (4 lane) Maharashtra 189.1 18,710 Chandikhole-Dubari-Bhuban (4 lane) Odisha 62.2 6,520 Parwanoo-Shimla (4 lane) Himachal Pradesh 89.6 22,930 Chhutmalpur-Saharapur-Yamunagarh-Haryana/UP border Uttarakhand/ UP 104.8 10,240 Eastern Peripheral expressway (6 lane) Haryana/ UP 135.0 Solapur-Vedishi (4 lane) Maharashtra 98.7 9,700 145.8 13,320 177 9,220 Hissar-Dabwali (4 lane) Haryana Jabalpur-Mandla Chipli section of NH12A Madhyapradesh Katni -Shahdol-Anooppur-chhattisgarh border section of NH-78 Madhyapradesh Zirakpur-Patiala section of NH-64 Punjab Punjab 50.7 5,360 174 18,990 157 65,710 2,582.10 307,810.00 Amritsar-Bhatinda section of NH-15 Punjab Punjab Ambala Kaithal, Haryana Haryana Delhi-Meerut Expressway, Delhi/Uttar Pradesh Delhi/UP Kazhakootam-Mukkola section of NH-47 , kerela Kerela Total Work awarded to IRB Infrastructure Bids invited Proposal considered by PPPAC and deferred Proposal considered by PPPAC and deferred No bids received, project to be restructured Work awarded to IRB Infrastructure PPPAC proposal circulated Source: NHAI, Emkay Research Emkay Research July 2, 2014 6 Sector Update Construction Exhibit 6: Construction work per km Exhibit 5: Order activity remains sedate 3000 2500 2000 1500 6380 1000 753 635 2848 2693 1784 2249 637 FY14 FY13 FY12 FY11 FY10 0 FY09 975 1682 2205 FY08 1116 500 FY07 FY12 FY11 FY10 FY09 643 FY14 1145 FY08 1390 FY07 1608 FY13 3360 FY06 5058 FY06 7000 6000 5000 4000 3000 2000 1000 0 Length completed (Km) Length awarded (Km) Source: Company, Emkay Research Source: Company, Emkay Research Exhibit 7: Awarding activity in BOT and EPC 7000 6380 6000 5058 5000 4000 3360 3055 3000 2000 1608 1390 1145 345 1000 89 1116 643 213 762 0 FY06 FY07 FY08 FY09 FY10 Length awarded (Km) BOT FY11 FY12 FY13 FY14 Length awarded (Km) EPC Source: Company, Emkay Research Emkay Research July 2, 2014 7 Sector Update Construction Exhibit 8: Competitive intensity among developers % Final Players bids preFinal Cost Length (km) bidders qualified participation (Rs bn) Date Name of Project Winners Apr-11 Ahmedabad Vadodara IRB Infrastructure 49.2 195 13 22 59% Apr-11 Beawar-Pali-Pindwara L&T 23.9 244 16 19 84% May-11 Barwa Panagarh DSC 16.7 123 9 20 45% Jul-11 Kishangarh--Ahmedabad GMR Infra 53.9 556 7 11 64% Sep-11 Gwalior Shivpuri Essel Infraprojects 10.6 125 15 28 54% Sep-11 Shivpuri Dewas GVK 28.2 330 14 19 74% Oct-11 Lucknow Sultanpur Essar - Atlanta 10.4 126 12 34 35% Nov-11 Cuttak Angul Ashoka Buildcon 11.2 112 16 27 59% Nov-11 Etawah and Chakeri (Kanpur) Oriental Structural 14.9 160 9 35 26% Nov-11 Hospet Chitradurga Ramky Infra 10.5 120 14 37 38% Nov-11 Mah/KNT- Sangareddy L&T 12.7 145 19 37 51% Nov-11 Patna - Buxar Gammon Infra 8.1 105 1 36 3% Nov-11 Raipur Bilaspur IVRCL 12.2 127 17 33 52% Dec-11 Bikaner - Suratgarh MBL Infra 5.1 172 6 33 18% Dec-11 Chittorgarh Neemachah Chetak Enterprises Ltd. Jan-12 Kiratpur - Ner chowk IL&FS Transportation Jan-12 Obdellagang - Betul Transtroy Mar-12 Amravati Jalgaon L&T Mar-12 Anadpuram- Visakhapatnam - Ankapalli Transtroy - OJSC Mar-12 Gomti Chauraha - Udaipur Sadbhav Engineering Mar-12 Hoskote - Dobaspet Transtroy - OJSC Mar-12 Jalgaon - Guj/Mah Border L&T Mar-12 Jind - Punjab/Haryana Border Unity infrastructure Mar-12 Kharagpur-Baleshwar IL&FS Transportation Mar-12 Rajahmundry - Gundugulunu IVRCL Asset Mar-12 Sikar - Bikaner Mar-12 5.1 117 9 36 25% 18.2 113 4 28 14% 9.1 121 6 36 17% 25.4 275 12 22 55% 8.4 58 6 35 17% 11.1 79 10 39 26% 7.2 80 4 36 11% 19.7 209 17 29 59% 4.4 69 5 40 13% 4.8 119 5 40 13% 16.2 121 3 35 9% IL&FS Transportation 6.3 238 1 30 9% Solapur - Bijapur Sadbhav engineering 11.0 110 16 38 42% Apr-12 Bridge across Narmada (Vadodara - Surat section) HCC 5.1 6 2 35 6% May-12 Walajahpet - Poonamallee Essel project 12.9 93 19 37 51% May-12 Goa karnataka - Kundapur IRB Infra 24.0 187 2 35 6% Jul-12 Raebareli-Jaunpur PNC Infratech 5.7 166 8 30 27% Jul-12 Coimbatore-Mettupalayam Transstroy-OJSC Consortium 5.9 54 6 35 17% Aug-12 Walayar-Vadakkancherry KNR Construction 6.8 54 1 32 3% Nov-12 Kashipur-Sitarganj Galfar Engg & Contracting SAOG 6.1 77 1 30 3% Nov-12 Rajasthan border-Fatehpur-Salasar Galfar Engg & Contracting SAOG 5.3 154 2 32 6% Nov-12 Rajsamand-Gangapur-Bhilwara 87 6.8 Sadbhav Engg Sadbhav Engg Ltd 6.8 87 1 35 3% Mar-13 Rohtak-Hissar Sadbhav Engg Ltd 9.6 99 5 34 15% Mar-13 Khed-Sinnar IL&FS Transportation Networks 13.5 138 4 40 10% Jan-14 Solapur yadeshi IRB Infrastructure 9.1 90 2 8 25% May-14 Yadeshi aurangabad IRB Infrastructure 32.0 190 3 8 38% May-14 Rajasthan -Kaithal IRB Infrastructure 23.0 166 1 8 13% Source: Company, Emkay Research Emkay Research July 2, 2014 8 IRB Infrastructure Prospects improved Your success is our success July 02, 2014 Rating Prospects improve with potential benefits from (a) premium restructuring scheme (aid near-term cashflows and value for Ahmedabad-Vadodara project), (b) new project wins in the construction arm, (c) macro recovery to help BOT business Strong cashflows from a healthy mix of operating and underconstruction assets, and moderate gearing – the key competitive differentiators in a capital-intensive business Earnings CAGR of 14% over FY14-16E, expect a CAGR of 25% in cash profits, providing the ability to fund equity in new projects. Revised FY15E/16E EPS by 13%/28%, the stock trades at 2x P/BV, 7.7x EV EBITDA on a FY16E basis Benefit of premium restructuring for AhmedabadVadodra/Tumkur-Chitradurga projects, addition of newly won projects in our valuation; revised target price to Rs262 Previous Reco Buy Buy Target Price CMP Rs262 Rs235 EPS Chg FY15E/FY16E (%) 13/28 Target Price change (%) 25 Nifty 7,635 Sensex 25,516 Price Performance (%) 1M 3M 6M 12M Absolute 19 126 144 138 Rel. to Nifty 13 99 103 83 Source: Bloomberg Construction revenue visibility kicks in with recent order wins Relative price chart 250 Rs % 90 210 62 170 34 130 6 90 50 Jul-13 -22 Sep-13 Nov-13 Dec-13 IRB Infrastructure (LHS) Mar-14 Apr-14 -50 Jun-14 Rel to Nif ty (RHS) Source: Bloomberg Stock Details Sector Construction IRB witnessed some slowdown in its construction revenues (flattish on a yoy basis) in FY14 on completion of four of its BOT projects (Talegaon-Amravati, Jaipur-Deoli, Amritsar-Pathankot and Tumkur-Chitradurga). The Ahmedabad-Vadodara project contributed the major portion of its construction business revenues at Rs19.6bn, which is 76% of FY14 construction revenues. However, over the last 4 months, the company has won three projects worth Rs70bn (EPC scope of Rs62bn), which increases the order book to Rs120bn, thereby providing EPC revenue visibility till FY17E. We expect construction at Solapur-Yedeshi and Yedeshi-Aurangabad to start in 2HFY15, as NHAI has already acquired 90% of the land, besides receiving all the required approvals for the projects, which should ease the commencement of EPC activity. However, we expect the Kaithal-Rajasthan project to start in FY16E. We expected construction revenue CAGR of 5.2% over FY14-16E. IRB IB Bloomberg 3,324 Equity Capital (Rs mn) 10 Face Value(Rs) 332 No of shares o/s (mn) 238/ 52 52 Week H/L Market Cap (Rs bn/USD mn) 78/ 1,302 Daily Avg Volume (No of sh) 6,746,169 Daily Avg Turnover (US$mn) 19.1 Shareholding Pattern (%) Mar'14 Dec'13 Sep'13 Promoters 61.7 62.3 62.2 FII/NRI 25.7 23.2 24.1 Institutions 3.0 3.8 3.6 Private Corp 1.7 3.3 3.2 