* IN THE HIGH COURT OF DELHI AT NEW DELHI % Order

*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Order delivered on: March 04, 2014
+
O.M.P. No.705/2012
UNION OF INDIA
Through
.....Petitioner
Mr.Ruchir Mishra, Adv. with
Mr.Mukesh Kr.Tiwari,Adv
versus
M/S GUPTA CONSTRUCTION CO AND ANR. ....Respondents
Through
Mr.Vinit Trehan, Adv. with
Ms.Sarika Goel, Adv. for R-1
CORAM:
HON'BLE MR. JUSTICE MANMOHAN SINGH
MANMOHAN SINGH, J. (ORAL)
I.A. No.13972/2012 (for condonation of delay in filing the objection
petition) & I.A. No.13973/2012 (for condonation of delay in re-filing the
objection petition)
1.
By way of present application under Section 34 of Arbitration and
Conciliation Act, 1996 (hereinafter referred to as “the Act”) the petitioner
has assailed award dated 6th May, 2011 passed by the learned Arbitrator for
setting aside the arbitral award.
2.
The brief facts which led to the filing of present application were as
under :(i)
The petitioner invited the tender for the work of Aesthetic
improvement of Bungalows under “I” Division during 20062007 with an estimated cost of Rs.75,59,928/- tender was
opened on 6th January, 2007.
OMP No.705/2012
Page 1 of 8
(ii)
The respondent was declared to be the lowest bidder and after
the negotiations with Chief Engineer (NDZ-I), CPWD, the
respondent was awarded the contract for the amount of
Rs.1,08,92,127/- vide agreement. The gross amount of work
done by the respondent under this agreement amount to
Rs.1,87,76,340/-. The said amount was paid in seven
installments
as
and
when
running
bills
along
with
measurements received in the Division Office for payment. The
7th and final bill was paid to the respondent on 6th November,
2008.
(iii)
The respondent invoked Clause 25 of the agreement and
requested Chief Engineer for appointment of arbitrator for
adjudication of disputes.
(iv)
The learned Arbitrator directed the respondent to file the
statement of facts in respect of his claims within 15 days from
the date of receipt of notice dated 1st January, 2009 and also
directed the petitioner to file their counter statement of facts
within 30 days of the receipt of the statement of facts from the
respondent and the date of hearing was fixed on 9th October,
2009.
(v)
On 9th October, 2009, respondent neither filed the statement of
facts nor appeared before the learned Arbitrator. Accordingly,
the learned Arbitrator passed an order dated 9th October, 2009,
giving another opportunity to the respondent with the directions
to file statement of facts by 15th November, 2009 and fixed the
next date of hearing as 18th November, 2009.
OMP No.705/2012
Page 2 of 8
(vi)
On 18th November, 2009, the respondent neither filed the
statement of facts nor appeared before the learned Arbitrator.
Consequently, the learned Arbitrator vide its order dated 20th
November, 2009 terminated the case under Section 25 (a) of the
Act.
(vii) Thereafter, the respondent filed petition under Section 15 of the
Act with the prayer for appointment of an arbitrator or
alternatively for appointment of a fresh arbitrator for
adjudication of disputes. Vide order dated 20th May, 2010, this
court set aside the order dated 20th November, 2009 passed by
the learned Arbitrator and simultaneously directed the
Arbitrator to issue fresh notice of hearing to both the parties and
thereafter, proceed to decide the matter on merits in accordance
with the law.
(viii) In compliance of the orders dated 20th May, 2009 passed by this
court, the learned Arbitrator issued fresh notice dated 25th June,
2010 directing the respondent to submit the statement of facts
and claims within 20 days from the date of issue of the notice
and also directed the petitioner to file counter statement of the
facts within 30 days of the receipt of the statement of the facts
from the respondent. The respondent filed statement of facts
and after filing the statement of facts, the respondent filed
another
application
before
the
learned
Arbitrator
for
amendment in the amount under Claim No.3 stating that by
advertence or otherwise or by means of typographic error in
Claim No.3, the respondent claimed a sum of Rs.6,25,000/- on
account of wrongful sanction of rates of various extra items
OMP No.705/2012
Page 3 of 8
whereas, the correct amount which should have been claimed is
Rs.36,35,000/-.
(ix)
On 9th March, 2011, the petitioner submitted the counter
statement of facts before the learned Arbitrator.
(x)
On 6th May, 2011, the sole arbitrator signed the award on the
non judicial stamp paper and awarded Rs.18,26,490/- to the
respondents against all their claims and simple interest as
awarded under para 7.1 of claim No.5 which was received by
the petitioner on 9th May, 2011.
(xi)
The objections under Section 34 of the Act challenging the
award before the District Judge, Delhi, on 5th August, 2011
within the period of 90 days. After filing the objections, the
respondent No.1 filed an application under Order VII rule 10
CPC raising objections that the claim made by the respondent
No.1 before the Arbitrator was more than Rs.20 lacs although
the respondent No.1 was awarded less than a sum of Rs.20 lacs.
Thus, the Additional District Judge had no jurisdiction to
entertain the petition filed by the petitioner under Section 34 of
the Act.
While accepting the contention of the respondent
No.1, who relied upon the decision of this Court in the case of
Union of India vs. S.R. Construction Company & Anr., 207
(4) Arb.CR 141 (Delhi), the Court opined that it has no
pecuniary jurisdiction to entertain the petition and order was
passed to return the petition to the petitioner to be filed before
the Court of competent jurisdiction on furnishing the certified
copy of the same on the court record.
