Many to Many Standard Capacity Product Availability Calculation

Many to Many: Standard Capacity
Product (SCP) Availability
Calculations
Radha Madrigal
Customer Service Department
August 18, 2014
Agenda
•
•
•
•
•
Background
New outage classifications in OMS
Sample outages for RA resources
Changes to RAAM
New variables for settlements & billing
Page 2
ISO PUBLIC © 2014 CAISO
Background
Page 3
ISO PUBLIC © 2014 CAISO
Many to Many Initiative Timeline
• Fall 2014 – October 1, 2014
– Many to Many: SCP Availability Calculations
– (to coincide with OMS activation)
• Spring 2015 – Maintenance Release
– Many to Many Substitution/App Consolidation
ISO PUBLIC © 2014 CAISO
Standard Capacity Product (SCP) Availability
Calculations
• The ISO reviews the availability of each Resource
Adequacy (RA) resource subject to SCP each month to
determine whether it meets the applicable availability
standard
• With the introduction of the Outage Management System
(OMS), newly defined outage categories impact the
settlement of SCP
• Outage MWs associated with approved forced outages
that are not subject to SCP shall be exempted within the
SCP pre-calculation configuration
Page 5
ISO PUBLIC © 2014 CAISO
New Outage Classifications in OMS
Page 6
ISO PUBLIC © 2014 CAISO
New Fields in OMS
• Opportunity
– Off Peak Opportunity
– Short Notice Opportunity
• SCP Exempt Flag
– The exempt MW capacity is not part of the availability
assessment
– Automatically set in OMS based on business rules
• Nature of Work
ISO PUBLIC © 2014 CAISO
When is the SCP Exempt Flag Set?
Outage Type
Difference between
date of outage
submission and
planned start date/time
of outage *
SCP Exempt Flag is set
Forced
4-7 calendar days
Yes
Forced
3 calendar days or less
No
Planned
N/A
No
(*excluding the date outage was submitted and planned start date of outage)
Page 8
ISO PUBLIC © 2014 CAISO
Forced Outage Types
Outage Type
Does Curtailment reduce Availability MW Is Curtailment MW considered Exempt
in SCP Availability Calculation?
MW in Calculation?
Nature of Work
Environmental Restrictions
Transmission Induced
Plant Maintenance
Plant Trouble
Ambient Due to Temperature
Ambient Not Due to
Temperature
Power System Stabilizer (PSS)
AVR/Exciter
Unit Testing
Metering/Telemetry
RTU/RIG
ICCP
Transitional Limitation
Unit Cycling
Unit Supporting Startup
Use Limit Reached
Unit Pre Commercial Testing
N
N
Y
Y
Y
N
N
N
N
N
N
N
Y
Y
Y
Y
Y
N
N
Y
N
N
Y
N
N
N
N
N
N
N
N
N
N
N
N
N
N
Y
Y
Y
Flag Type
Short Notice Opportunity Flag
Off Peak Opportunity Flag
SCP Exempt Flag
ISO PUBLIC © 2014 CAISO
Sample Outages for RA Resources
Page 10
ISO PUBLIC © 2014 CAISO
Weighted Average Calculation
Outage
OF1
Total (per outage):
Final Curtailment
(weighted average): OF1
RESOURCE
RESA
Outage Type
Forced
Pmax
100
RA
Obligation Curtailment
100
50
Forced
100
100
MWMinutes Minute
60
3000
60
3000
50
Availability Exempt
(MW)
(MW)
50
0
• RAAM will report 50 MW of availability for this hour
Page 11
ISO PUBLIC © 2014 CAISO
Overlapping Outages & SCP Exempt
• Two outages for the same hour and resource
Outage
Outage Type
OF1
Forced
OF2 (Exempt) Forced
Total (per outage): OF1
Total (per outage): OF2 (Exempt)
Final Curtailment
(weighted average): OF1
Forced
Final Curtailment
(weighted average): OF2 (Exempt) Forced
RESOURCE
RESA
Pmax
100
100
RA
Obligation Curtailment Minutes
100
50
60
100
50
60
60
60
100
100
50
100
100
50 <-SCP exempt MW
MWMinute
3000
3000
3000
3000
Availability Exempt
(MW)
(MW)
50
50
• RAAM will report 50 MW of availability and 50 exempt
MW for this hour
Page 12
ISO PUBLIC © 2014 CAISO
Changes to Resource Adequacy Availability
Management (RAAM)
Page 13
ISO PUBLIC © 2014 CAISO
Changes to RAAM
• The Resource Adequacy Availability Management
(RAAM) application was updated to accommodate the
new outage classifications in the Outage Management
System (OMS)
• New rules engine for SCP availability calculation
• Old rules engine still available for historic data
• User interface changes for SCP calculations and CPM
calculations
Page 14
ISO PUBLIC © 2014 CAISO
Query SCP Calculations
• Select New SCP Calculation checkbox to display run
output for the new SCP availability calculation engine
• Enter start date and end date
• Select the checkbox next to Resources “All” or select
specific resources from the multi-select box
• Click Query to view the calculations
Page 15
ISO PUBLIC © 2014 CAISO
SCP Calculations – Outages Tab
• Details related to the resource outage
• Asterisks identify outages excluded due to outage
correction
Page 16
ISO PUBLIC © 2014 CAISO
SCP Calculations – Details Tab
• Parameters related to resource availability
Page 17
ISO PUBLIC © 2014 CAISO
SCP Calculations – Values Tab
• Resource level information that is used for settlements
purposes
• Shows final availability and the exempt MW at the
resource-hour granularity, that will be used for SCP
settlements
Page 18
ISO PUBLIC © 2014 CAISO
Query CPM Calculations
• Select New CPM Calculation checkbox to display run
output for the CPM availability calculation
• Enter start date and end date
• Select the checkbox next to Resources “All” or select
specific resources from the multi-select box
• Click Query to view the calculations
Page 19
ISO PUBLIC © 2014 CAISO
CPM Calculations – Outages Tab
• Details related to the resource outage
• Asterisks identify outages excluded due to outage
correction
Page 20
ISO PUBLIC © 2014 CAISO
CPM Calculations – Details Tab
• Parameters related to resource availability
Page 21
ISO PUBLIC © 2014 CAISO
CPM Calculations – Values Tab
• Resource level information that is used for settlements
related purposes.