Public 7.9 7.4 6.9 Source: Bloomberg Nitin Arora [email protected] +91-22-66242491 Kunal B. Soni [email protected] +91-22- 66242431 Emkay Global Financial Services Ltd. Comfortably placed to meet incremental equity; restructuring to also help Given that the equity requirement stands at Rs11bn for existing Ahmedabad-Vadodra (Rs5.9bn) and Goa-Kundapur project (Rs5.2bn), the three newly won projects adds to incremental equity requirement of Rs18bn, which will take the total equity requirement to Rs29bn. The company needs the same to infuse funds over the next 3-3.5 years. We believe, given the cash balance of Rs15bn, along with operating cashflow from BOT projects (bulk of this originates from the Mumbai-Pune project), the construction business would be sufficient to meet the equity requirement. The recent premium restructuring scheme, which offsets the lower negative cashflows from AhmedabadVadodara and Tumkur-Chitradurga projects, also supported the cashflows. However, we note that any further award wins in FY15 may put equity funding of new projects from internal cashflows under strain. (Rsmn) Financial Snapshot (Consolidated) EV/ EPS RoE APAT (Rs) % chg (%) P/E EBITDA P/BV 47.0 4,591 13.8 -17.5 16.6 17.0 9.4 2.7 51.3 5,955 17.9 29.7 19.0 13.1 8.9 2.3 29,285 55.9 6,139 18.5 3.1 17.0 12.7 7.8 2.0 30,181 56.7 6,185 18.6 0.8 15.2 12.6 7.8 1.8 EPS EBITDA YE- Net Mar Sales (Core) (%) FY14A 37,319 17,537 FY15E 45,495 23,335 FY16E 52,390 FY17E 53,196 9 Company Update Emkay © Company Update IRB Infrastructure Premium restructuring offers some relief for Ahmedabad-Vadodra project The underlying principle of premium restructuring provided some respite to AhmedabadVadodra project in terms of a cashflow mismatch. The project is likely to pay a premium outgo of Rs7.6bn over FY15-20E as against earlier assumptions of Rs23bn, which would help improve the near-term cashflows and potential net value from the project. However, we believe, even despite the restructuring scheme, the project may still potentially be suboptimal with potential equity returns of about 9%. Toll from recent project wins stabilizing at targeted levels Talegaon-Amravati: The company received partial CoD for the Talegaon-Amravati project in 1QFY14, and started toll collections equivalent to about 58% of the total length of the project. Post-tolling of full length, per day toll has improved to targeted initial levels of Rs1.5-1.6mn. Jaipur-Tonk-Deoli: The company also started tolling its Jaipur-Tonk-Deoli project in 2QFY14, and reported toll collections of about Rs186mn for 4QFY14. It currently receives toll collection equivalent to about 75% of the total tariff level. The collections imply a daily toll collection of about Rs2.8mn. Note that tolling at full rates has started from May 21, 2014. Amritsar-Pathankot: Tolling for Amritsar-Pathankot is yet to start (await approvals for 5 RoBs from the Indian Railways). The company expects tolling to start in another 1-2 quarters. Exhibit 10: EBITDA to edge higher on higher BOT revenue contribution Exhibit 9: Revenue CAGR of 18.5% over FY14-16E 35 60 50 52 40 37 15 24 10 17 5 11 16 14 18 8 - FY10 FY11 FY12 FY13 FY10 FY14E FY15E FY16E FY17E FY11 FY12 FY13 FY14E FY15E FY16E FY17E Source: Company, Emkay Research Source: Company, Emkay Research Exhibit 12: EPS to proper higher Exhibit 11: Earnings CAGR of 15% over FY14-16E 20 7.0 6.0 5.0 4.0 30 23 20 37 31 20 29 25 45 30 10 30 53 5.3 4.5 6.0 5.6 5.0 6.2 15 5.5 16 15 19 16 14 13 4.6 18 17 10 3.0 2.0 5 1.0 - FY10 FY11 FY12 FY13 Source: Company, Emkay Research Emkay Research July 2, 2014 FY14E FY15E FY16E FY17E FY10 FY11 FY12 FY13 FY14E FY15E FY16E FY17E Source: Company, Emkay Research 10 Company Update IRB Infrastructure Exhibit 14: BOT revenue CAGR of 42% over FY14-16E Exhibit 13: Construction revenue CAGR of 5.2% over FY14-16E 30 30 25 24 20 28 27 26 25 26 20 20 15 27 24 19 15 15 10 10 5 5 12 9 10 7 8 FY10 FY11 FY12 FY13 10 - 0 FY10 FY11 FY12 FY13 FY14E FY15E FY16E FY17E FY14E FY15E FY16E FY17E Source: Company, Emkay Research Source: Company, Emkay Research Exhibit 15: Total Investments (Equity, loans & advances) Project Rsmn Investments in road projects Equity Short term Long term Total Equity 611 611 978 778 611 Mumbai-Pune Expressway 778 Pune-Sholapur 451 451 451 Pune-Nashik 519 12 531 519 Ahmednagar-Karmala-Tembhurni 80 0 80 Bridge over Patalganga River-Kharpada 80 200 Long term Equity Short term Long term Total 611 778 451 451 451 534 519 519 80 80 80 80 80 80 80 80 80 222 707 929 222 872 2,297 3169 872 855 855 2,611 2611 257 18 Total 629 Bharuch-Surat 434 15 500 611 1,073 295 722 222 6 228 5,472 6344 872 2680 3,552 1,336 227 1563 1,336 566 1,902 4,653 1,117 5770 4,653 847.8 1792 355 162 1,145 1662 774 7.9 2326.3 3,109 5,501 Pathankot-Amritsar 355 Talegaon-Amravati 322 2 57 381 322 151 828 1301 364 352 1093.4 1,810 Jaipur-Deoli 390 264 272 926 780 200 1,837 2817 974.9 480.62 2924.9 4,380 Panji-Goa 311 929 1240 311.4 1,173 1484.4 311.4 1173.1 1,485 0 1,181 1337 476 476 952 1110.67 315.727 1110.7 2,537 1000 33.61 2950.0 3,984 801.6 972.92 6,558 11578.2 33,075 Tumkur-Chitradurg 1,180 Short term 1212 Thane-Ghodbunder Surat-Dahisar Loans & advances Loans & advances Thane-Bhiwandi bypass Integrated Road Development in Kolhapur FY13 FY12 FY11 Loans & advances 156 1,000 Ahmedabad-Vadodara Expressway 69 2,950 4019 MVR Infra Subtotal - Investment in road projects 8,457 6,772 742 15971 7,832 8,942 29620.4 312 1353.214 1665.2 12,846 Investments in other subsidiaries 14,939 1,775 0 - 312 957 1,269 Construction subsidiary 312 1,588 1900 Real estate subsidiary 586 1 587 586 1 587 586 1 587 Hospitality subsidiary 0 26 26 0 119.472 119.562 0.09 182 182 Sindhudurg Airport 0 182 182 0 10.124 10.22399 0.09999 211 211 898 1,796 2694 898 1483.81 2381.81 898 1351 2,249 9,354 8,570 18666 13,744 9,316 32002 15,837 7,909 Subtotal - Investment in other subsidiaries Total investments in subsidiaries 742 8,942 11,578 35,324 Source: Company, Emkay Research Emkay Research July 2, 2014 11 Company Update IRB Infrastructure Exhibit 16: FCFE of both construction and BOT business FY15 FY16 FY17 Net income (less other income) 3,131 3,500 2,819 Add: Depreciation 7,616 8,598 9,869 (44,792) (37,658) (20,973) (64) (137) (109) (34,110) (25,697) (8,394) Debt and repayments and grant 31,292 29,666 10,087 Free cash flow to equity (2,817) 3,970 1,692 FCFE from BOT Business Less: Capex Add: Working capital Free cash flow to the firm Less: Interest adj for tax 3397 2882 4534 Net surplus/(Deficit) FCFE from construction business 579.54 6,851.92 6,226.16 Equity requirement 6960 12640 9700 Ahmedabad Vdr 3760 2120 Kandapur 2870 2350 0 Solapur yadeshi 1290 1190 1430 Yadeshi Aurangabad 2850 2390 2880 Kaithal Rajasthan 1870 1650 2650 Source: Company, Emkay Research Maintain Buy with the revised target price of Rs262/share We have revised our consolidated estimates for FY15E-16E to Rs17.8/18 per share from Rs15/14 per share based on higher construction business revenues, slightly higher traffic growth assumptions for road projects, and incorporating premium restructuring scheme. We have also revised our SOTP from Rs210 to Rs262/share on account of: a) increased value of road project portfolio from Rs140/share to Rs175/share by addition of newly won projects in our valuation (increase of 20/share) and