OMP No.705/2012
Page 4 of 8
3.
An oral statement was made by the learned counsel for the petitioner
that date may be fixed directing the parties to appear before the court of
competent jurisdiction for which no objection was raised by the learned
counsel appearing on behalf of the respondent No.1.
In view thereof,
direction was passed by the Additional District Judge on 27 th March, 2012 to
appear before the Registrar General of this Court on 7th May, 2012 at 10:30
am.
4.
The contention of the petitioner is that there was bonafide belief and
impression that the relevant record would be transmitted to this court well
before 7th May, 2012 and upon appearance of both the parties, the Registrar
General will fix the matter for further proceedings. However, when the
petitioner through counsel appeared before the Registrar General, it was
revealed that the record from the District Court was not transmitted to this
Court. Accordingly, the petitioner filed the present OMP on 11 th May, 2012
after obtaining the certified copy. The Registry raised certain objection with
regard to the filing of objections without application for condonation of
delay.
The certified copy of Section 34 petition of District Court was
obtained by the petitioner on 7th April, 2012.
5.
Admittedly the original objections were filed within three months
from the date of receipt of copy of the award. The delay has happened due
to misunderstanding by the petitioner for the reasons stated above and in
view thereof, four days’ day has happened even after the expiry of 30 days.
It is a matter of fact that after raising of objections by the Registry, the
petitioner subsequently filed an application for condonation of delay of 46
days in re-filing the petition.
OMP No.705/2012
Page 5 of 8
6.
The explanation given in the second application is that the delay in re-
filing has occurred on account of time consumed in procuring documents,
arbitral record and preparing needful applications and completing other
formalities as well as administrative formalities in approving the
applications for filing before this court.
So the prayers in both the
applications are made that the delay of four days in filing the petition be
condoned and in the second application, delay of 46 days delay in re-filing
be condoned.
7.
Both the applications are opposed by the respondent No.1.
8.
Learned counsel for the respondent No.1 states that the objections
under Section 34 ought to have been filed before this Court after passing the
order dated 27th March, 2012 and since the same are not filed within the
time, the objections are liable to be dismissed.
Learned counsel for the respondent No.1 has referred to the decision
in the case of Union of India vs. M/s. Harbhagwan Harbhajan Lal, 2010
(6) R.A.J. 310 (Del), in which the decision of the Supreme Court in Union of
India vs. M/s. Popular Construction Co., AIR 2011 SC 4010 had been
discussed. Counsel states that delay in filing the objections under Section 34
cannot be condoned and even delay of re-filing is not liable to be condoned
as there is no bonafide on the part of the petitioner to file the objections
before this Court.
9.
After considering the entire gamut of the matter, it emerges that
admittedly the objections under Section 34 were filed before the District
Judge, Delhi, within the period of 90 days. It is not in dispute that on the
objection raised by the respondent No.1, the learned Additional District
OMP No.705/2012
Page 6 of 8
Judge has come to the conclusion that the court has no pecuniary jurisdiction
to entertain the objections and order was passed on 27 th March, 2012 to the
effect that the petition be returned to be filed before the Court of competent
jurisdiction. But at the same time, it was agreed by the parties to appear
before the High Court on 7th May, 2012. On 7th May, 2012, when the matter
was not listed before the Registrar General of this Court, on enquiry it came
to the notice of the learned counsel for the petitioner that the record has not
been received nor was filed by the petitioner.
10.
It appears to the Court that the grounds taken by the petitioner are
bonafide and the benefit of delay would go in favour of the petitioner. It is
not dispute that the original objections under Section 34 were filed in time.
As far as re-filing is concerned, in Delhi Development Authority vs. M/s.
Durga Construction Co., 2014 (1) R.A.J. 490 (Del.), the Division of this
Court has come to the conclusion that the aspect of re-filing has to be
considered as per its own merit. In view of the statement made in the
application for condonation of delay in re-filing, I am of the considered view
that the reasons given in the said application are sufficient to condone the
said delay.
11.
It is manifest that the petitioner has been pursuing its remedy with all
diligence without avoiding any delay. The original objection rather was
filed within the prescribed period of three months. Thus, there was not even
a single day delay in challenging the Award. It is different matter if some
delay has happened on returning the petition on account of lack of pecuniary
jurisdiction and to refile the same in this court. At the best the said delay of
few days is to be considered as delay in re-filing and an advantage cannot be
derived by the respondent for such a delay when the objection under Section
OMP No.705/2012
Page 7 of 8
34 are filed in time. No doubt the court has to consider the application for
condonation of delay in refilling as per its own merit and incase the
petitioner is able to make out a case by establishing a case of sufficient
cause, the same can be considered in view of observation made by the
Division Bench in the case of Durga Construction (Supra).
12.
Thus, there is no force in the submission of respondent that such delay
even one day in filing the petition if returned for want of pecuniary
jurisdiction is to be considered and treated in the same manner when the
main objections under Section 34 are filed.
13.
Thus, the prayers made in both the applications are allowed. The
delay in filing as well as in re-filing the petition is condoned.
14.
The applications are disposed of.
O.M.P. No.705/2012 & I.A. No.13971/2012 (for stay)
List on 28th April, 2014.
MANMOHAN SINGH, J.
MARCH 04, 2014/jk
OMP No.705/2012
Page 8 of 8