• Shows Final Planned and Forced Availability at the
resource-hour granularity, that will be used for CPM
settlements
Page 22
ISO PUBLIC © 2014 CAISO
New Variables for Settlements & Billing
Page 23
ISO PUBLIC © 2014 CAISO
BPM Configuration Guide: Standard Capacity Product
Pre-calculation (Schedule)
• Updated version of the configuration guide is going
through change management process
• Proposed changes can be accessed under PRR 752
• Will be discussed at BPM stakeholder meeting on
August 26th
ISO PUBLIC © 2014 CAISO
BPM Configuration Guide: Standard Capacity Product
Pre-calculation (Updated Business Rules)
• SCP exempt capacity MWs shall not be subject to SCP
Non-Availability Charges and Availability Payments.
• A resource’s MW Capacity entered into a grandfathered
contract as specified in Tariff Section 40.9.2(2) & (3) shall
be treated as SCP exempt capacity.
•
Outage MW Capacity associated with an RA
maintenance outage or short-notice opportunity outage
that is approved as a forced outage not subject to SCP
shall be treated as SCP exempt capacity.
Page 25
ISO PUBLIC © 2014 CAISO
New Input Variable Name
• BARAResourceOutageExemptQuantity BrtF’S’mdh
• Outage Exempt Quantity represents the RA Capacity
exempt from SCP due to:
– RA Maintenance outage
– Off-Peak Opportunity RA Maintenance Outage
– Short Notice Opportunity Outage
Page 26
ISO PUBLIC © 2014 CAISO
New Output Variable Name
• BAHourlyRAResourceSCPCapacityNonExemptQuan
tity BrtF’S’mdh
– Eligible Capacity that is not exempted
• Replaces the following:
BAHourlyRAResourceSCPCapacityNotGrandfatheredQu
antity BrtF’S’mdh
– Eligible capacity that is not grandfathered by
Business Associate B and resources r and Resource
Type t
Page 27
ISO PUBLIC © 2014 CAISO
Questions?
• [email protected]
• Updated RAAM user guide:
http://www.caiso.com/Documents/ResourceAdequacyAv
ailabilityManagementDraftToolUserGuide_MarketParticip
ants.pdf
• Additional Training Opportunity:
Fall 2014 Release Settlements Training on August 27th
ISO PUBLIC © 2014 CAISO
Appendix
Page 29
ISO PUBLIC © 2014 CAISO
Overlapping Forced Outages
Outage Type
Forced
Forced
Ambient due to Temp
(counted for availability)
Ambient due to Temp
(counted for availability)
SNOO
SNOO
Planned
Planned
Pmax
100
100
RA
Obligation Curtailment Minutes
100
15
30
100
20
30
100
100
0
15
0
100
100
100
100
100
100
100
100
100
100
10
10
15
0
10
45
15
45
42
18
60
60
60
60
450
150
675
0
180
1050
450
825
180
OF1
Forced
100
100
17.5
OF2
Nature of work
100
100
7.5
OF3
SNOO
100
100
13.75
OP1
Planned
100
100
3
Outage
OF1
OF1
OF2
Total (per outage):
Total (per outage):
Total (per outage):
Total (per outage):
Final Curtailment
(weighted average):
Final Curtailment
(weighted average):
Final Curtailment
(weighted average):
Final Curtailment
(weighted average):
OF2
OF3
OF3
OP1
OP1
OF1
OF2
OF3
OP1
RESOURCE
RESA
MWMinute
450
600
Availability Exempt
(MW)
(MW)
75
13.75
Page 30