benefit from premium restructuring scheme for Ahmedabad-Vadodara and Tumkur-Chitradurga projects (increase of Rs24/share), b) higher value of construction business (by Rs8/share) on increase the E&C earnings multiple, due to a better margin trajectory. We maintain a Buy, with a revised target price of Rs262/share. Exhibit 17: Earnings upgrade by 13%/28% for FY15E/16E FY16E FY15E Change Earlier Revised Change Earlier Revised Sales 45,041 45,495 1% 52312 52,390 0% EBIDTA 21,794 23,235 7% 25688 29,285 14% 48.4 51.1 49.1 55.9 4,780 5,406 13% 4659 5,975 28% 14.4 16.3 13% 14.0 18.0 28% EBIDTA (%) Net Profit EPS Source: Emkay Research Emkay Research July 2, 2014 12 Company Update IRB Infrastructure Exhibit 18: SOTP fair value @262 EPC BOT SPV Asset Operated Holding Valuation Measure Disc rate Value (Rs mn) Val/Share Modern Road Makers EPC Business 100% PER 8 25972 78.1 PV of O&M Contracts PV of O&M Contracts 100% NPV 13.5% 3,133 9.4 Value of Contruction segment - (a) Value of Construction segment - (a) 29,105 88 Mhaiskar Infrastructure Mumbai Pune Expressway & NH4 100% FCFE 12.5% 16,529 49.7 Surat Dahisar SPV Surat Dahisar 90% FCFE 13.5% 2,593 7.80 IDAA Infrastructure Bharuch Surat 100% FCFE 13.5% 2,352 7.1 MMK Toll Road Mohol-Mandrup Road 100% FCFE 13.5% -139 -0.4 IRB Infrastructure Kharpada-Patalganga Bridge 100% FCFE 13.5% 251 0.8 NKT Road & Toll Ahmednagar Tembhurni Road 100% FCFE 13.5% 251 0.8 Thane Ghodbunder Toll Road Thane Ghodbunder 100% FCFE 13.5% 1,349 4.1 ATR Infrastructure Pune Nashik 100% FCFE 13.5% 474 1.4 Aryan Toll Road Pune Sholapur 100% FCFE 13.5% 700 2.1 Ideal Road Builders Thane Bhiwandi Bypass 100% FCFE 13.5% 1,803 5.4 IRB Kolhapur IRDC Kolhapur City Roads 100% FCFE 14.5% 3,703 11.1 Namakkal - Omallur Namakkal - Omallur - NH-7 100% FCFE 13.0% 1,646 5.0 Amritsar Pathankot Amritsar Pathankot 100% FCFE 14.0% 7,623 22.9 Jaipur - Deoli Jaipur - Deoli 100% FCFE 14.0% 9,146 27.5 Amravati Talegaon Amravati Talegaon 100% FCFE 14.0% 3,426 10.3 Tumkur Chitradurga Tumkur Chitradurga 100% FCFE 14.0% -729 -2.2 Ahmedabad Vadodara Ahmedabad Vadodara 100% FCFE 15.5% 2,379 7.2 Goa - Kundapur Goa - Kundapur 100% FCFE 14.5% 5,813 17.5 Solapur yadeshi Solapur yadeshi 100% FCFE 13.5% 1,903 5.7 Yadeshi Aurangabad Yadeshi Aurangabad 100% FCFE 13.5% 2,085 6.3 Kaithal Rajasthan Kaithal Rajasthan 100% FCFE 13.5% 2,247 6.8 65,407 197 Gross value of BOT Gross value of BOT Add: PV of Loans to SPV Add: PV of Loans to SPV Less : Net Debt at Parent Level 2,272 6.8 Less : Net Debt at Parent Level -9,630 -29 Value of BOT - Net of debt - (b) Value of BOT - Net of debt - (b) 58048.6 174.7 Total Total Value - (a+b) 87,154 262 Source: Company, Emkay Research Emkay Research July 2, 2014 13 IRB Infrastructure Company Update Key Financials (Consolidated) Income Statement Balance Sheet Y/E Mar (Rsmn) FY14A FY15E FY16E FY17E Y/E Mar (Rsmn) FY14A FY15E FY16E Net Sales 37,319 45,495 52,390 53,196 Equity share capital 3,324 3,324 3,324 3,324 1.2 21.9 15.2 1.5 Reserves & surplus 32,283 40,290 53,800 61,493 19,782 22,160 23,105 23,015 Net worth 35,607 43,614 57,124 64,817 1,799 1,815 1,845 1,898 356 308 244 144 0 0 0 0 Growth (%) Expenditure Employee Cost Other Exp SG&A EBITDA 1,482 1,453 1,249 1,259 17,537 23,335 29,285 30,181 7.4 33.1 25.5 3.1 47.0 51.3 55.9 56.7 Growth (%) EBITDA margin (%) Depreciation Minority Interest Secured Loans Unsecured Loans Loan Funds Net deferred tax liability Total Liabilities 4,771 6,909 8,491 9,196 12,766 16,427 20,794 20,985 34.2 36.1 39.7 39.4 Other Income 1,214 1,092 1,260 1,487 Interest expenses 7,562 9,273 13,176 13,700 PBT 6,419 8,246 8,878 8,772 Current Assets Tax 1,823 2,340 2,802 2,688 Inventories 28.4 28.4 31.6 30.6 Adjusted PAT 4,591 5,955 6,139 6,185 Growth (%) -17.0 28.5 2.9 0.1 12.3 13.0 11.6 11.4 Other current assets (Profit)/loss from JVs/Ass/MI 5 -48 -63 -101 Adj. PAT After JVs/Ass/MI 4,591 5,955 6,139 6,185 0 0 0 0 Reported PAT 4,591 5,955 6,139 PAT after MI 4,591 5,955 Growth (%) -17.5 EBIT EBIT margin (%) Effective tax rate (%) Net Margin (%) Gross Block Less: Depreciation FY17E 93,980 131,593 152,464 158,608 8,965 8,965 8,965 8,965 102,945 140,558 161,429 167,573 247 247 247 247 139,155 184,727 219,045 232,780 88,916 102,154 143,738 160,352 3,372 3,925 4,500 5,098 Net block 85,544 98,229 139,238 155,254 Capital work in progress 44,867 80,296 75,004 145 145 145 145 27,064 23,902 23,120 22,728 2,683 2,385 2,787 2,678 55 851 907 902 15,806 12,148 10,907 10,630 8,519 8,519 8,519 8,519 0 0 0 0 Current lia & Prov 17,986 17,367 17,983 16,844 Current liabilities Investment Sundry debtors Cash & bank balance Loans & advances 71,976 15,099 14,479 15,095 13,956 Provisions 2,888 2,888 2,888 2,888 6,185 Net current assets 9,078 6,536 5,137 5,884 6,139 6,185 Misc. exp 0 0 0 0 29.7 3.1 0.8 FY14A FY15E FY16E FY17E PBT (Ex-Other income) 5,205 7,154 7,618 7,285 Profitability (%) Depreciation 4,771 6,909 8,491 9,196 EBITDA Margin Interest Provided 7,562 9,273 13,176 13,700 0 0 0 0 117 -1,117 158 Tax paid -1,823 -2,340 Operating Cashflow 15,832 Capital expenditure Free Cash Flow E/O items Cash Flow Total Assets 139,634 185,206 219,524 233,260 Key Ratios Y/E Mar (Rsmn) FY14A FY15E FY16E FY17E 47.0 51.3 55.9 56.7 Net Margin 12.3 13.0 11.6 11.4 ROCE 11.7 11.4 11.8 10.9 -1,024 ROE 16.6 19.0 17.0 15.2 -2,802 -2,688 RoIC 20.1 19.2 18.4 14.8 19,879 26,641 26,469 Per Share Data (Rs) -31,682 -55,023 -44,208 -22,185 EPS 13.8 17.9 18.5 18.6 -15,851 -35,144 -17,567 4,284 CEPS 28.2 38.7 44.0 46.3 1,214 1,092 1,260 1,487 BVPS 87.6 101.4 115.6 129.8 475 0 0 0 2.8 0.0 0.0 0.0 -29,993 -50,497 -34,152 -17,755 0 0 0 0 Loans Taken / (Repaid) 23,884 37,614 20,871 6,144 Interest Paid -7,562 -9,273 -13,176 -13,700 Dividend paid (incl tax) -1,065 -1,382 -1,424 -1,435 Income from investments 0 0 0 Others 0 0 15,258 Other Non-Cash items Chg in working cap Other income Investments Investing Cashflow Equity Capital Raised Y/E Mar DPS Valuations (x) 17.0 13.1 12.7 12.6 P/CEPS 8.4 6.1 5.3 5.1 P/BV 2.7 2.3 2.0 1.8 EV / Sales 4.4 4.5 4.4 4.4 0 EV / EBITDA 9.4 8.9 7.8 7.8 0 0 Dividend Yield (%) 1.2 0.0 0.0 0.0 26,960 6,271 -8,991 Gearing Ratio (x) 1,096 -3,659 -1,241 -277 3.0 3.8 3.9 3.6 Opening cash position 14,710 15,806 12,148 10,907 Net Debt/EBIDTA Closing cash position 15,806 12,148 10,907 10,630 Working Cap Cycle (days) Financing Cashflow Net chg in cash Emkay Research July 2, 2014 PER Net Debt/ Equity 5.0 5.5 5.1 5.2 -65.8 -45.0 -40.2 -32.6 14 Sadbhav Engineering Standing tall Your success is our success July 02, 2014 Rating Construction revenue recovers, momentum to continue in FY15E/16E (revenue/EPS CAGR of 15% over FY14E-16E), increased share of mining & irrigation in backlog augur well Well placed to fund equity requirement of Rs3.5bn for BOT projects over FY14-16E by: a) cashflows from the construction business, b) ARRIL securitization proceeds, c) recovery of receivables, and d) dilution at the SIPL level 63% of equity investment in BOT assets becomes operational, toll revenue CAGR of 37% over FY14-16E, revised average portfolio traffic growth to 5.7%, incorporate premium restructuring impact Given a large order backlog (stands at Rs90bn 4x revenue visibility), with improvement in EBITDA margins, it has potential to generate further growth capital. Maintain a Buy, with a revised target price of 250 (earlier Rs212) Previous Reco Buy Buy CMP Target Price Rs249 Rs202 EPS Chg FY15E/FY16E (%) NA Target Price change (%) 17 Nifty 7,635 Sensex 25,516 Price Performance (%) 1M 3M 6M 12M Absolute 17 108 111 111 Rel. to Nifty 11 83 75 62 Source: Bloomberg Relative price chart 225 Rs % 80 190 54 155 28 120 2 85 50 Jul-13 -24 Sep-13 Nov-13 Dec-13 Mar-14 Sadbhav Engineering (LHS) Apr-14 -50 Jun-14 Rel to Nifty (RHS) Source: Bloomberg Strong construction momentum to continue in FY15E-16E With the order backlog providing 4x revenue visibility, Sadbhav Engineering Ltd.’s (SEL) revenue growth is expected to be propelled over the next 6-8 quarters. We build in construction revenue CAGR of 15% over FY14-16E, of which the road segment (both cash contracts and BOT assets) would account for 65% of the revenue share, mining 18% and irrigation 17%. The backlog consists of: 1) a 34% share of BOT road projects, 2) 17% of road cash contracts, 3) 22% of irrigation projects, and 4) 27% of mining projects. EBITDA margin expands on higher contribution from mining arm Stock Details Sector Construction SADE IB Bloomberg 152 Equity Capital (Rs mn) 1 Face Value(Rs) 152 No of shares o/s (mn) 213/ 51 52 Week H/L Market Cap (Rs bn/USD mn) 31/ 511 Daily Avg Volume (No of sh) 311,498 Daily Avg Turnover (US$mn) 0.8 Shareholding Pattern (%) Mar'14 Dec'13 Sep'13 Promoters 48.7 48.8 48.8 FII/NRI 16.0 16.4 18.0 Institutions 26.2 26.5 23.7 Private Corp 6.2 5.5 6.6 Public 2.9 2.8 2.9 Source: Bloomberg Nitin Arora [email protected] +91-22-66242491 Kunal B. Soni [email protected] +91-22- 66242431 Emkay Global Financial Services Ltd. SEL reported an EBITDA margin of 10.3% in the last 3 quarters of FY14E; however, in Q4FY14 it clocked a margin expansion of 11%. It attributes the margin expansion to the operating leverage (on the back of a strong pick-up in revenue), as well as to higher revenues from mining, a high-margin business, which clocked an average EBITDA margin of 18-20%. Moreover, In terms of profitability, the mining segment has been more profitable than irrigation contracts, since SEL sub-contracts 10-12% of its work orders in the irrigation segment, which has an EBITDA margin of 5-5.5%. We expect EBITDA margin expansion of 80bps over FY14-16E to 11%/11.4% in FY15E/16E. Well placed to fund incremental equity of Rs3.5bn for BOT projects With the cancellation of the Solapur project, SEL’s equity requirement has come down to Rs3.6bn over FY14E-16E. In our view, the company would be able to meet the requirement from: a) operating cashflows from the standalone construction business, b) proceeds from ARR securitization, c) potential for further securitization/sale of operational BOT projects, d) receivables from the Dhule project, and e) dilution of the stake at SIPL level. So far, SEL has invested equity worth Rs12bn in BOT road assets. In Q4FY14, the company also raised about Rs1.3bn in non-convertible debentures for 6 years (Rsmn) Financial Snapshot (Standalone) YE- Net EBITDA EPS Mar Sales (Core) FY13A 18,110 1,558 8.6 127 0.8 -91.0 FY14A 23,581 2,494 10.6 1,445 7.0 736.4 16.4 28.8 FY15E 28,237 3,095 11.0 1,117 7.4 5.2 11.3 FY16E 31,312 3,566 11.4 1,414 9.3 26.6 12.9 (%) APAT EPS RoE (Rs) % chg (%) EV/ P/E EBITDA P/BV 1.6 241.3 24.4 3.7 15.4 3.3 27.4 12.3 3.0 21.7 10.8 2.6 15 Company Update Emkay © Company Update Sadbhav Engineering Developments over the last 4 months Proceeds from NCDs, impending securitization to fund equity requirement SEL raised about Rs1.3bn in non-convertible debentures for 6 years (including moratorium in principal payments for the first 3 years). It indicated that it was close to completing securitization of the Aurangabad-Jalna project, which is expected to raise Rs2.5bn. These sources of funding are likely to support the Rs3.4bn pending equity requirement for projects under construction. Received approval for premium deferment on key projects The company received approvals to defer premium for its Rohtak-Panipat and HyderabadYadgiri projects. For the third project, which SEL won at a premium (Gomti ka Chauraha), the NHAI will give approval for premium restructuring after achieving CoD. Tolling at nine check-posts; expects to toll 16 by December 2014. The company has received completion certificates for 11 out of its 22 check-posts in the Maharashtra Border Check-post project. Out of these, it is collecting revenues from nine check-posts. It also disclosed that the five check-posts were close to achieving CoD, which would become operational by December 2014. Exhibit 19: FCFE from BOT and construction segment FCFE from BOT Projects FY15E FY16E FY17E Net income (less other income adj for tax) (1,695) (1,603) (1,235) Add: Depreciation 1,185 1,290 2,796 Less: Capex (13,975) (12,824) (4,685) Free cash flow to the firm (14,484) (13,137) (3,124) 9,741 8,244 3,008 (4,744) (4,893) (116) FCFE from construction buisness 1,533 2,346 - Cash flow from ARR secuiritisation 2,210 310 NCD raised at SIPL level 1,300 Debt and repayments Free cash flow to equity Cash surplus/Deficiet 300 (2,237) (116) Debt repayment adjusted for stake at SIPL level 354 534 804 Stake (%) Total Invested Pending 100 810 810 80 416.8 417 Source: Company, Emkay Research Exhibit 20: Equity Requirement Projects Aurnagabad Jalna Ahmedabad Ring road Nagpur seoni 100 489 489 Dhule palesnar 27 955 955 Mumbai Nashik 20 104 104 Mah Border check post 90 2,970 2970 100 2,436 2436 Rohtak Panipat Hydarabad Yadgiri 60 601 601 Bijapur hungund 77 1,055 1,055 Gomti Ka Chauraha 100 3,115 1037.2 2077.8 Rajsamand -Bhilwara 100 1,333 867 463 Rohtak Hissar 100 1,077 542.8 515.4 Karnataka State highway project 100 390 0 390 15752 12284 3446.2 Total Source: Company, Emkay Research Emkay Research July 2, 2014 16 Company Update Sadbhav Engineering Maintain Buy – Revised target price to Rs250/share Given the a) large order backlog (Rs90bn, 4x years of construction revenue visibility), b) recovery in EBITDA margins due to a recovery in revenues, as well as a higher revenue contribution from the mining segment, c) 63% of the BOT projects are operational, we expect a recovery in earnings over FY14E-16E (revenue and earnings CAGR of 15% each), with an improvement in the EBITDA margin (EBITDA CAGR of 20% over FY14E16E) expansion, with the EBITDA to margin to remain in the range of 11-11.4%. The stock trades at FY15E/16E EV EBITDA of 12.3x/10.8xand P/B of 3x/2.6x. Our target price of Rs250 is based on the sum-of-the-parts (SOTP) valuation method, which comprises the following: Rs89/share value (adjusted for debt at the construction business) from the standalone construction business (valued at 6x one-year forward FY16E EBITDA). Rs160share from the road BOT projects (based on one-year forward FCFE valuations. Exhibit 21: SOTP Fair value at Rs250/share Value Rsmn % stake EPC Business 13524 100 Sadbhav Infrastructure Projects Buisiness Value adjusted for stake Per share (Rs) 89 Methodology Based on FY16E EBITDA - 6X for construction business Based on FCFE valuation of projects 41237 80 30246 Aurangabad Jalna 1723 100 1722.6 9.1 Cost of Equity 14% Ahmedabad Ring Road 3182 80 2545.6 13 Cost of Equity 14% Nagpur-Seoni 261 100 261.2 1 Cost of Equity 14% Dhule 4726 27 1276.0 7 Cost of Equity 14% Mumbai Nasik 5465 20 1093.1 5.8 Cost of Equity 14% 11237 90 10113.5 53 Cost of Equity 14% 4143 100 4143.2 22 Cost of Equity 14% MBCPNL Rohtak-Panipat 481 60 288.7 1.5 Cost of Equity 14% Bijapur-Hungund 3387 77 2608.1 14 Cost of Equity 14% Gomti ka Chaurah 2963 100 2963.0 15.7 Cost of Equity 14% 434 100 434.2 2 Cost of Equity 14% 2360 100 2360.1 12.5 Cost of Equity 14% 874 50 436.9 2.3 Cost of Equity 13% Hyderabad-Yadgiri Rajsamanad-Bhilwara Rohtak hissar Karnataka BOT Value per share 160 Target price 249 Source: Emkay Research Emkay Research July 2, 2014 17 Sadbhav Engineering Company Update Key Financials (Standalone) Income Statement Balance Sheet Y/E Mar (Rsmn) FY13A FY14A FY15E FY16E Y/E Mar (Rsmn) FY13A FY14A FY15E Net Sales 18,110 23,581 28,237 31,312 Equity share capital 151 152 152 152 -32.3 30.2 19.7 10.9 Reserves & surplus 8,174 9,189 10,200 11,508 Expenditure 16,552 21,087 25,142 27,746 Net worth 8,325 9,341 10,351 11,659 Raw Material 2,684 3,301 3,981 4,227 428 602 678 750 Growth (%) Employee Cost Construction Expenses Minority Interest 0 0 0 0 Secured Loans 4,656 8,133 7,500 8,000 Unsecured Loans 2,974 500 250 500 Loan Funds 7,630 8,633 7,750 8,500 12,513 16,148 19,427 21,573 EBITDA 1,558 2,494 3,095 3,566 Growth (%) -46.3 60.1 24.1 15.2 Net deferred tax liability 8.6 10.6 11.0 11.4 Total Liabilities EBITDA margin (%) Depreciation 317 357 357 357 16,272 18,330 18,458 20,516 Gross Block 5,148 7,301 7,901 8,401 Less: Depreciation 1,845 2,319 2,844 3,414 3,303 4,982 5,058 4,987 323 474 524 571 1,235 2,020 2,570 2,996 6.8 8.6 9.1 9.6 Net block Other Income 103 114 123 132 Capital work in progress Interest expenses 844 931 1,026 1,016 Investment PBT 495 1,203 1,667 2,111 Current Assets Tax 368 -242 550 697 Inventories Effective tax rate (%) 74.3 -20.1 33.0 33.0 Sundry debtors Adjusted PAT 127 1,445 1,117 1,414 -91.0 1,038.5 -22.7 26.6 EBIT EBIT margin (%) Growth (%) Net Margin (%) Cash & bank balance Loans & advances Other current assets 0 8,370 6,466 6,565 Net current assets Misc. exp 1,979 323 474 524 571 Provisions 0 0 0 0 16,272 18,562 18,690 20,748 FY13A FY14A FY15E FY16E EBITDA Margin 8.6 10.6 11.0 11.4 Net Margin 0.7 6.1 4.0 4.5 ROCE 9.4 12.3 14.6 16.0 Total Assets Key Ratios Y/E Mar (Rsmn) PBT (Ex-Other income) Depreciation Interest Provided Chg in working cap Y/E Mar Profitability (%) 0 931 1,026 1,016 810 117 0 0 -1,069 -241 1,497 243 ROE 1.6 16.4 11.3 12.9 -368 242 -550 -697 RoIC 12.9 17.4 21.6 27.2 697 2,228 4,042 3,112 -695 -2,153 -600 -500 EPS 0.8 7.0 7.4 9.3 1 75 3,442 2,612 CEPS 3.0 12.7 10.8 13.1 BVPS 55.0 61.7 68.4 77.0 0.6 0.7 0.6 0.6 241.3 28.8 27.4 21.7 68.1 16.0 18.7 15.4 P/BV 3.7 3.3 3.0 2.6 EV / Sales 2.1 1.6 1.3 1.2 24.4 15.4 12.3 10.8 0.3 0.3 0.3 0.3 0.9 0.8 0.7 0.7 Other Non-Cash items Tax paid Operating Cashflow Capital expenditure Free Cash Flow Other income Per Share Data (Rs) 103 114 123 132 Investments -2,627 174 -1,955 -2,030 DPS Investing Cashflow -3,219 -1,865 -2,433 -2,398 Valuations (x) 29 0 0 0 3,096 1,003 -883 750 Interest Paid -844 -931 -1,026 -1,016 Dividend paid (incl tax) -105 -124 -106 -106 0 0 0 0 EV / EBITDA Equity Capital Raised Loans Taken / (Repaid) Income from investments Others PER P/CEPS 0 0 0 0 Dividend Yield (%) 2,176 -52 -2,015 -373 Gearing Ratio (x) -346 311 -406 341 Net Debt/ Equity Opening cash position 563 218 529 123 Net Debt/EBIDTA Closing cash position 218 529 123 465 Working Cap Cycle (days) Financing Cashflow Net chg in cash Emkay Research 11,152 7,585 1,414 1,545 10,831 16,214 1,117 706 9,707 0 1,062 1,001 697 7,043 15,086 736 FY16E 355 0 Reported PAT FY15E 761 11,717 0 FY14A 8,579 218 0 1,414 0 FY13A 8,123 8,636 1,117 -383 Cash Flow 7,517 Current liabilities 1,445 26.6 1,887 7,782 464 609 1,414 22,779 1,779 16,214 127 -22.7 21,552 1,638 464 E/O items 1,117 20,087 1,022 15,086 Adj. PAT After JVs/Ass/MI 1,445 16,221 464 0 1,038.5 0 9,196 11,717 4.5 0 127 0 7,166 157 4.0 0 -91.0 0 5,210 8,636 6.1 0 Growth (%) 0 5,385 Current lia & Prov 0.7 (Profit)/loss from JVs/Ass/MI PAT after MI FY16E July 2, 2014 4.8 3.2 2.4 2.2 148.5 117.8 79.0 68.4 18 Ashoka Buildcon Scalable with assured growth Your success is our success July 02, 2014 Rating Buy Biggest beneficiary of road projects to be tendered out in 2HFY15E, scalability potential/capacity to bid enhances as secure funding for current and future growth, qualified to bid for a single project worth Rs31.8bn Scale up in the BOT portfolio, revises EPS for FY15E/16E by12%/25% on account of higher order inflow assumption; we have revised target price to Rs162 on earnings roll-forward to FY16E, newer project addition Target Price CMP Rs162 Rs148 EPS Chg FY15E/FY16E (%) 12/25 Target Price change (%) 5 Nifty 7,635 Sensex 25,516 Price Performance (%) 1M 3M 6M 12M Absolute 10 94 109 145 4 71 73 88 Rel. to Nifty Source: Bloomberg Relative price chart Rs % 90 128 64 106 38 84 12 62 -14 40 Jul-13 Well-funded portfolio, sufficient internal cash flows to cater equity requirement, moderately levered vis-à-vis peers (cons. debt equity at 2.45x, standalone debt equity at 0.2x) Previous Reco Buy 150 Sep-13 Nov-13 Dec-13 Ashoka Buildcon (LHS) Mar-14 Apr-14 -40 Jun-14 Rel to Nif ty (RHS) Source: Bloomberg Stock Details Sector Construction ASBL IB Bloomberg 791 Equity Capital (Rs mn) 5 Face Value(Rs) 158 No of shares o/s (mn) 52 Week H/L 155/ 41 Market Cap (Rs bn/USD mn) 23/ 389 Daily Avg Volume (No of sh) 218,834 Daily Avg Turnover (US$mn) 0.4 Shareholding Pattern (%) Mar'14 Dec'13 Sep'13 Promoters 67.6 67.6 67.6 FII/NRI N/A N/A N/A Institutions 17.9 17.9 18.3 Private Corp 6.8 6.8 6.3 Public 7.7 7.8 7.8 Source: Bloomberg Nitin Arora [email protected] +91-22-66242491 Kunal B. Soni [email protected] +91-22- 66242431 Emkay Global Financial Services Ltd. Order backlog provides reasonable EPC earnings visibility Ashoka Buildcon Ltd. (ABL) enjoys a 2.5x (ex-Cuttuck Angul) visibility on FY14 construction revenues, with order backlog of Rs35.4bn. On account of the recently won projects (distribution projects in Bihar worth Rs6.6bn, road project in Karnataka of Rs4.5bn), along with order inflow assumption of Rs24bn in FY15E-16E, we expect construction revenue CAGR of 9.1% over FY14-16E. We believe the exclusion of the Cuttuck-Angul project (not included in the ACL portfolio), which had cost overruns of 810%, provides further scalability to bid for new projects. The company has executed a concession agreement for the KSHIP road project, which is expected to start construction in 2HFY15E. Funding secured for future growth, equity requirement of Rs1bn over the next 2 years The current equity requirement stands at Rs1bn, which needs to be infused over the next 2-3 years. The company needs to pump in Rs400mn in Dhankuni-Kharagpur, Rs280mn in KSHIP road project, Rs100mn in Sambalpur, and Rs300mn in the Chennai ORR project. ABL has received the fourth tranche of investment of Rs1.33bn from SBI Macquarie. ABL’s business ramp-up is ideally complemented by its lucrative cash generating portfolio and strong execution skills, which will ensure that ABL’s transition to a full-scale national level player is smooth with limited dilution. We believe the company remains the biggest beneficiary for re-bidding of contracts, which will be tendered in 2HFY15. Upgraded FY15E-16E earnings estimates on higher construction revenue, increase in margin assumptions We have increased our construction revenue assumption for FY15E/16E by 12%/25% on newer order addition, as well as higher order inflow assumptions over FY14-16E. We have increased earnings estimate for FY15E by 12% on higher EBITDA flow and lower tax outgo. For FY16, we have upgraded earnings estimate by 25%, due to the commissioning of two road projects, as well as higher order inflow. However, we believe, earnings could pan out higher for FY16E, as the company has the requisite strength to take up new orders, which will come from the NHAI by 2HFY15E. (Rsmn) Financial Snapshot (Consolidated) EV/ EPS RoE (Rs) % chg (%) P/E EBITDA P/BV -47.4 9.6 38.3 12.4 2.2 27.7 3.7 30.0 13.5 1.8 6.5 32.6 10.7 22.6 11.4 1.7 5.6 -14.9 8.4 26.6 8.7 1.5 EPS EBITDA YE- Net Mar Sales (Core) (%) APAT FY13A 18,527 3,719 20.1 999 3.9 FY14A 17,949 3,945 22.0 426 4.9 FY15E 23,696 5,525 23.3 1,421 FY16E 25,226 7,763 30.8 1,237 19 Company Update Emkay © Company Update Ashoka Buildcon Exhibit 22: Increased EPS estimate by 20% FY16E FY15E change Earlier Revised change 23,696 2.5% 22,794.0 25,226 10.7% 5,525 1.7% 7,445.0 7,763 4.3% 24% 23% -0.8% 32.7% 30.8% -6% APAT 922 1,033 12.0% 701.0 879 25% EPS 5.84 6.5 12.0% 4.4 5.6 25% Rs Mn Earlier Revised Sales 23,112 5,433 EBIDTA EBIDTA (%) Source: Company, Emkay Research Exhibit 24: BOT Revenue to edge higher Exhibit 23: EPC Revenue to sustain 8.0 20.0 7.0 6.0 15.0 5.0 10.0 18.6 14.8 10.3 5.0 11.4 14.1 17.0 4.2 1.0 1.7 1.9 FY10 FY11 2.6 2.9 2.9 FY12 FY13 FY14E - FY10 FY11 FY12 FY13 FY14E FY15E FY16E 30.0 25.0 20.0 15.0 23.7 10.0 18.5 15.0 25.2 17.9 8.0 0.0 FY10 FY11 FY12 FY16E Exhibit 26: EBITDA CAGR of 40% over FY14-16E Exhibit 25: Revenue CAGR of 18.5% over FY14-16E 13.0 FY15E Source: Company, Emkay Research Source: Company, Emkay Research FY13 FY14E FY15E 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 - FY16E 7.8 5.5 3.3 3.7 3.9 FY12 FY13 FY14E FY15E 19.4 21.7 20.1 22.0 23.3 FY11 FY12 FY13 FY14E FY15E 2.1 2.5 FY10 FY11 FY16E Source: Company, Emkay Research Source: Company, Emkay Research Exhibit 28: Margin to expand Exhibit 27: Earnings CAGR of 6% over FY14-16E 8.0 35.0 7.0 30.0 6.0 25.0 5.0 20.0 4.0 3.0 7.3 3.0 2.0 5.5 5.0 4.0 5.4 6.5 7.3 6.5 2.0 3.9 4.9 15.0 5.6 30.8 26.9 10.0 5.0 1.0 - FY10 FY11 FY12 FY13 Source: Company, Emkay Research Emkay Research July 2, 2014 FY14E FY15E FY16E FY10 FY16E Source: Company, Emkay Research 20 Company Update Ashoka Buildcon Exhibit 29: SOTP fair value @162 Cost of Equity Equity value Stake ABL Value ABL per share/Value Ashoka Concessions Ltd. Dhankuni - Kharagpur 14.0% 6,160.3 100.0% 6,160.3 39.0 Sambhalpur - Baragarh 14% 5,279.9 100.0% 5,279.9 33.4 Belgaum - Dharwad 15% 1,336.7 100.0% 1,336.7 8.5 Pimpalgaon - Nasik 15% (0.6) Value for Under construction projects (334.5) 26.0% (87.0) 12,442.40 0.0% 12,690.0 80.4 Jaora - Naigaon 14% 10,979.6 37.5% 4,117.3 26.1 Durg - Chhattisgarh 14% 1,518.9 51.0% 774.7 4.9 Chhattisgarh - Bhandara 15% 67.3 51.0% 34.3 0.2 Chennai ORR 13% 2,191.7 1,095.8 6.9 27,199.8 11,841.7 80.6 Value of ACL at 66% stake – (b) Indore - Edalabad 14% 2,238.6 100.0% 2,238.6 14.2 Waiganga river Bridge 14% 525.8 50.0% 262.9 1.7 Pune - Shirur 14% 543.4 100.0% 543.4 3.4 Dewas Bypass 14% 718.8 100.0% 718.8 4.6 Katni Bypass 14% 306.8 99.9% 306.4 1.9 A'nagar - Karmala 14% - 100.0% A'nagar - Aurangabad 14% 139.5 100.0% 139.5 0.9 Nasirabad Road ROB 14% - 100.0% Mudhol Maharashtra Road Project 13% 1,575.5 51.0% 803.5 5.1 Sherinallah Bridge 14% 47.6 100.0% 47.6 0.3 Dhule Bypass 14% - 100.0% Anwali Kasegaon - - 5.0% FOBs - Eastern Exp H'way - 6 14% 20.6 100.0% 20.6 0.1 Value for operating projects – (c) 5,081.3 32.2 Total BOT Fair value – (a + b + c) 16,923.1 112.8 16,923 113 Add: Net holding company cash/debt Net Value of BOT Add: EPC valuation Fair value per share 7,786 49 24,708.8 162 Source: Company, Emkay Research Emkay Research July 2, 2014 21 Ashoka Buildcon Company Update Key Financials (Consolidated) Income Statement Balance Sheet Y/E Mar (Rsmn) FY13A FY14A FY15E FY16E Y/E Mar (Rsmn) FY13A FY14A FY15E Net Sales 18,527 17,949 23,696 25,226 Equity share capital 675 939 939 939 23.5 -3.1 32.0 6.5 Reserves & surplus 9,832 11,690 13,111 14,348 14,808 14,003 18,172 17,463 10,507 12,628 14,049 15,286 502 583 814 871 0 0 0 0 482 432 1,028 1,024 Unsecured Loans 3,719 3,945 5,525 7,763 Loan Funds Growth (%) Expenditure Employee Cost Other Exp SG&A EBITDA Net worth Minority Interest Secured Loans FY16E 2,787 4,645 4,296 2,092 23,469 31,032 42,275 45,925 0 0 0 0 23,469 31,032 42,275 45,925 Growth (%) 14.4 6.1 40.0 40.5 Net deferred tax liability 0 0 0 0 EBITDA margin (%) 20.1 22.0 23.3 30.8 Total Liabilities 36,763 48,306 60,620 63,303 Depreciation 1,324 1,389 1,512 2,031 Gross Block 20,275 20,275 56,921 93,567 EBIT 2,395 2,556 4,012 5,732 Less: Depreciation 5,275 6,664 8,176 10,207 12.9 14.2 16.9 22.7 Net block 15,000 13,611 48,745 83,360 Capital work in progress 96,100 106,199 79,253 47,289 EBIT margin (%) Other Income 294 246 246 258 Interest expenses 1,395 1,335 2,441 4,396 Investment 2,824 2,847 3,464 4,135 PBT 1,295 1,467 1,817 1,594 Current Assets 9,672 11,869 13,887 11,811 Tax 685 688 784 715 Inventories 5,399 6,272 5,930 4,911 Effective tax rate (%) 52.9 46.9 43.2 44.8 Sundry debtors 862 1,305 1,797 1,658 Adjusted PAT 609.6 778.7 1032.6 878.9 Cash & bank balance 518 1,205 2,785 1,648 Growth (%) -47.4 27.7 32.6 -14.9 Loans & advances 2,893 3,087 3,376 3,593 Net Margin (%) 3.3 4.3 4.4 3.5 Other current assets 0 0 0 0 (Profit)/loss from JVs/Ass/MI 389 -353 388 358 Current lia & Prov 87,624 87,077 85,584 84,148 Adj. PAT After JVs/Ass/MI 999 426 1,421 1,237 Current liabilities 87,624 87,077 85,584 84,148 E/O items 157 157 0 0 0 0 0 0 1,156 583 1,421 1,237 Net current assets -77,953 -75,208 -71,697 -72,337 Reported PAT Provisions 999 426 1,421 1,237 Misc. exp -19.9 -57.4 233.7 -13.0 Total Assets FY13A FY14A FY15E FY16E PBT (Ex-Other income) 1,451 1,467 1,817 1,594 Profitability (%) Depreciation 1,324 1,389 1,512 2,031 EBITDA Margin Interest Provided 1,395 1,335 2,441 4,396 -85 0 0 0 61,230 -2,107 -1,931 -702 -688 -784 PAT after MI Growth (%) 0 0 0 0 35,971 47,449 59,764 62,448 FY13A FY14A FY15E FY16E 20.1 22.0 23.3 30.8 Net Margin 3.3 4.3 4.4 3.5 ROCE 8.3 6.6 7.8 9.7 -497 ROE 9.6 3.7 10.7 8.4 -715 RoIC -7.3 -4.0 -9.1 -70.1 Cash Flow Key Ratios Y/E Mar (Rsmn) Other Non-Cash items Chg in working cap Tax paid Operating Cashflow Capital expenditure Free Cash Flow Y/E Mar 64,999 1,396 3,055 6,809 -69,694 -7,212 -9,865 -4,833 Per Share Data (Rs) 3.9 4.9 6.5 5.6 -4,695 -5,815 -6,810 1,976 CEPS 14.7 11.5 18.6 20.7 BVPS 66.5 80.0 89.0 96.8 1.3 1.5 1.7 1.5 PER 38.3 30.0 22.6 26.6 P/CEPS 10.1 12.9 8.0 7.1 P/BV 2.2 1.8 1.7 1.5 2.5 3.0 2.7 2.7 12.4 13.5 11.4 8.7 0.9 1.0 1.2 1.0 2.2 2.4 2.8 2.9 6.2 7.6 7.1 5.7 EPS Other income -274 0 0 0 Investments -772 -23 -617 -671 Investing Cashflow -70,740 -7,235 -10,482 -5,504 Equity Capital Raised 11,798 263 0 0 Loans Taken / (Repaid) -4,395 7,563 11,243 3,651 Interest Paid -1,395 -1,335 -2,441 -4,396 Dividend paid (incl tax) 0 0 0 0 EV / Sales Income from investments 0 0 0 0 EV / EBITDA Others 0 35 204 -1,696 Dividend Yield (%) 6,008 6,526 9,007 -2,441 Gearing Ratio (x) 267 688 1,580 -1,136 Net Debt/ Equity Financing Cashflow Net chg in cash DPS Valuations (x) Opening cash position 500 518 1,205 2,785 Net Debt/EBIDTA Closing cash position 767 1,205 2,785 1,648 Working Cap Cycle (days) Emkay Research July 2, 2014 -1,546.0 -1,553.9 -1,147.3 -1,070.5 22 IL&FS Transportation Higher leverage to suppress earnings Your success is our success July 02, 2014 Rating Hold CMP Target Price Standalone leverage to surge higher to 2x, as ITNL pumps in equity (Rs10bn) to complete the projects. High leverage in the absence of meaningful rate cuts to exert pressure on standalone profitability Issue of preference share capital doesn’t address leverage concerns, given the redeemable nature, the debt equity stands at 2.3x/4.48x As leverage surged higher and ITNL earnings highly leveraged to new orders, equity funding gap would still put pressure on balance sheet. Maintain Hold rating, revised target price of Rs221 on roll-forward of earnings to FY16E Rs221 Rs209 EPS Chg FY15E/FY16E (%) NA Target Price change (%) 24 Nifty 7,635 Sensex 25,516 Price Performance (%) 1M 3M 6M 12M Absolute 9 79 55 48 Rel. to Nifty 3 57 29 13 Source: Bloomberg Construction revenue growth intact, but fee income to stagnate Relative price chart Rs % 30 198 16 171 2 144 -12 117 -26 90 Jul-13 Robust order backlog (4x FY13 construction rev) to help a construction income CAGR of 17% over FY14-16E, but a high margin fee income to stagnate, to exert pressure on EBITDA Previous Reco Hold 225 Sep-13 Nov-13 Dec-13 Mar-14 IL&FS Transportation (LHS) Apr-14 -40 Jun-14 Rel to Nifty (RHS) Supported by back-ended FY13 order wins (Rs38bn), ITNL’s order book currently stands at healthy Rs110bn. With robust revenue visibility (4x FY14E construction revenues), we expect the standalone construction revenues to surge at a CAGR of 17% over FY14-16E. ITNL has booked a fee income of Rs6.8bn in FY14, which, we believe, almost completed the entire fee income booking from existing projects. Winning new awards may help ITNL in generating more fee income, but would simultaneously compound balance sheet leverage concerns. The commissioning of Gurgoan Metro, Pune-Sholapur, Narketpally-Addanki and Moradabad-Bareilly projects should increase interest and depreciation costs in the P&L, which would challenge near-term earnings. Source: Bloomberg Leverage to surge higher, putting pressure on standalone profitability Stock Details Sector Construction ILFT IB Bloomberg 2,467 Equity Capital (Rs mn) 10 Face Value(Rs) 247 No of shares o/s (mn) 232/ 93 52 Week H/L Market Cap (Rs bn/USD mn) 52/ 859 Daily Avg Volume (No of sh) 355,070 Daily Avg Turnover (US$mn) 1.0 Shareholding Pattern (%) Mar'14 Dec'13 Sep'13 Promoters 72.5 72.5 72.5 FII/NRI 4.9 4.9 3.4 Institutions 2.5 2.9 3.1 Private Corp 6.8 7.0 7.4 13.4 12.7 13.7 Public Source: Bloomberg Nitin Arora [email protected] +91-22-66242491 Kunal B. Soni [email protected] +91-22- 66242431 Emkay Global Financial Services Ltd. Due to a lower contribution of fee income to the overall revenue, we see ITNL resorting to taking further debt on the standalone book to infuse equity requirements towards funding its new projects. Hence, we see a surge in debt on the standalone balance sheet from Rs46.2bn (debt equity of 1.55x) in FY14 to Rs55bn (debt equity of 1.98x) by FY16E, which would lead to a further deterioration in its leverage ratios, which, in turn, would increase the interest burden on ITNL. In order to address the balance sheet concerns, the company has so far issued three tranches of preference shares, totaling 376.45mn shares or Rs7.5bn in FY14. Given their compulsorily redeemable nature, we believe it to be more like debt than equity. ITNL reported FY14 standalone/consolidated leverage at 1.55/3.76x; however, if preference shares are treated as debt, then leverage would have been 2.29/4.48x, respectively. However, in case leverage increases further, it would become essential for the company to maintain its EBITDA at Rs5bn and Rs5.5bn in FY15E and FY16E excluding other income respectively, to service interest costs at the standalone level. (Rsmn) Financial Snapshot (Consolidated) YE- Net EBITDA EPS EPS RoE Mar Sales (Core) (%) APAT (Rs) % chg (%) FY13A 66,449 18,446 FY14A 65,870 18,953 27.8 5,244 27.0 5.5 16.6 28.8 4,686 8.2 -69.6 10.8 FY15E 71,929 21,570 30.0 3,644 6.4 -22.2 7.2 FY16E 73,314 23,931 32.6 4,243 7.4 16.4 8.1 EV/ P/E EBITDA P/BV 7.7 9.8 1.1 25.5 15.9 2.4 32.8 13.8 2.3 28.1 12.6 2.2 23 Company Update Emkay © Company Update IL&FS Transportation Exhibit 30: SOTP Fair value at Rs221/share Holding SPV Valuation Measure Disc rate Equity Value (Rs mn) Stake Value (Rs mn) Value/ Share 31.2 BOT Gujarat Road and Infrastructure company ltd WGEL Delhi - Noida Gomti - Beawar RIDCOR RIDCORII 83.6% Operational FCFE 13% 9,212.9 7,702.9 100.0% Operational FCFE 13% 2,021.3 2,021.3 8.2 25.4% Operational FCFE 13% 8,653.6 2,193.7 8.9 100.0% Operational FCFE 13% 4,167.6 4,167.6 16.9 50.0% Operational FCFE 13% 10,164.0 5,082.0 20.6 50.0% Under development FCFE 14.50% 4,475.9 2,237.9 9.1 100.0% Under Construction FCFE 14.50% 4,722.0 4,722.0 19.1 Chadrapur Warora Road Project 35.0% Under development FCFE 14.50% 1,997.6 699.1 2.8 Narkatapally to Addanki Road Project 50.0% Under development FCFE 14.50% 3,949.7 1,974.8 8.0 Moradabad Bareili Road Project 100.0% Under development FCFE 14.50% 8,416.4 8,416.4 34.1 Kharagpur - Baleshwar Pune Sholapur NH-9 Road Project 100.0% Under development FCFE 14.50% 1,089.7 1,089.7 4.4 Kiratpur Ner Chowk 100% Under development FCFE 14.50% 8,238.2 8,238.2 33.4 Sikar Bikaner 100% Under development FCFE 14.50% 2,525.9 2,525.9 10.2 Khed Sinnar 100% Under development FCFE 14.50% 730.1 730.1 3.0 Barwa adda panagarh 100% Under development FCFE 14.50% 1,209.3 1,209.3 4.9 Toll Projects - (A) 71,574.1 53,011.1 215 North Karnataka expressway ltd Road Project 94% Operational FCFE 13% 1,356.5 1,268.3 5.1 Thiruvananthpuram Road Development Company Ltd Road Project 50% Operational FCFE 13% -301.0 -150.3 -0.6 Andhra Pradesh expressway ltd Road Project 100% Operational FCFE 13% -584.8 -584.8 -2.4 East Hyderabad expressway ltd Road Project 74% Under Construction FCFE 13% 783.3 579.7 2.3 Hyderabad Ring Road 26% Under Construction FCFE 13% 76.9 20.0 0.1 Hazaribaug Ranchi expressway ltd Road Project 74% Under Construction FCFE 14% 599.7 443.8 1.8 Jharkhand - Ph - I Road Project 100% Under Construction FCFE 14% 204.0 204.0 0.8 Jharkhand Ph - II Road Project 100% Under development FCFE 14% 193.8 193.7 0.8 Shillong Jorbat Road Project 50% Under development FCFE 14% 1,807.6 903.8 3.7 Chenani Nashri Road Project 100% Under development FCFE 14% 4,081.7 4,081.7 16.5 14% 8,217.7 6,959.8 28.2 Annuity Projects - (B) Vansh Nimay infraprojects Limited Operational FCFE 14% 301.6 301.5 1.2 ITNL ENSO Rail system limited 100% 70% Under Construction FCFE 14% 4,332.4 3,032.6 12.3 MP Check post 51% Under development BV 1x 1,174.2 YuHe Project - Chonguin Road project 49% Opeartional BV 1x Urban Infra Projects - '(C) Investments in Elsamax 100% BV 5,808.2 5,978.3 24.2 1.0x 11.0 2,722.2 11.0 1,109.3 1,109.3 4.5 1,120.4 3,831.6 15.5 18,960 18,960 76.9 18,960.4 18,960.4 76.9 Other Subsidiaries - (D) EV/EBITDA Construction business - (E) 4.8 6.0 14% Investments in other Companies E&C business 1,174.2 1,470.0 3.5x Net Debt at parent levels -34,309 -34,309 -139 Total Value (A+B+C+D+E) 71,372.1 54,432.6 221 Source: Company, Emkay Research Emkay Research July 2, 2014 24 IL&FS Transportation Company Update Key Financials (Consolidated) Income Statement Balance Sheet Y/E Mar (Rsmn) FY13A FY14A FY15E FY16E Y/E Mar (Rsmn) FY13A FY14A FY15E Net Sales 66,449 65,870 71,929 73,314 Equity share capital 1,943 5,707 5,707 5,707 18.5 -0.9 9.2 1.9 Reserves & surplus 34,456 44,331 45,689 47,647 48,003 46,918 50,359 49,383 Net worth 36,398 50,038 51,397 53,354 Employee Cost 3,819 4,142 4,672 4,758 Minority Interest 2,716 3,727 3,998 3,193 Other Exp 2,016 2,016 2,016 2,016 Secured Loans Unsecured Loans Growth (%) Expenditure SG&A EBITDA 4,483 6,206 6,182 5,963 18,446 18,953 21,570 23,931 Loan Funds FY16E 135,931 178,764 128,757 124,314 8,522 10,262 52,649 63,080 144,453 189,026 181,407 187,394 Growth (%) 25.9 2.7 13.8 10.9 Net deferred tax liability EBITDA margin (%) 27.8 28.8 30.0 32.6 Total Liabilities 185,992 244,782 238,792 245,932 Gross Block 175,342 231,423 223,840 227,097 Depreciation EBIT 944 1,510 1,896 2,543 17,502 17,442 19,675 21,388 26.3 26.5 27.4 29.2 EBIT margin (%) Other Income Less: Depreciation Net block 1,414 2,154 2,396 2,664 11,190 14,710 16,476 19,141 PBT 7,726 4,887 5,595 4,912 Current Assets Tax 2,274 266 1,678 1,473 Inventories 29.4 5.4 30.0 30.0 5,244 4,686 3,644 4,243 Cash & bank balance 1.2 -15.2 -15.3 -12.2 Loans & advances Interest expenses Effective tax rate (%) Adjusted PAT Growth (%) Capital work in progress Investment Sundry debtors 2,425 5,356 1,990 6,866 1,990 8,762 1,990 11,305 169,986 224,557 215,079 215,792 0 0 0 0 6,871 4,691 4,738 4,975 28,985 42,005 45,811 51,354 169 172 311 311 7,517 9,875 13,222 15,322 4,252 6,828 2,506 4,750 14,170 20,763 22,894 23,019 Net Margin (%) 8.2 7.0 5.4 4.7 Other current assets 2,877 4,368 6,878 7,952 (Profit)/loss from JVs/Ass/MI 208 -65 272 -805 Current lia & Prov 19,911 26,546 26,909 26,263 Adj. PAT After JVs/Ass/MI 5,244 4,686 3,644 4,243 Current liabilities 23,594 0 0 0 0 Reported PAT 5,244 4,686 3,644 PAT after MI 5,244 4,686 5.5 -10.6 FY13A 17,297 23,573 24,240 Provisions 2,614 2,973 2,669 2,669 4,243 Net current assets 9,075 15,459 18,901 25,091 3,644 4,243 Misc. exp 0 0 0 0 -22.2 16.4 FY14A FY15E FY16E 7,726 4,887 5,595 4,912 Profitability (%) 944 1,510 1,896 2,543 EBITDA Margin 11,190 14,710 16,476 19,141 0 0 0 0 5,497 -3,809 -7,764 Tax paid -2,274 -266 Operating Cashflow 23,083 17,032 Capital expenditure -47,846 -53,039 Free Cash Flow -24,763 -36,007 E/O items Growth (%) Cash Flow Total Assets Key Ratios Y/E Mar (Rsmn) PBT (Ex-Other income) Depreciation Interest Provided Other Non-Cash items Chg in working cap Other income Investments Investing Cashflow Loans Taken / (Repaid) Interest Paid Y/E Mar Net Margin FY15E FY16E 27.8 28.8 30.0 32.6 8.2 7.0 5.4 4.7 ROCE 11.8 9.1 9.1 9.9 -3,945 ROE 16.6 10.8 7.2 8.1 -1,678 -1,473 RoIC 11.6 8.6 8.5 9.1 14,524 21,177 Per Share Data (Rs) 7,583 -3,257 EPS 27.0 8.2 6.4 7.4 22,107 17,920 CEPS 31.9 10.9 9.7 11.9 BVPS 187.4 87.7 90.1 93.5 3.4 3.8 0.0 0.0 PER 7.7 25.5 32.8 28.1 P/CEPS 6.6 19.3 21.6 17.6 P/BV 1.1 2.4 2.3 2.2 EV / Sales 2.7 4.6 4.1 4.1 0 0 0 2,180 -47 -237 -50,763 -50,859 7,536 -3,494 0 8,481 0 0 41,332 44,574 -7,620 5,988 -11,190 -14,710 -16,476 -19,141 -786 -2,286 -2,286 -2,286 0 0 0 0 EV / EBITDA 9.8 15.9 13.8 12.6 1.6 1.8 0.0 0.0 3.9 3.6 3.5 3.4 Income from investments Others DPS Valuations (x) -262 343 0 0 Dividend Yield (%) 29,094 36,402 -26,381 -15,439 Gearing Ratio (x) 1,414 2,575 -4,321 2,244 Net Debt/ Equity Opening cash position 2,838 4,252 6,828 2,506 Net Debt/EBIDTA Closing cash position 4,252 6,828 2,506 4,750 Working Cap Cycle (days) Net chg in cash FY14A 0 Dividend paid (incl tax) Financing Cashflow FY13A -2,917 Equity Capital Raised Emkay Research 185,932 244,707 238,718 245,858 July 2, 2014 7.6 9.6 8.3 7.6 26.5 47.8 83.2 101.3 25 Construction Sector Update Emkay Global Financial Services Ltd. 7th Floor, The Ruby, Senapati Bapat Marg, Dadar - West, Mumbai - 400028. India Tel: +91 22 66121212 Fax: +91 22 66121299 Web: www.emkayglobal.com DISCLAIMER: Emkay Global Financial Services Limited and its affiliates are a full-service, brokerage, investment banking, investment management, and financing group. We along with our affiliates are participants in virtually all securities trading markets in India. Our research professionals provide important input into our investment banking and other business selection processes. Investors may assume that Emkay Global Financial Services Limited and/or its affiliates may seek investment banking or other business from the company or companies that are the subject of this material and that the research professionals who were involved in preparing this material may participate in the solicitation of such business. Our salespeople, traders, and other professionals may provide oral or written market commentary or trading strategies to our clients that reflect opinions that are contrary to the opinions expressed herein, and our proprietary trading and investing businesses may make investment decisions that are inconsistent with the recommendations expressed herein. In reviewing these materials, you should be aware that any or all of the foregoing, among other things, may give rise to real or potential conflicts of interest. Additionally, other important information regarding our relationships with the company or companies that are the subject of this material is provided herein. This report is not directed to, or intended for distribution to or use by, any person or entity who is a citizen or resident of or located in any locality, state, country or other jurisdiction where such distribution, publication, availability or use would be contrary to law or regulation or which would subject Emkay Global Financial Limited or its group companies to any registration or licensing requirement within such jurisdiction. Specifically, this document does not constitute an offer to or solicitation to any U.S. person for the purchase or sale of any financial instrument or as an official confirmation of any transaction to any U.S. person unless otherwise stated, this message should not be construed as official confirmation of any transaction. No part of this document may be distributed in Canada or used by private customers in United Kingdom. All material presented in this report, unless specifically indicated otherwise, is under copyright to Emkay. None of the material, nor its content, nor any copy of it, may be altered in any way, transmitted to, copied or distributed to any other party, without the prior express written permission of Emkay. All trademarks, service marks and logos used in this report are trademarks or registered trademarks of Emkay or its Group Companies. The information contained herein is not intended for publication or distribution or circulation in any manner whatsoever and any unauthorized reading, dissemination, distribution or copying of this communication is prohibited unless otherwise expressly authorized. Please ensure that you have read “Risk Disclosure Document for Capital Market and Derivatives Segments” as prescribed by Securities and Exchange Board of India before investing in Indian Securities Market. In so far as this report includes current or historic information, it is believed to be reliable, although its accuracy and completeness cannot be guaranteed. Emkay Research July 2, 2014 26 www.emkayglobal.com
© Copyright 2024 ExpyDoc